Although the metal build Quad 3 that is hanging in the staging building has been checked out and is ready to be put in storage, today I used it to test fit a new ECD magnet replacement block and check wire lengths. So, currently it's M0 top mass is locked and the BOSEMS on the main chain tablecloth are detached. We will be doing a couple more retrofits of parts (and possibly another round of testing to vet these retrofits) before we are ready to put it in storage. STATUS: Q3 IS NOT SUSPENDED AND BOSEMS ARE DETACHED.
EricA & I today installed the Actuators in the HAM2 HEPI Housings. This paves the way for us to now Float the ISI on the HEPI Springs and set the elevation and level of the Optical Table. We could do that tomorrow and then be ready for IAS horizontal assessment and alignment correction.
With IAS (Jason) giving us the all good yesterday on Horizontal position, today we checked the elevation and level. Attached are my notes (some is JimW) recording level survey, dial indicator readings, HEPI Spring turns and load cell readings from the week of work on this chamber. The last page records today's final level shots. On average we are 0.1mm low with a level of 0.2mm p-p; pretty sure this will be considered in spec. So IAS is free to relocate to HAM2--no rush though.
The first round of H1 MC2 transfer functions have been taken and committed to svn under:
/ligo/svncommon/SusSVN/sus/trunk/HSTS/H1/MC2/SAGM1/Results
filenames:
2012-07-19_0900_H1SUSMC2_M1*
Kissel will look these over tonight.
I measured the LONG and PIT OLTFs and put in some simple damping loops for in both in ITMY and ETMY. The L "plant" had very low gain compared with P, probably because of the factor of ~10 radio of the Euler matrices. To avoid a very high gain in the filter bank, I put a gain of 10 in the L2L SensAlign and another 10 in L2L. This gave a gain of -5 for L, with penty of gain margin. I set the P gain to -3, again with lots of gain margin (the plot was made with a gain of -5.)
A few days ago the first 2 plates for LHO's next BSC were brought to the staging building. The first of these (D0900894-v2, s/n 1) was placed on the granite table today, and will be helicoiled over the next couple weeks, in between work on other install tasks. We won't really be able to get back into production of BSC's until at least one of the test stands can be switched back to a BSC configuration, but that is hopefully no more than a week or two out.
Pulled SUS PR2-TOP 25DB cable (CAB_H1:SUS_HAM3-3), from HAM3 Field Rack to HAM3 SUS assembly/testing area. Cable was routed to clean room but NOT connected to the mockfeedthru, since it requires full garb inside the cleanroom.
Since the suspension had been moved from the staging building test stand to the LVEA test stand (which utilized production electronics), I rechecked and tweeked the OLV offsets and the gains. Today's measured OLVs and their channels are listed below:
27693 H1:SUS-MC2_M1_OSEMINF_T1_OUTMON (was -13851, set to -13846)
gain was 1.083, set to 1.083
22937 H1:SUS-MC2_M1_OSEMINF_T2_OUTMON (was -11462, set to -11468)
gain was 1.309, set to 1.308
28101 H1:SUS-MC2_M1_OSEMINF_T3_OUTMON (was -14049, set to -14050)
gain was 1.068, set to 1.068
26782 H1:SUS-MC2_M1_OSEMINF_LF_OUTMON (was -13383, set to -13391)
gain was 1.121, set to 1.120
27729 H1:SUS-MC2_M1_OSEMINF_RT_OUTMON (was -13847, set to -13864)
gain was 1.083, set to 1.082
30198 H1:SUS-MC2_M1_OSEMINF_SD_OUTMON (was -15085, set to -15099)
gain was 0.994, set to 0.993
24246 H1:SUS-MC2_M2_OSEMINF_UL_INMON (was -12413, set to -12123)
gain was 1.208, set to 1.237
23231 H1:SUS-MC2_M2_OSEMINF_LL_INMON (was -12030, set to -11615)
gain was 1.247, set to 1.291
23466 H1:SUS-MC2_M2_OSEMINF_UR_INMON (was -12152, set to -11733)
gain was 1.234, set to 1.278
25039 H1:SUS-MC2_M2_OSEMINF_UL_INMON (was -12977, set to -12519)
gain was 1.156, set to 1.198
24397 H1:SUS-MC2_M3_OSEMINF_UL_INMON (was -12411, set to -12198)
gain was 1.209, set to 1.230
23153 H1:SUS-MC2_M3_OSEMINF_LL_INMON (was -11815, set to -11576)
gain was 1.270, set to 1.296
25610 H1:SUS-MC2_M3_OSEMINF_UR_INMON (was -13089, set to -12805)
gain was 1.146, set to 1.171
19328 H1:SUS-MC2_M3_OSEMINF_UL_INMON (was -9727, set to -9664)
gain was 1.542, set to 1.552
Turned on Hepa fan on table at approximately 0930 while accessing the table for pictures of feed through s returned at 1205 to turn off fan while John W opened the gate valve. The fan is now off.
H1 and H2 DAQ.
all four frame writers (h[1,2]fw[0,1]) are showing instability. I have extended their raw minute trend update periods to 30 minutes. The new configuration will be applied if any of them restart due to the original problem.
This morning Thomas told me that ETMY OPLEV MEDM screen was not working.
Though the medm screen for new OPLEV channels are present (H2SUSETMY_ETMY_L3_OPLEVWIT_P and Y, what's this stupid ETMY_ETMY thing anyway?), and though the output of the QPD segmens looked OK, the INMONs of OPLEVWIT_P and Y were zero, and more outrageously, the outputs were 1E20 though the gains were 1 and there was no filters. As soon as we set the gain to anything except 1.0, the output becomes zero. Some serious stupidity was going on.
We found that the signs of the oplev segments were all wrong, but that didn't fix this 1E20 thing.
On a deeper inspection we've found that OPLEV does all calculation in a C code /opt/rtcds/userapps/release/aos/common/src/OPLEV.c, and in this code PIT and YAW are calculated by
pitch = (UL + UR - LR - LL)/(sum*linearResponse*leverArm);
yaw = (UR + LR - UL - LL)/(sum*linearResponse*leverArm);
linnear Response and leverArm are EPICS channels H2:SUS-ETMY_L3_OPLEVINF_LINRESP and H2:SUS-ETMY_L3_OPLEVINF_LEVERARM. These used to be 1, but in yesterday's terrible burt restore these were set to zero, therefore both pitch and yaw were calculated as NaN or something, and depending on what number you multiply that would be displayed as 0 or 1e20, or something like that.
I set these two parameters to 1 and the OPLEV error signal started working.
On a side note, I think OPLEV could use an input matrix (cdsMuxMatrix) to generate raw SUM, YAW and PIT, then use a standard multiply/divide, rather than maintaining its own C code.
It's the way all qpd and wfs DC are done in ISC (see attached).
See the attached.
Watchdog is supposed to watch SUM, PIT and YAW of the optical lever, but as of now OPLEV laser power is connected to the YAW input of the watchdog. Please fix it.
It appears that the RFM loop on the managed hub (VMIC 5595) is in the opposite way to which we imagined, from the higher numbered port down to the lower numbered port. Because we put the loop together "backwards" it turned out that for the IOP watchdog on the SUS ETMY frontend to communicate with the SEI BSC6 front end less than a foot away phyiscally, it had to run through 8km of fiber because we extended the loop to the LVEA on Tuesday this week. To run through 8km of fiber optics cable takes about 40uS. The IOP runs at 64KHz, with a processing loop taking about 15uS. So not surprisingly the SEI BSC6 IPC receiver was giving 65538 error per second.
The EY ISC was also going through 8km of fiber to communicate with SUS ETMY. This system runs at 16KHz and has 60uS loop time. 40uS could have been just sufficient, and indeed I did see a non-zero communication error rate, at about 1 error per minute.
I reconfigured the RFM loop at EY to the following
[ISC EY] -> [SUS ETMY] -> [SEI BSC6] -> [LVEA SUS ITMY] -> back to ISC EY
Now the EY IOP watchdog error rate is zero. I'll trend the ISC EY -> SUS ETMY to check it is now truely zero, but I watched it for several minutes last night and it was zero.
I am running some TFs on MC2. This is noted for other tester staff. Everyone else should continue work as normal in the LVEA.
Vincent left the ISIs on with their new isolation loops tonigiht. Their performace is noticably better than a few days ago at 1Hz, and the lock is quite stable. The attached plot shows 3 spectra: green is with the BSC8 ISI tripped, blue with both ISIs running their isolation loops, and red with some more SUS damping (the SUS settings suffered a setback after recent changes to the models).
Bram, Matt
The cavity is left unlocked (ISCTEY HEPA fan off) in anticipation of Hartman work starting in a few hours. The CM PDH path is off, the ETM offload path is open, and the ITM is misaligned by ~1000 counts in YAW from +554 to -500.
New blend filters were installed on the 2 ISIs (750mHz blend - less agressive than the initial ones). 250mHz low blend filters were installed on stage 1 - Y direction on BSC8 exclusively. Isolation filters of the 2 ISIs had some minor tweaks.
The ETM optical lever shows interference fringes when the TM is subject to a large longitudinal drive. I guess this will go away when the front surface beam is found, but it is something to look for on all the optical levers to be sure that we don't add noise from longitudinal motion.
Whenever you guys (ISC) are ready, I can go in and fix that.
A quick check of ITMY (push in a length offset and remove it) show no signs of fringes.
I measured the TMS ISC table angular and lateral stability when the end station VEA was quiet last night.
I found the table displacement to be around 5-10 um rms laterally and 1-3 urad rms in angle over 100s. The motion thus appears to be within the requirements: 100 um and 1 urad, respectively.
These are the close loop plots of the same measurements.
As Keita noted, the HEPA-off curves show a large bump at around 100mHz which which goes above spectra with the HEPA on. It's not clear why.