In anticipation of putting the Arm Cavity Baffle on to the ISI Stage0, we've put the HEPI (and entire Cartridge) on stops at the HEPI Crossbeam Foot. This lifted the assembly 1 to 2 mils (.001-.002") monitoring the dial indicators. We also brought in the out board stops (facing inward) on each Foot just to further constrain the position. In case I don't make it back after the new year please don't forget. GregG knows the story and where the numbers are recorded. *** Please don't disturb the dial indicators at the Support Tube ends *** Once the ACB is mounted up, we'll lift the load off the set screws, back them out of the way and set the payload back where it started.
This week we have been decommissioning the iLIGO H1 systems in the MSR and control room. The iligo DAQ is now powered down, all legacy VE, FMCS and slow PEM have been transitioned to the new H2 DAQ. All but the legacy computers and networking gear have been removed from the MSR (see photo). The archival iLIGO services (ilog, blue, wiki) are being relocated to the LDAS server rooom and will run in read-only mode to support S6 and squeezer data analysis.
(Chris K., Corey, Randy, Zach)
HAM3
With every thing staged and ready to go a couple of days go for HAM3 SEI Stack extraction, the Apollo crew and I made quick work of extraction this morning. Our goal was to remove iLIGO SEI hardware (above Support Table), and keep the Optics Table and Masses clean. We did this work in roughly 2hrs (8-10am). Both doors were off of this chamber and everything was pulled out the West Siiide. Nothing new here.
The Optics Table is currently in the South Bay next to the HAM1 Table near the H1 Racks. The Leg Element (masses) are on a pair of pallets nearby. Other hardware is dirty and in a tub on top of the Optics Table.
I believe the Apollo crew will install the doors this afternoon.
All photos of work at the HAM3 De-install Colection at: https://ligoimages.mit.edu/?c=897
HAM2
Since there was access to HAM2 & I had a tool, I went into HAM2 to disconnect all cabling from feedthrus.
BSC2
Additionally, since I was in-chamber, I went ahead and did some work in BSC2. Here's what I did:
The POX & POY mirrors are currently in a nearby mini-cleanroom on a "clean" table and have a layer of foil on them. Not sure whether or not we need to keep these guys clean (sent out emails asking).
The counterweights, screws and Pick Off mirror dog clamps are all outside HAM3 on the ground.
Oh, I accidentally left a 3/16" allen wrench in BSC2 on one of the Beam Dumps (aka "cornucopias"). I didn't go back in to get it since we won't be pumping down this volume any time soon.
So, the only items on the BSC2 Optics Table are the BS Suspension & the cables/bracket on the table. See attached photo of the Table.
Photos of BSC2 (and also some from BSC8) are at: https://ligoimages.mit.edu/?c=898
All of the CPS are within 3000 counts of zero, and their locked position which is good enough for testing.
EricA, GregG, RichM, CoreyG Yesterday while IAS was dialing in their instruments, we did a minor level tweak looking at the ISI Optical Table with the HEPI Springs. We (Jim & I)had seem .530mrad on 12 Dec and today we lowered that as best we could. I'll say it is perfect but it looked a bit saddled about on the scale of the manufacturing tolerances. My observances are flat +-.004" or +-.1mm. We might be looking over 1.5m of the table for a level to about 1.4mrad. This sounds out of spec but I don't think it can be improved given what I see of the table shape. Late yesterday IAS gave us a position of 1.6mm -X and 2.4mm +Y of nominal. We moved this with the HEPI Springs in four steps totaling about 1-3/4 turns on the 3/4-20 Spring threads. We made direct translations first North (+X), then East (-Y), East again, and finally North. This put us well within spec. We then did a small tweak up to the Optical Table Level again dropping the NW corner and raising the SE <0.2mm each. With the table as level as we can get, SUS freed the optic and we got it quiet enough for a YAW shot after Travis pulled down the top edge of the First Contact. IAS saw a rotation of 1.29mrad CW. We broke for lunch. After lunch with new found courage and Eric's calibrated wrench arm, we made a CCW rotation in three steps turning the 3/4-20 thread 1-1/12 turns. IAS has done another final round and I'll let them post those results but I believe we are still good in our elevation, translational position as well as the yaw position. Thanks Crew!
Used HEPI static adjustments today to adjust horizontal position and fine tune longitudinal position of the ITMy. After, ITMy was fully released from stops, yaw was measured at 1.29 mrad clockwise (direction given assuming a top-down view). HEPI static adjustment was used to correct for this yaw error, then horizontal, vertical, and longitudinal position was measured again to check for any changes caused by the yaw adjustment; pitch was also measured. The ITMy is currently sitting:
IAS has temporarily moved out of the spool piece area (except for one piece of equipment which is in critical alignment and roped off with caution tape; please DO NOT TOUCH) to allow SLC to install the ACB in BSC 08 on Thursday.
Will add bellows tie-rods between BSC6 and BSC10 tomorrow and continue pump down. BSC6 stand is not grouted yet. Tie-rods will share horizontal load to additional anchors.
More cabling continued on the underside of the ISI table. Travis and I added the TMS bracket-to-feed thru cables, so there are now ~7 cables that are ready to be handed off to SEI for dressing up the ISI stack. We still have a few more to add, such as the broken (and repaired) ESD DXXX1617 cable and 2 more D100225-199". We also prepped the UIM wire segments in prep for mating the lower M0 to the upper structure, and refit most of the lower face EQ stops with the newly designed version.
To facilitate the IAS measurements this afternoon, I unclamped the ITMy and then barely pushed the lower line stops back up to just-touching the ITMy barrel. I also pushed the top PUM barrel stops in to just-touching. I left the ITMy SUS in this state in hopes that these stops would provide a bit of friction during any HEPI moves subsequent to today's measurements (although Hugh assures me that the motion felt by the ITMy will be very slow and smooth). The reaction chain and FMy are still clamped. Other small items not yet in the log: Greg and I pulled the manifold barrier down which was left from the cleaning crew. It was blocking the IAS view of ITMy. We set it in the tube propped up against the side, but leaving a clear shot for IAS to the ITMy. AOS is considering using the barrier when bringing in baffle hardware later this week. Also, the last of my in-chamber FMy cables looks to have been restored to it's bracket and mating connector (after an end-to-end flip was made in order to mate to the feed-thru). So, I suppose the FMy chassis can be powered up as well.
(Corey, Ed, Mark, Slim Jim)
Today we removed components from the HAM3 Optical Table (Recycling Mirror, Telescope, Beam Dumps, and weights). We also did preparations for iLIGO stack removal tomorrow.
The Telescope was removed and not kept clean (it is on the floor in the south bay). There is no distiguishing serial number on this assembly other than part numbers for individual parts.
The Recycling Mirror (RM) was kept semi-clean, and is on a table in the Optics Lab with several other iLIGO Suspensions. This mirror is designated as: RM03-B.
The forklift with a short "surfboard" was used to pull the Telescope and RM from the HAM3. This work took roughly 4hrs.
Photos of HAM3 work from today and tomorrow will be posted in Resource Space at this location:
https://ligoimages.mit.edu/?c=897
J. Oberling, D. Cook
First set of alignment numbers for the ITMy were taken today; we measured horizontal, vertical, and longitudinal positions. Positions are relative to the desired optic position and directions are given when facing the front of the optic.
The horizontal translation will be done tomorrow morning via a HEPI static adjustment.
The H1 Input Mode Cleaner Tube(iLIGO) was removed and set outside today. No paint was scratched in the process. HAM3 optical components were removed and preparations made for wrapping the stack for future use. Alignment is underway at BSC8 and the ITM.
Completed cabling of SEI and SUS field cables to BSC8. Ran cables from H2 Test Racks along Y-arm to BSC8. Moved Sat. Rack into beergarden. As of now, SUS coil drivers for QUAD are powered on. Units for PUM, UIM, FMY and ISI coil drivers units are powered down. F. Clara, R. McCarthy, J. Garner
I removed old preference files from the controls user account for Ubuntu workstations. The regenerated preferences have restored the window focus behavior that allows windows to pop to the front when links to them are clicked. This affects matlab and medm applications in particular. This will now make it much easier to work with applications that have large windows that hide other windows.
The air-bake oven in the LSB optics lab has had a new controller installed. The controller is capable of handling ramp and soak functions. Large changes to the oven (opening or closing the flue, etc.) will now need the autotune process after the change has been made if an accurate temperature ramping is desired. More info can be found here: Omega Manual. The controller can run a program with 30 setpoints to ramp and soak at different rates and hold times.
Attached is a graph of a ramp up from 40 to 70 degrees in 30 minutes that was run as a test. I will attach a more detailed report to this when it is finished, but if anyone would like to use that oven I will be more than happy to give a run down on how to set it up. This controller really suffers from a Blinking 12 problem.
Also attached is the modified wiring schematic that represents what is now in use for the oven. As you can see the controller will stay on even with the power switch off. This is how I intended it to be, the fan and heater will be de-energized by the switch still.
With most of the cabling completed we got the Dial Indicators in place and followed that with suspending the HEPI from the double start counter wound Springs. Of course that means everything is floating--SEI Crossbeams (external blue), Support Tubes (in-vacuum), SEI-ISI & Suspensions. *** Do not disturb the Blue Crossbeams *** Ah heck--DON"T TOUCH ANYTHING, please! EricA, MitchellR, RichM & Hugh
The first phase of network switch changes is complete for the coming migration of the iLIGO legacy systems to aLIGO. Note that there will be short data gaps (1-2 min) from this afternoon in the VE and FMCS data when the connections between switches were moved.
A soluation may be either checkboxes for relevant interferometers (as was done in the iLog), or list all the subsystems under the "Task" menu when the LHO "Section" is chosen.
This would be useful for classifying tasks such as:
- A subsystem purchases a tool, e.g. romer arm pr camera, for use throughout a site.
- Pcal calibrates a power meter that will be used for all interferometers.
- A seismic event happens that affects all interferometers.
- IAS working in BSC8, installing corner cube
- Richard and SEI pulling cables
- SLC hoping for Wednesday installation
- Kyle looking for missing ConFlat flanges
- H1 PSL contractor coming Tuesday to lay down linoleum
- HAM1,2,3 - removing optics from HAM3
- Hanford Fire Department on site for testing
Correction: FMy was left off it's stops over the break as well. All suspensions in BSC8 are currently hanging and awaiting TFs in preparation for the handoff to SEI for their portion of testing.