Displaying reports 78741-78760 of 79123.Go to page Start 3934 3935 3936 3937 3938 3939 3940 3941 3942 End
Reports until 16:31, Wednesday 08 December 2010
H2 INS
cheryl.vorvick@LIGO.ORG - posted 16:31, Wednesday 08 December 2010 (404)
H2 Deinstall: removal of plumbing between chiller closet and TCS table
- Zach, Rodney, Cheryl

Removed plumbing, including all copper pipe and hoses, between the H2 TCS tables and the chiller closets.  Tables are only tethered by the card access system, since H1 and H2 TCS enclosures are tied together to one card-swipe box.
H2 INS
dani.atkinson@LIGO.ORG - posted 16:05, Wednesday 08 December 2010 (403)
Ops Day Shift Summary
  • HAM7 was closed up and the clean room moved over to cover HAM12 in preparation for tomorrow's dirty work.
  • NSF tours were taken through the LVEA.
  • Cheryl dismantled some of the TCS plumbing, leading to some minor leaks of propylene glycol, which were cleaned up.
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:58, Wednesday 08 December 2010 (402)
Kobelco "Alert" bogus
The Corner Station purge air compressor (Kobelco) has had a "Service Alert" ever since the power glitch a few days ago. The PLC memory battery failed and the various service parameters have defaulted to initial (not applicable) values.  Operationally, the purge air is fine. 
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:54, Wednesday 08 December 2010 (401)
HAM7 doors
Kyle, Corey, Joe, Chris -> Hung West and East doors on HAM7
LHO FMCS
mark.lubinski@LIGO.ORG - posted 09:00, Wednesday 08 December 2010 (400)
site inspection
Annual site septic field inspection.
Drain field was rotated
LHO FMCS
mark.lubinski@LIGO.ORG - posted 07:57, Wednesday 08 December 2010 (399)
X mid roll up door
X-mid door installed not complete
H2 General
jonathan.berliner@LIGO.ORG - posted 17:14, Tuesday 07 December 2010 (398)
Ops Day Log
Major work:
- NSF Review Begins...Tour scheduled for 1330
- HAM7 passive stack extraction
- aLIGO Wiki upgraded
- Door on HAM7 still off
- Praxair Delivery
- Closing HAM7 and craning clean-room from HAM7 to HAM12 not completed at time of writing

Times in PST:
0835 - Overhead doors arrive at MX
0847 - Corey out to HAM7 with Cheryl, Jeff, Rodney, Ski, to move MMT3
0905 - Squeezer on
0934 - Les Schwab arrives with tires
1131 - EX CP8 alarms, due to fueling by Praxair
1134 - Corey confirms that HAM7 is done
1331 - Jodi begins testing rotary tool at MX...disappointing results
H2 INS
corey.gray@LIGO.ORG - posted 14:08, Tuesday 07 December 2010 (397)
HAM7 iLIGO Seismic Isolation Stack Removal
[9:45 -11:15am]
(Corey, Jeff, Rodney, Ski, Zach)  

After helping out with moving SOS's around, the HAM7 stack removal commenced.  The procedure went smoothly.  The hardware is piled on top/next to the HAM8/9 hardware.  This pile of hardware will be moved out of the LVEA as soon as we receive recycling bins.
Images attached to this report
H2 INS
david.barker@LIGO.ORG - posted 08:47, Tuesday 07 December 2010 (396)
advligo wiki being replaced with awiki
The old advligo wiki was transitioned to read-only mode at 8am. Its data content is being transferred to the new awiki server (latest moinmoin with ligo.org authentication). We hope to have the new server ready for use by end of business.

Dave, Patrick, Jonathan H.
H2 General
cyrus.reed@LIGO.ORG - posted 16:32, Monday 06 December 2010 (395)
Ops Day Shift Summary
Today's major activities:

  • HAM7 optics removal (complete)
  • HAM7 prep for SEI stack removal.
  • Some on site deliveries.
  • The other usual miscellaneous stuff.
Also note that there are occasional high temp alarms for LVEA Zone 4F due to the increase in equipment added by the squeezer group. These are OK (unless the temperature continues to rise, or other zones also go into alarm, obviously).
H2 General
david.feldbaum@LIGO.ORG - posted 16:25, Monday 06 December 2010 (394)
HAM7 deinstall (DF, D.Tanner, Mike, Betsi, Rodney, Carolyn)
We have removed all the optics from HAM7. This includes:

H2 MMT3 LOS                          -- to be transported out of LVEA by crane

H2 MC1  
H2 MC3
H2 MMT1  
H2 SM1
H2 SM3                              --  stored in the optics lab

H2 old style Faraday isolator
~ 16 DLC mounts with mirrors    
~ 2 Tanner mounts                   --  being packaged for shipping to the UF.


Thanks to everyone for helping to make this operation go smoothly and efficiently. 
LHO FMCS
kyle.ryan@LIGO.ORG - posted 17:13, Friday 03 December 2010 (393)
VE power failure recovery
Custom battery backups for MTP levitation worked correctly following power failure today for all spinning MTPS on site.  All isolation valves "safety" valves worked correctly and isolated valved-in MTPs from foreline header at loss of power -> Restarted QDP80s and MTPs and resumed pumping (YBM, Vertex, XBM, X-end).  Had to switch back to turbo for HAM6 and valve-out ion pump.  Had to restart aux. carts pumping HAM1 and GV10 annuli.  
LHO FMCS
kyle.ryan@LIGO.ORG - posted 17:03, Friday 03 December 2010 (392)
HAM 7, 8 and 9 doors
Kyle, Ski, Jim, Rodney, Zack - Hung West doors on HAM9 and HAM8.  

Chris, Joe - Removed all but (4) "cracked loose" bolts from HAM7 East and West doors
H2 INS
dani.atkinson@LIGO.ORG - posted 15:59, Friday 03 December 2010 (391)
Ops Day Shift Summary
Doors went back on HAMs 8 and 9, and HAM 7 was prepped for entry Monday (including removal of IOT7 and ISCT7 enclosures). We had a very brief power outage in the morning and appear to have recovered, except for the possible death of h0pemms. Richard has also installed a camera for outreach purposes along the Y-arm in the LVEA, looking towards the BSC8/HAM10 area, to catch the upcoming single-arm work.
LHO FMCS
dani.atkinson@LIGO.ORG - posted 11:08, Friday 03 December 2010 (390)
Power Flicker
We had a power outage of about a second at 9:41PST. We're still restoring some of the systems on site. H2 deinstall activities in the LVEA were only minimally effected.
H2 General
patrick.thomas@LIGO.ORG - posted 17:25, Thursday 02 December 2010 (389)
Ops Day Summary
The H2 BS LOS was removed.

All the optics were removed from HAM10.

fb0w was restarted and should be writing frames.

Corey started cleaning up the seismic equipment removed from HAM 8 & 9.
H2 General
patrick.thomas@LIGO.ORG - posted 17:25, Thursday 02 December 2010 (388)
Ops Day Summary
The H2 BS LOS was removed.

All the optics were removed from HAM10.

fb0w was restarted and should be writing frames.

Corey started cleaning up the seismic equipment removed from HAM 8 & 9.
H2 INS
keita.kawabe@LIGO.ORG - posted 12:40, Thursday 02 December 2010 - last comment - 13:04, Thursday 02 December 2010(386)
HAM10 deinstall (Rodney, Zach, Dani, Matt, Keita)
We deinstalled all optics from HAM10. 

Main things were output Faraday, three sets (one AS and two POs) of beam reducing telescope, periscopes, and beam handling mirrors. These were all inventoried by Dani.

Faraday, AS periscope and AS beam handling mirrors were stored in one of the ISC/squeezer cabinets, others are still on the table near HAM8/9.

AS telescope is on the table by HAM8/9 under the clean room, but the PO telescopes are left on the support table of HAM9 because we didn't have any room outside to put them down.

We accessed HAM10 from HAM9 through BSC4. The picture taken from BSC4 shows Matt and Rodney working in HAM10.
Images attached to this report
Comments related to this report
keita.kawabe@LIGO.ORG - 13:04, Thursday 02 December 2010 (387)
There were several long fibers dangling from the upper table of BS in BSC4. They looked as if they were ripped off of bunny suits.

After all these years out-gasing, probably they've become ultra high vacuum compatible lints (but this time let's not repeat this).

Pictures show two particularly long ones. I took one sample out of chamber but it was somehow lost during moving things around.
Images attached to this comment
H2 INS
cheryl.vorvick@LIGO.ORG - posted 10:07, Thursday 02 December 2010 (385)
BSC4 Deinstall Complete - Beamsplitter LOS removed.
- Jim, Corey, Zach, Rodney, Cheryl

Beamsplitter LOS was removed - BSC4 is now empty.
Displaying reports 78741-78760 of 79123.Go to page Start 3934 3935 3936 3937 3938 3939 3940 3941 3942 End