Displaying reports 79661-79680 of 84537.Go to page Start 3980 3981 3982 3983 3984 3985 3986 3987 3988 End
Reports until 11:00, Saturday 29 December 2012
LHO VE
kyle.ryan@LIGO.ORG - posted 11:00, Saturday 29 December 2012 (5011)
HAM2-HAM3 pumpdown
1040 hrs. local 

2.7 x 10-6 torr @ turbo inlet -> Foreline @ 4.1 x 10-3 torr 

Domestic water storage tank @ 43", raw water storage tank > 60" 

BT roads still not passable -> tumbleweed crew working towards Y-mid 

1100 hrs. local -> Leaving site now
H1 CDS
david.barker@LIGO.ORG - posted 15:15, Friday 28 December 2012 (5010)
Rack relocation work complete

We have completed the removal of the two infrastructure racks in the H2 Building, with their contents now relocated in the MSR. All items went into the right side two MSR racks with the exception of:

the Qlogic switch which was moved to the DTS DAQ rack (previously the H2 DAQ rack)

the GC switch which was relocated into the DTS computer rack

the conlog machine which was relocated to the H1 DMT rack, this will become an H1 FE computer

The cdswiki machine was finally made to boot via a manual grub startup. This machine looks like it lost one of its LVM2 drives. Since it will be replaced with the new Debian box next week, we will hope it holds together until then.

The backup file server died again, we suspect a bad boot drive. It is scheduled for a reinstall on the second boot drive soon.

H1 CDS
david.barker@LIGO.ORG - posted 10:59, Friday 28 December 2012 (5009)
Rack relocation

Work continues on the rack relocation from the H2 Building to the MSR. Today we are fixing the cdswiki problems, moving the conlog machine into the H1 DMT rack, getting all services restarted and gutting the old H2 racks. Access to the DTS is down while we reconfigure the GC network in the H2 Building.

Attached is a picture of the two new MSR racks. They are the computer racks next the the two UPS racks.

Images attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 18:13, Thursday 27 December 2012 (5008)
CDS shutdown for server rack relocation

WP 3615, Dave B and Jim B

We shutdown all the servers in the H2 Building, starting at 9am today. All machines were re-racked in the MSR. The original network switches were moved along with the computers. All were connected to the Raritan Paragon KVM system.

We powered the machines on in order of importance: file and boot servers, admin servers, ifo servers, web and login servers.

All came back except for cdswiki, which appears to have a disk error. We will continue to work on this tomorrow, but for tonight there is no CDS web services: medm snapshots, web pages, work permit, cds wiki. If we cannot get cdswiki working tomorrow, we will put a temporary web server in place to serve the medm screen shots.

Staff with login account should be able to use their accounts now.

We check that the DAQ is acquiring the Vacuum controls and FMCS signals. All front ends were unaffected by this move.

All Ubuntu workstations in the control room needed a power cycle to get operational, we suspect DHCP issues.

I'll post a more detailed alog later.

LHO VE
kyle.ryan@LIGO.ORG - posted 13:11, Thursday 27 December 2012 - last comment - 13:12, Thursday 27 December 2012(5006)
HAM2-HAM3 pumpdown
1300 hrs. local 

3.3 x 10-6 torr @ turbo inlet -> foreline @ 4.4 x 10-3 torr
Comments related to this report
kyle.ryan@LIGO.ORG - 13:12, Thursday 27 December 2012 (5007)
Tumbleweed crew are working their way to Y-mid
H1 CDS
james.batch@LIGO.ORG - posted 11:32, Wednesday 26 December 2012 - last comment - 12:21, Wednesday 26 December 2012(5004)
h1boot restarted
The h1boot computer had a kernel panic Dec. 25 in the morning.  Rebooted at 11:19 PST Dec. 26. 
Comments related to this report
david.barker@LIGO.ORG - 12:21, Wednesday 26 December 2012 (5005)

logs suggest that h1boot became unresponsive at 01:55am Christmas Morning. 

LHO VE
john.worden@LIGO.ORG - posted 11:24, Monday 24 December 2012 - last comment - 11:27, Monday 24 December 2012(5002)
HAM3-HAM2 Pumpdown

HAM3 pressures as of Dec 24,  11:00 am

Cold Cathode - 5.6 e-6

Pirani - 5.6 e-3

 

Not a typo - both gauges read 5.6 but 3 decades apart.

Comments related to this report
john.worden@LIGO.ORG - 11:27, Monday 24 December 2012 (5003)

Tumbleweed baling continues.

The buildings are relatively clear now. One lane has been opened to XMID, the crew expects this lane to be done to XEND at the end of today.

Wednesday they will start on the YARM - we need access for LN2 and work planned for the YEND station in early January. They expect to work

through the holidays except for Dec 25.

LHO VE
kyle.ryan@LIGO.ORG - posted 13:45, Sunday 23 December 2012 (5001)
Energized CC gauge -> Gauge has yet to fire -> foreline 6.6 x 10-3 torr
1345 hrs. local -> Leaving site now
LHO VE
kyle.ryan@LIGO.ORG - posted 13:12, Sunday 23 December 2012 (5000)
1315 hrs. local -> Arriving to connect gauge and check on pump down
Expect to be here 30 mins.
LHO VE
kyle.ryan@LIGO.ORG - posted 11:18, Saturday 22 December 2012 (4999)
Switched HAM2-HAM3 pumping over to Turbo
1030 hrs. local -> HAM2-HAM3 @ 1.2 x 10-1 torr -> Relatively fast rough-down (scroll pump) due to 2" hose connection to 2.5" Vent/Purge valve as opposed to pumping through deenergized turbo pump (observed ultimate pressure of this particular scroll pump is 3 x 10-3 torr).  

Tumbleweed crew bailing near Y-arm penetration.  

1115 hrs local -> Leaving site now.
LHO VE
kyle.ryan@LIGO.ORG - posted 10:18, Saturday 22 December 2012 (4998)
1015 hrs. local -> Arriving to check on pumps -> Expect to be here 30 mins


			
			
H1 CDS
david.barker@LIGO.ORG - posted 17:17, Friday 21 December 2012 (4997)
rebuilt the backup server

The CDS backup disk server cdsfs1 crashed late last night and would not reboot today. We could not recover its boot disk, so we reinstalled Ubuntu 10.04LTS. The backup raid contents were preserved, so no need to rsync everything from /ligo and h1boot again. We are now re-installing the backup scripts and linking the tape backup system.

cdsfs1 had become very flakey lately, hopefully the rebuild will fix this.

H1 SEI
james.batch@LIGO.ORG - posted 17:12, Friday 21 December 2012 (4996)
h1seih16 rebooted multiple times, ADC channel hopping
Models running on h1seih16 would not run more than a few minutes.  The IOP model would die with complaints of ADC channel hopping, the GDS TP screen showed ADC1 as the culprit.  In an effort to find the problem, Richard McCarthy 1.) reseated all the cards in the I/O chassis, then 2.) moved the ADC card for ADC1 to a different slot so it would no longer be ADC1, 3.) Completely rearranged the cards to match the h1seih23 system (minus 2 ADC cards).  In all cases, the models would stop after a period of time (up to 25 minutes) with the same complaint of ADC channel hopping and the indication that ADC1 was the problem.

David Barker modified the IOP model to only use 1 ADC card and the model was restarted.  So far after many hours, the IOP model is still running.  All cards were left in the I/O chassis for this test.

We need to troubleshoot this to find out if any 2 ADC cards cause channel hopping, or if there is a specific ADC card that is causing the issue, or some other cause.

LHO General
dale.ingram@LIGO.ORG - posted 16:22, Friday 21 December 2012 (4995)
Ops shift summary
A quiet day in the CR.  The biggest news was the startup of pumping of the volume between HAM's 2 and 3. See Kyle's entry below.  Kyle has his eye on the LN2 tank for CP4 which reads 31.3 today.  Tumbleweeds nixed last week's scheduled fill of this tank. Dave Barker, Jim and Richard swapped ADC cards for HAM1/HAM6 SEI in an attempt to provide readouts for seismic.  See Kiwamu's entry below regarding the move of IOT1.  The tumbleweed crew has been working all day.

Jeff Barlett, Mark Barton, Kyle and Dave Barker have placed work permits for work that will occur over the holiday break.
LHO VE
kyle.ryan@LIGO.ORG - posted 15:08, Friday 21 December 2012 (4994)
Began roughing HAM2-HAM3 @ 1345 hrs. local -> 400 torr @ 1455 hrs
Will be in occasionally to check on status, record pressure and to switch over to turbo etc. -> Will make aLOG stating my intended duration when I arrive and an entry when I leave site -> Am continuing to pump down Vertex + YBM over the break for the data.
H1 IOO
kiwamu.izumi@LIGO.ORG - posted 12:18, Friday 21 December 2012 - last comment - 14:41, Friday 21 December 2012(4992)
IOT1 moved in

The IOT1 table [1] was transported from the squeezer bay to the place next to  HAM2 where the table is supposed to be. The disk-shaped spacers were installed between the enclosure and legs after the table moved in there.

Some pictures will be uploaded shortely.

[1] LHO alog #4985

Comments related to this report
kiwamu.izumi@LIGO.ORG - 14:41, Friday 21 December 2012 (4993)
Images attached to this comment
Displaying reports 79661-79680 of 84537.Go to page Start 3980 3981 3982 3983 3984 3985 3986 3987 3988 End