Displaying reports 78861-78880 of 81685.Go to page Start 3940 3941 3942 3943 3944 3945 3946 3947 3948 End
Reports until 15:32, Monday 21 May 2012
H1 FMP
jodi.fauver@LIGO.ORG - posted 15:32, Monday 21 May 2012 (2908)
BSC2-HAM4 ICC
The fourth dust barrier was repaired and installed between HAM4 and the new Mode Cleaner Tube. Start of work checks on compressors,hoses, etc were completed and brushing started in BSC2. Upper, collar and mid sections were all brushed today and only ONE (1!) drill was used.
H2 SUS
jeffrey.garcia@LIGO.ORG - posted 14:55, Monday 21 May 2012 (2907)
H2 SUS ETMY M0 R0 Diagonalization
The attached are diagonalization measurements run on H2 SUS ETMY M0 & R0 for Vertical and Yaw DoFs this afternoon.  Every measurement indicates ideal isolation of at least 20dB on both DoFs for both top masses.   
Non-image files attached to this report
H2 SUS
jeffrey.garcia@LIGO.ORG - posted 11:08, Monday 21 May 2012 (2906)
H2 SUS ETMY M0 R0 TFs
The attached are the latest TF measurements on H2 SUS ETMY M0 & R0 top masses.  There may be indication of rubbing in the M0 Transverse DoF seen in the 0.6Hz to 2Hz band.  All the other DoFs look fairly clean for all bands.
Non-image files attached to this report
X1 DTS
david.barker@LIGO.ORG - posted 09:19, Monday 21 May 2012 (2905)
Summary of X1 install work in H2 EE building
Summary of install of the new DAQ Test Stand (DTS X1) May 14th - 18thth

Rolf, Dave, Richard, Jim.
--------------------

We have installed the following X1 systems in the H2 EE building:

Timing, including timing fanout and IRIG-B distribution. We are running the new Timing Master Fanout in the MSR with a GPS antenna connected directly to its F-type connector.

DC power (12V) for the IRIG-B and timing fanout.

Networking, including three switches: the general X1 network switch; the FE-DAQ network switch with 10GE link to data concentrator; the 10GE DAQ switch

The x1boot machine, which is also the code build machine. RCG branch2.5 was installed and the x1ioppsl0 model was built. All file systems for user apps, rtscore, rebuild etc. were constructed.

The NAT router connecting X1 with GC. We ran a GC line from the GC switch in the H2 racks. We installed a new Vyatta based NAT router, using the original GC address for the DTS (badger.ligo-wa.caltech.edu)

We installed one IO Chassis with an AC PS, we booted one front end, the x1psl0 system.
------------------------

Next item is to get the DAQ fully operational.
H2 SUS
jeffrey.garcia@LIGO.ORG - posted 20:39, Friday 18 May 2012 (2904)
ETMY M0 & R0 measurements begun
Measurements on H2 SUS ETMY M0 & R0 began at 1021432185 (May 18 2012 20:09:30 PST).  Estimated completion time is May 19 at ~04:00 PST.


LHO VE
gerardo.moreno@LIGO.ORG - posted 17:19, Friday 18 May 2012 (2903)
H1 Input Tube Vacuum Update
Turbo pump was started yesterday at 16:22 local time, pressure this morning had reached 3.4x10^-03 torr, no update on current pressure since CC has not turned on yet, but pump continues to pump.
LHO VE
gerardo.moreno@LIGO.ORG - posted 17:15, Friday 18 May 2012 (2902)
BSC08/YBM Vacuum Update
Started turbo at 16:25 local time, about 30 min. later I started the CC, we see a pressure of 1.30x10^-05 torr.
LHO General
patrick.thomas@LIGO.ORG - posted 16:41, Friday 18 May 2012 (2900)
plots of dust counts
Attached are plots of dust counts > .5 microns. I have also included plots of the mode for the dust monitors at end Y to show when they were moved.
Non-image files attached to this report
H2 AOS
keita.kawabe@LIGO.ORG - posted 16:38, Friday 18 May 2012 - last comment - 08:29, Wednesday 24 April 2013(2901)
Beam diverter test (Dan Hoak)

Dan tested beam diverter and everything worked including the motor and the two reed switches.

That's strange as one of the two reed switches was stuck before, but somehow it's unstuck. Anyway it's good.

Comments related to this report
corey.gray@LIGO.ORG - 08:29, Wednesday 24 April 2013 (6179)

I'm curious to get my hands on this Beam Diverter, after my experience with building five of them.  For me, the Sensor Magnet's polarity seem to affect the functionality for the Reed Switches (Chirs Guido mentioned the position of this magnet was more the issue for him).

LHO General
patrick.thomas@LIGO.ORG - posted 16:37, Friday 18 May 2012 (2899)
ops summary
Dave restarted all the models of h2seib6.
Gerardo moved dust monitor 2 in the end Y LVEA into the clean room over BSC 6.
The IOP watchdogs for SUS BSC6 were tripped (in chamber work)
H2 SUS
betsy.weaver@LIGO.ORG - posted 15:37, Friday 18 May 2012 (2898)
ETMy ready for TFs

Today, we finished fixing the PUM (L2) LR magnet/flag.  We then verified that the suspension was free of any mechanical rubbing (many head to toe inspections) and adjusted all OSEMs to nominal settings, accounting for buoyancy.  So, we are ready for TFs on this guy.

H1 CDS
robert.schofield@LIGO.ORG - posted 14:50, Friday 18 May 2012 (2895)
More on I/O chassis fans, power supplies, and magnetic field coupling sites

Summary:

The power supply and fan issues with the i/o chasses could be solved with a new power supply producing smaller magnetic fields (being planned by CDS), routing cables away from power supplies, and a separate supply for the fans.  The strongest magnetic field coupling sites to the OSEM read back channels were the cable connectors to the chasses that the signal passes through and not boards such as the a to d board. However, since the cables pass close to the power supply, the dominant coupling for the power supply fields was to the cables instead of the connectors at their ends. The separate issue of the fan frequencies showing up in channels can be solved by using an external power supply: the remaining coupling (from magnetic fields) when using a separate supply was measured here to be down by at least ten. 

 

Power supplies in the I/O chasses:

In  a previous log I reported that magnetic fields from the I/O switching power supply were strong enough to couple into channels at an unacceptable level (here).  Since then, I have investigated the magnetic field coupling sites to see if there were any coupling sites that could be mitigated.

I looked for magnetic field coupling sites to one of the UIM OSEM readback channels for ITMY. I used a centimeter scale coil and slowly scanned circuit boards etc., while monitoring the coupling on a screen. The strongest coupling that I found was to the cable connectors to the UIM coil driver, the anti-aliasing module and the I/O chasis. The coupling to the connectors was stronger than the coupling to the a to d board, or any other location inside the coil driver or I/O chassis or along the cables. Note that this is only a test of coupling to the read back channel: I have not fully tested coupling of rack magnetic fields to the coil actuators.

Notwithstanding that the strongest coupling site was to the cable connectors, the dominant coupling site for the fields from the I/O chassis power supply was to the cables themselves because they pass so close to the power supply. Figure 1 demonstrates cable coupling, showing that when the cable into the UIM coil driver was about 10 cm from a field generator set on the I/O chassis power supply, the injected comb showed up strongly on the channel, but much less so when the cables were moved about 40 cm away from the field source, with no other changes.

Fans in the I/O chasses:

I noted in a recent ilog (here) that i/o chasis fan frequencies showed up in the channels passing through the chasis. When the fans were run on a separate power supply, the coherence was lower, but because of time constraints and dtt crashes, I was not able to run long coherence measurements to make sure that the coupling was much lower. Figure 2 shows the results of a recent 79,000-average coherence measurement, and the fan peaks appear to be showing with a low level of coherence. The plot suggests that the coupling of the fans to the i/o chassis channels is down by a factor of about 10 when the fans are run on a separate power supply. 

For this reason, I think that running the fans on a separate power supply will be sufficient. So, to solve the issues I have raised recently, the i/o chasis power supplies should be replaced and the fans should run on independent supplies.  There is a chance that power supply ripple from the fans would not be a problem with the new power supplies. I have not tested this.

Non-image files attached to this report
LHO General
gerardo.moreno@LIGO.ORG - posted 10:50, Friday 18 May 2012 - last comment - 15:17, Friday 18 May 2012(2894)
Y-End Dust Monitors
Relocated the Y-End station dust monitor #2, it is set inside the BSC06 clean room, it is next to the SE pier.  However it needs to move closer to where the action is, but we need a longer cable to accomplish that, yes we are looking for a longer cable.

Dust monitor #1 remains located West of the iLIGO racks inside one of the cleanrooms.
Comments related to this report
gerardo.moreno@LIGO.ORG - 14:42, Friday 18 May 2012 (2896)
We found a cable, thanks Richard, so we re-relocated the dust monitor (#2), now the location is by the NW pier of BSC06.
patrick.thomas@LIGO.ORG - 15:17, Friday 18 May 2012 (2897)
The dust monitor labeled 'L' is at location 1. The dust monitor labeled 'M' is at location 2.
LHO General
patrick.thomas@LIGO.ORG - posted 18:49, Thursday 17 May 2012 (2893)
plots of dust counts
Attached are plots of dust counts > .5 microns.
Non-image files attached to this report
H2 SUS
travis.sadecki@LIGO.ORG - posted 16:04, Thursday 17 May 2012 (2890)
Summary of SUS work at BSC6 today

See Betsy's closeout checklist  for the latest updates.  https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=2848

Since Betsy was working with Derek on Triples gluing stuff, I was on my own for much of the day.  I rediscovered that working on a monolithic Quad is rarely a one-person job, especially in chamber with TMS as its neighbor.  I began by attempting to remove the TFE caps that were on many of the spherical tip and silica tip EQ stops.  After cautiously removing as many as I could confidently do by myself, I was left with 4 caps on the underside of the top masses that were inaccessible by me solo due to limited access from the reaction side of the Quad.  These 4 caps require that someone with skinnier arms than mine reach through the Quad between the top and UI masses to grip the TFE cap from the inside while simultaneously working the screw from the outside to thread the cap off.  With a few spare minutes, Betsy helped me remove these last 4 caps.  Even with 2 people, we found this activity less than relaxing.  Note for future builds: Remove these caps before the monolithic is installed (since the majority of the clamping/unclamping is done by that point, the particulate issues these hoped to resolve is less of a concern). 

After the caps were removed, we noticed that one of the flags on the penultimate mass was dislodged from its steel disc baseplate, and that the magnet on the end of it was not seated correctly.  Betsy returned to her work with Derek, so I was on my own again.  To remedy this required the removal of the AOSEM opposite the flag in question in order to grasp the flag.  However, grasping the flag to remove/realign it is not trivial either.  This requires the use of a set of 10" long tweezers which must be inserted through the AOSEM hole (~1" diameter) in the PenRe to gingerly grab the assembly so as not to drop either of the 2mm x 6mm magnets of either end.  Again, due to access issues to the reaction side, I could not see the flag from this side.  To complete this simple task, 2 people will also be required: one to manipulate the tweezers and one to view/guide from the main chain side by looking through the penultimate mass, which luckily is transparent glass.  After bumping my head for the third time attempting the solo version of this task, I decided to move on (Note to TMS designers: much much larger chamfers on parts would be greatly appreciated).  I then installed the last of the sleeve screws that had been in use at BSC8 until recently.   Currently, the Quad is not fully suspended due to the PenRe being locked until the flag repair is complete. 

H2 General
jeffrey.garcia@LIGO.ORG - posted 16:00, Thursday 17 May 2012 (2891)
Ops log
Work in and around BSC6 throughout the day.  There were a few dust level alarms for "DST1_3" which is one of the two located in the End-Y VEA (the exact location of this dust monitor is not clear from the medms).

H1 PSL work in the LVEA.  

No machine reboots to report.


LHO VE
gerardo.moreno@LIGO.ORG - posted 10:18, Thursday 17 May 2012 - last comment - 17:08, Thursday 17 May 2012(2884)
8:39 AM local -> Start of pumping YBM


			
			
Comments related to this report
gerardo.moreno@LIGO.ORG - 17:08, Thursday 17 May 2012 (2892)
Pumping was stopped overnight, system is not designed to run unattended, will restart early tomorrow.  Pressure at 1.74 torr.
H2 SUS
betsy.weaver@LIGO.ORG - posted 16:31, Monday 14 May 2012 - last comment - 11:41, Friday 25 May 2012(2848)
BSC6 To-Do list before closing up
Following is the list of items that need to be completed (in roughly the order below) before we can close this chamber.  Some of the items have been finished and are still on the list as markers for redlining the installation procedure.  Please add a comment if I have missed any steps

1) Electrical grounding checks - DONE
2) IAS SEI alignment complete, ISI & HEPI floating - DONE
3) IAS ETMy alignment Round 1 - DONE
4) TMS alignment - DONE
5) ESD continuity check
6) Clamp ETMy EQ stops
7) Reapply FirstContact to ETMy-HR and ERM-AR
8) Swap Flooring - Waiting for FTIR on new set, can slip down list but not beyond 14a.
9) Viewport in-situ cleaning (or swap if deemed necessary)
10) TMS OSEM alignment
11) Close the ring heater and set fiber guard to "nominal" position
12) Unlock ETMy, remove all TFE except TM line stops, and physically check for rubbing as per T1200213 (still drafting)
13) ETMy BOSEM alignment, factoring in buoyancy as per T1100616
14a) ETMy testing (See Phase 3a G1100693)
14b) IAS ETMy alignment again (if testing showed interference and suspension was adjusted to fix)
15) Repeat step 14 until all Phase 3a testing is complete - usually done in 3 rounds in order to clear all issues.  Note, IAS requires removal of ETMy-HR FC completely. 
16) TMS alignment check if needed
17) Lock down flooring nuts if loose
18) Set all EQ stops as per M1100256
19) Final FirstContact cleaning if needed
20) Remove TM line stops
21) Take pictures and count number of PEEK clamps
22) Set witness plates
23) Remove all tools
Shut the doors.
Comments related to this report
betsy.weaver@LIGO.ORG - 13:07, Wednesday 16 May 2012 (2873)

The good news is we're working down the list.  The bad news is, I added a few more items to the list.  Edited to reflect actual order:

 

1) Electrical grounding checks (moved down the list since it was DONE on the test stand, not on the chamber)

2) IAS SEI alignment complete, ISI & HEPI floating - DONE

3) IAS ETMy alignment Round 1 - DONE

4) TMS alignment - DONE

5) TMS OSEM alignment - moved up list since DONE

6) ESD continuity check

7) Clamp ETMy EQ stops - DONE

8) Reapply FirstContact to ETMy-HR and ERM-AR - (did not so ETM-HR since sheet was still somewhat intact) DONE

9) Swap Flooring - Waiting for FTIR on new set, can slip down list but not beyond 14a.

10) Viewport in-situ cleaning (or swap if deemed necessary)

11) SEI Electrical grounding checks

12) SUS Electrical grounding checks

13) Close the ring heater and set fiber guard to "nominal" position

14) Unlock ETMy, remove all TFE except TM line stops, and physically check for rubbing as per T1200213 (still drafting)

15) ETMy BOSEM alignment, factoring in buoyancy as per T1100616

16a) ETMy testing (See Phase 3a G1100693)

16b) IAS ETMy alignment again (if testing showed interference and suspension was adjusted to fix)

17) Repeat step 16 until all Phase 3a testing is complete - usually done in 3 rounds in order to clear all issues. Note, IAS requires removal of ETMy-HR FC completely.

18) TMS alignment check if needed

19) Lock down flooring nuts if loose

20) Set all EQ stops as per M1100256

21) Final FirstContact cleaning if needed

22) Remove TM line stops

23) Take pictures and count number of PEEK clamps

24) Set witness plates

25) Remove all tools

Shut the doors.

travis.sadecki@LIGO.ORG - 15:21, Thursday 17 May 2012 (2889)

Update to closeout checklist:

1) Electrical grounding checks (moved down the list since it was DONE on the test stand, not on the chamber)

2) IAS SEI alignment complete, ISI & HEPI floating - DONE

3) IAS ETMy alignment Round 1 - DONE

4) TMS alignment - DONE

5) TMS OSEM alignment - moved up list since DONE

6) ESD continuity check

7) Clamp ETMy EQ stops - DONE

8) Reapply FirstContact to ETMy-HR and ERM-AR - (did not so ETM-HR since sheet was still somewhat intact) DONE

9) Swap Flooring - Waiting for FTIR on new set, can slip down list but not beyond 14a.  DONE

10) Viewport in-situ cleaning (or swap if deemed necessary)  IN PROCESS

11) SEI Electrical grounding checks

12) SUS Electrical grounding checks

13) Close the ring heater and set fiber guard to "nominal" position

14) Unlock ETMy, remove all TFE except TM line stops, and physically check for rubbing as per T1200213 (still drafting)  DONE (PenRe has be relocked due to flag repair) Also, 1/4-20 x 3/4" vented screws installed for sleeve (these were overlooked in the making of this list).

15) ETMy BOSEM alignment, factoring in buoyancy as per T1100616

16a) ETMy testing (See Phase 3a G1100693)

16b) IAS ETMy alignment again (if testing showed interference and suspension was adjusted to fix)

17) Repeat step 16 until all Phase 3a testing is complete - usually done in 3 rounds in order to clear all issues. Note, IAS requires removal of ETMy-HR FC completely.

18) TMS alignment check if needed

19) Lock down flooring nuts if loose

20) Set all EQ stops as per M1100256

21) Final FirstContact cleaning if needed

22) Remove TM line stops

23) Take pictures and count number of PEEK clamps

24) Set witness plates

25) Remove all tools

Shut the doors.

travis.sadecki@LIGO.ORG - 11:41, Friday 25 May 2012 (2952)

Update to closeout checklist:

1) Electrical grounding checks (moved down the list since it was DONE on the test stand, not on the chamber)

2) IAS SEI alignment complete, ISI & HEPI floating - DONE

3) IAS ETMy alignment Round 1 - DONE

4) TMS alignment - DONE

5) TMS OSEM alignment - moved up list since DONE

6) ESD continuity check

7) Clamp ETMy EQ stops - DONE

8) Reapply FirstContact to ETMy-HR and ERM-AR - (did not so ETM-HR since sheet was still somewhat intact) DONE

9) Swap Flooring - Waiting for FTIR on new set, can slip down list but not beyond 14a.  DONE

10) Viewport in-situ cleaning (or swap if deemed necessary)  DONE

11) SEI Electrical grounding checks

12) SUS Electrical grounding checks

13) Close the ring heater and set fiber guard to "nominal" position DONE, AS MUCH AS IT CAN BE

14) Unlock ETMy, remove all TFE except TM line stops, and physically check for rubbing as per T1200213 (still drafting)  DONE (PenRe has be relocked due to flag repair) Also, 1/4-20 x 3/4" vented screws installed for sleeve (these were overlooked in the making of this list).  DONE

15) ETMy BOSEM alignment, factoring in buoyancy as per T1100616  DONE

16a) ETMy testing (See Phase 3a G1100693)  DONE

16b) IAS ETMy alignment again (if testing showed interference and suspension was adjusted to fix)  DONE

17) Repeat step 16 until all Phase 3a testing is complete - usually done in 3 rounds in order to clear all issues. Note, IAS requires removal of ETMy-HR FC completely.  DONE (PENDING FINAL SET OF TFS TODAY)

18) TMS alignment check if needed  IN PROCESS

19) Lock down flooring nuts if loose

20) Set all EQ stops as per M1100256  DONE

21) Final FirstContact cleaning if needed

22) Remove TM line stops

23) Take pictures and count number of PEEK clamps

24) Set witness plates

25) Remove all tools

Shut the doors.

Displaying reports 78861-78880 of 81685.Go to page Start 3940 3941 3942 3943 3944 3945 3946 3947 3948 End