(Corey, Keita, Lisa, Matt, Virginio)
In-Vacuum ISC Table
Lisa & Matt finished up laying out optics on the table (this included installing the mirror on the Beam Diverter, and installing the High Power Beam Dump [although one of the ceramic legs broke & will need to be replaced]). This afternoon they were approaching point of aligning optics.
Setting Up Alignment Laser & Telescope Work
Virginio & Keita worked on setting up the alignment laser. Before using it, they wanted to measure the beam profile of the laser. The Telescope Assy was suspended from its tooling. Made an Ameristat "tent" to enclose the Telescope and the Ag-plated mirrors when they are ready to be installed. The mirrors will be insalled when the desiccant packs arrive on site.
Clean Up, ISC-ing, Photos, Feedthru, & Humidity
Continued putting hardware away, and working on making ICS Assy Loads for the TMS. Continue to upload photos of progress, here. Helped Filiberto install the final roof-side cable to the TMS feed-thru. The humidity in the Lab was 34-40%.
Filiburto DC powered the IO Chassis for h1iscex, Jim and I started the IOP model. We found that the IO Chassis appears to be the PEM MY (one ADC, one 18bit DAC) rather than the ISC EX Chassis (3 ADC, one 16bit DAC).
Last shift at LIGO. It's been fun!
Valved-in YBM turbo @ 0930 hrs -> 6.5 x 10-7 torr*L/sec Valved-out YBM turbo @ 1600 hrs. -> 4.3 x 10-7 torr*L/sec
Just before lunch, I moved, unplugged and replugged back in the dust monitor at X-end. It had been sitting in the large cleanroom over the chamber, but since the the chamber is closed with the hard-covers, the more fitting place is for it to monitor near the ETMx optic. So, it is now in the cartridge assembly cleanroom.
At around 4:50 PM I restarted and burtrestored the h0dustex EPICS IOC. It was reporting errors.
Following the activation of jumbo frames on the EX DAQ switch, the IOP models h1iopsusex, h1iopsusauxex and h1iopseiex were successfully started with no negative impact on the DAQ system. The IO Chassis for h1iscex is not connected or powered, and so that front end is not running at the moment.
Here is the current status of the aLIGO SEI work regarding the HAM chambers. Everything in bold is to be completed for HIFO-Y. Everything in red is a change from last week's status. Everything in green is available.
· HAM 1
o HEPI unlocked and running
Ongoing commissioing
· HAM2
o ISI: previously commissioned with HEPI locked (recent performance spectra), currently unlocked, in vacuum
o HEPI: to be commissioned, currently locked, models and electronics ready. Commissioning could start once HEPI is unlocked.
· HAM 3
o ISI: previously commissioned with HEPI locked (recent performance spectra), currently unlocked, in vacuum
o HEPI: To be commissioned, currently locked, model and electronics ready. Commissioning could start once HEPI is unlocked.
· HAM 4
o ISI: In chamber, Previously tested during assembly validation, currently locked, no suspension installed, in-vac cables not connected, chamber temporarily closed.
Electronics ready, in field cables ready, in-rack cables 90%
Simulink Model was created.
Model is running, and MEDM screens are available in the Sitemap.
o HEPI: Currently locked, to be commissioned
Electronics ready, in field cables ready, in-rack cables 90%
Simulink Model was created.
Model is running, and MEDM screens are available in the Sitemap.
· HAM 5
o ISI: In Chamber, Previously tested during assembly validation, currently locked, no suspension installed, in-vac cables not connected, chamber temporarily closed.
Electronics ready, in field cables ready, in-rack cables 90%
Simulink Model was created.
Model is running, and MEDM screens are available in the Sitemap.
o HEPI: Currently locked, to be commissioned
Electronics ready, in field cables ready, in-rack cables 90%
Simulink Model was created.
Model is running, and MEDM screens are available in the Sitemap.
· HAM 6
o ISI: in a container. Need to be retrofitted with aLIGO censors (GS13, CPS) and to receive a new set of Actuator Cables. Cables and inertial sensors will be tested prior to installation. All this will happen chamber-side prior to installation in chamber. Commissioning will follow.
Electronics and cables started, the rest is ordered.
Simulink Model was created.
Model is running, and MEDM screens are available in the Sitemap.
o HEPI: Currently locked, to be commissioned
Electronics ready, in-rack cables 90%
Simulink Model was created.
Model is running, and MEDM screens are available in the Sitemap.
Here is a plot from last night showing the VCO stability using the slow servo to keep it at nominal. The standard deviation of the distribution is about 16Hz.
None of the end-x front end computers had correct BIOS settings, so all have been changed to disable as many "features" as possible, and to enable PXE boot option ROM loading. New BIOS settings resemble those of h1susb123 in the BIOS settings document (T-1300536).
The HEPI model at the end station (H1HPIETMY) was recompiled to receive the LSC lenth signal.
Changes since https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=6595
BSC1
ISI: https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=6832
HEPI: Locked
BSC2
ISI: https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=6834
HEPI: Unlocked - Valve of actuator V4 will be changed on June 25th.
BSC6
ISI: https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=6768
HEPI: Unlocked - Controlled in position and with IPS-L4C blend
https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=6709
STS2
STS-2 are connected at the corner station and at EY. Their locations are specified in:
https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=6456
For now, only HEPI ETMY and ISI ITMY respect the convention. Other models will be changed at the next "boot fest" to follow the convention.
This is a log from this past Friday:
The goals of the day were (1) to measure a calibrated CARM signal and (2) to try switching the frequency sensor to the PFD (Phase Frequency Discriminator). The former was achieved but the latter was not.
Calibration of the CARM signal
The VCO-based PLL, which is our frequency sensor for the CARM, was calibrated by an IFR RF generator so that one can evaluate the CARM fluctuation in a meaningful unit. The output signal from the PLL gets into an SR560 which does a signal amplification (pole at 100 Hz and gain of 10 ) and then is branched to the common mode board and an ADC through an RFPD interface box for monitoring the CARM signal. This channel is called H1:ALS-C_COMM_A_RF_I. Since this doesn't go through the common mode board the calibration is independent of the common mode board gain, which is good. Anyway according to a measurement where a known RF signal is injected to the RF input of the PLL a calibration factor of 176.2 Hz/ counts was obtained. This number was currently put in the gain of ALS-C_COMM_A_RF_I.
Calibrated CARM in-loop signal
The plot below is a measured CARM in-loop spectrum.
The residual fluctuation was measured to be 23.66 Hz in RMS integrated from 10 mHz to 7 kHz (shown as dashed line). However we are aiming a residual RMS of 8 Hz in order to confine the PSL frequency well within the arm resonance whose linewidth is approximately 80 Hz. So we are still far from the requirement by a factor of 4-ish but this is not surprising since we established the CARM control very recently.
Some notes on this plot
Alignment drift in the arm cavity
It seems there was an alignment drift which turned out to be big enough to prevent us from a long term measurement (say more than 30 min.). This looks due to a longitudinal to angle coupling in the ETMY top mass actuators. We have used an length offload scheme that relieves the end PDH signal from the low frequency saturation by branching the signal to the arm length via the ETMY top mass actuation. According to Matt the One-Arm-Test people used to offload this signal to HEPI rather than the ETMY or ISI, but recently we ended up with this ETMY scheme for some reason. Anyhow I think we have to go back to the old school -- offloading to the HEPI rather than the ETMY suspension for more rock solid lock.
The time series attached below is a trend during the CARM was locked. The CARM loop was closed right after the end PDH was engaged and then it was brought to the arm resonance several minutes later. I was tweaking PR2 and IM4 in the first 5-ish minutes after the IR became resonant. Then I stopped messing around afterward and simply let it locked. Obviously the oplev was seeing drift in both and YAW and PIT of ETMY by 0.3 urad or so over 20 minutes. Eventually the lock was lost (probably the end PDH first and then every loop lost their lock) due to the bad alignment. Once the length offload was shut off the alignment came back perfectly --- this strongly suggests a length to angle coupling in the ETMY top mass actuators at low frequency.
CARM control with PFD
Still unsuccessful --- I tried to close the CARM loop without using the PLL frequency sensor that we recently have been using but this basically destroys the IMC lock. One big reason is that there is a big gain discrepancy between the frequency sensor and phase sensor modes. This complicates the control scheme. Another reason is that it seems difficult to confine the PFD within its phase sensor mode by feeding the CARM signal to the MC2 suspension. The MCL control bandwidth can be 100 Hz or so, but probably this is not good enough to confine it within the phase range in the first place. Hmmm .... Also, I tried to confine the sensor close to the phase range by feeding a low frequency signal to the ALS_comm VCO through the Beckoff by using ezcaservo but this turned out that the slow control is too slow for this job, plus everytime the sensor enters the phase sensor range it gives a large signal and somehow kicks the VCO frequency away from it instantaneously.
The last thing we can try is a transition from the PLL frequency sensor to the PFD once everything is locked with the frequency sensor (though we need to establish some kind of fast switching since the CARM signal is mainly processed in the analog land).
Beatnote lost and found -- it was BS HEPI alignment
As reported (see alog 6835) the beatnote had been lost at the corner station. This turned out to be due to mainly an alignment of the BS HEPI and indeed the beam was hitting the mount of one of the 1 inch mirror on ISCT1 before the beam gets combined with the PSL green light. Vincent told me that the BS HEPI had been stack since the last Monday (correct me if wrong) and he suggested me to recover the position of the HEPI by introducing biases in the actuators. We tried this and it worked -- the beam came back to a good position on ISCT1 and we became able to see the beatnote again. It is still unclear why the BS HEPI alignment changed between Wednesday to Thursday even though it was stack. Although the alignment was mostly recovered, later on a fine tuning of the green beam alignment was done by tweaking PR3.
Giles report from yesterday's work:
(Travis, Mark, Jason, Doug, Giles)
After leaving the PUM hanging overnight there was no further development of the crack. We then proceeded to re-lock the PUM and hang the ETM to perform modal measurements. Using the autocollimator we measured the longitudinal, pitch and yaw modes. We then setup and optical lever to measure the transverse, bounce and roll modes. Finally we measured the 4 fundamental violin modes. The modal data gathered was:
Longitudinal 0.656 Hz
Pitch 1.09 Hz
Yaw 1.09 Hz
Transverse 0.656 Hz
Bounce 6.75 Hz (this will be sqrt(2) higher when the PUM is free)
Roll 9.6 Hz (this will be sqrt(2) higher when the PUM is free)
FR 505 Hz
FL 506.5 Hz
BR 506.5 Hz
BL 505 Hz
We finally installed the fibre guards and covered the entire lower stage.
Serial Numbers of fibers on the suspension now:
FL S1300183
FR S1300191
BL S1300190
BR S1300193
S1300186 was trashed during the welding as it was installed and then cut out as noted above.
Correction: BR is actually S1300173.
Attached are plots of dust counts requested from 5 PM June 20 to 5 PM June 21.
Attached are plots of dust counts requested from 5 PM June 19 to 5 PM June 20.
(Corey, Keita, Lisa, Matt, Virginio)
ISC Table Layout Has Begun
I roughly laid out the QPD Sleds, High Power Beam Dump, & Beam Diverter. Matt & Lisa started laying out all the rest of the optics (which required brining all the hardware from the Corner Station and then building each component, and then laying it out.) Most of the optics are now on the Table. Matt & Lisa will finish off laying them out and then begin aligning everything next week.
Telescope: Staging & Tooling
Virginio & I unwrapped Tooling for suspending the Telescope. Virginio is staging to start using our alignment laser.
Continuing To ICS
Continue to start making Assy Loads and accounting for all parts used for this installation.
EX TMS Weather
Relative Humidity started at 30% in the morning and went to 35% in the afternoon. We will receive desicant packs and hygrometers on Mon/Tues.
Following the installation of timing, networking and ipc in EX, we booted the h1susauxex front end computer and started the IOP model. This caused mx-stream DAQ errors from many other front ends, including all at EY and on the LVEA test stand. Restarting the mx streamers on these front ends did not clear the problem. When h1susauxex was powered down (thereby killing the mx streaming) all the other front ends became good again with intervention needed.
We will keep EX powered down for this weekend and revisit this problem Monday or Tuesday next week.
You may be encountering problems when manually starting models See this wiki page https://awiki.ligo-wa.caltech.edu/aLIGO/FrontEndStart You will see that the old scripts start_streamers.sh and start_iop_mx_stream.sh still use a single port MX stream. As described, modifying start_streamers.sh is easy (merely stop/start /etc/init.d/mx_stream). Discard start_iop_mx_stream.sh. * I have tested the new startup scheme described there on the LLO DAQ test stand, but have not attempted in on L1. The RCG 2.7 roll-out would be a good chance to do that.
Also make sure that the /diskless/root/etc/rtsystab file has been updated with a line for the new computer and IOP model. Several startup scripts depend on it. In particular /etc/init.d/mx_stream uses it to figure out the MX stream card and slot.
There was a configuration error on the EX DAQ switch on two ports, including the one for h1susauxex (h1seiex being the other). It was missing the mtu setting to allow transmission of jumbo frames (the dainbramaged CLI pagination code in these switches makes this hard to see, even when expressly looking for it...). This has been corrected, and I suspect it will work now barring any other problems, but this is yet to be tested.
HAM HEPIs 4 and 5 were brought into run mode yesterday, June 20th.
current HEPI Status:
| Bleed Mode | Run Mode |
| HAM 2 | BSC 1 |
| HAM 3 | BSC 2 |
| BSC 9 | BSC 3 |
| BSC 6 | |
| HAM 1 | |
| HAM 4 | |
| HAM 5 | |
| HAM 6 |
HAM 2 is now on the run list.
HAM 3 is now in run mode as well.