Displaying reports 82481-82500 of 82933.Go to page Start 4121 4122 4123 4124 4125 4126 4127 4128 4129 End
Reports until 08:06, Wednesday 12 January 2011
H2 INS
hugh.radkins@LIGO.ORG - posted 08:06, Wednesday 12 January 2011 - last comment - 13:33, Wednesday 12 January 2011(473)
BSC7's Passive Internal Seismic Isolation(PISI) Stack Removed
Yes as Patrick logged, the PISI was removed yesterday from BSC7--CoreyG JimW Zack Rodney Chris & HughR

We pulled the dome before lunch.  There was quite a bit a stuck O-Ring during the separation but we got it back in place without any unusual effort requiring maybe 20-30 minutes.  No issues after that--remember to PULL the draw string when installing a flat cover!

After lunch we went for the PISI pull.  The bolts below on the inside of the Support Tubes were generally bound and did not un-thread readily as they did in MidY.  The top bolts were fine.  Relief came with a little lift from the crane but we didn't fine tune that too much.  There are only 18 bolts below and James powered through.  Again, as at MidY, no trouble pulling the Support Table from between the Tubes.  We pulled the Work Platforms before we exited.

Except for flange/o-ring cleaning/inspection and Dome balancing, the Chamber is ready to be buttoned back up.

The Stack is now by the LEA roll-up door and we be de-stacked today.  Good location for a look-see of the simpler times of iLIGO.

I don't have any photos but Dale video'd and photo'd the entirety; I'm sure we'll see something good from him.
Comments related to this report
dale.ingram@LIGO.ORG - 13:33, Wednesday 12 January 2011 (474)
I've attached three photos of the BSC7 stack removal.  The complete set of photos are available in ResourceSpace at https://ligoimages.mit.edu/?c=460.  The name of the ResourceSpace collection is LHO_BSC7_stackremove.
Images attached to this comment
H2 INS
patrick.thomas@LIGO.ORG - posted 17:36, Tuesday 11 January 2011 (472)
Ops Shift Summary
Unifirst delivery
Paradise water delivery
Mount's Lock & Key on site
Drain Surgeon on site
Interwest Systems on site

BSC7 dome and passive ISI removed
X1 SEI
james.batch@LIGO.ORG - posted 15:15, Tuesday 11 January 2011 (471)
Increased Java Heap Memory on SEI test stand workstation for Matlab
Increased amount of Matlab's java Heap Memory from default of 128M to 512M on the workstation attached to the SEI test stand.  This is to try to solve an error reporting that the java Heap Memory has been exhausted when a large test script was loaded.  The new value is probably too big, but I didn't see the error any more.  Note that the maximum value allowed is over 3G.
H2 INS
david.barker@LIGO.ORG - posted 14:26, Tuesday 11 January 2011 (470)
h1 psl epics turned on and burt restored

In preparation for the H1 PSL run tonight, we powered up the VME epics IOC rack (h1psl), the beckhoff controller box in the LVEA and the ethercat-OPC-EPICS system (h1pslopc). all IOCs were burt restored back to early Sep 2010. Epics records are resolving and green, but show zeros at the moment (needs more boxes to be powered up in the diode room?).

H2 INS
david.barker@LIGO.ORG - posted 12:08, Tuesday 11 January 2011 (469)
CDS file servers no longer dual ported machines

The two CDS file servers cdsfs0 and h2boot are no longer dual ported machines on both the CDS LAN and H2FE LAN. Clients on either lan now contact the remote file server via the cdsnat1 router. As mentioned in the  previous alog, routing tables are being changed using the new puppet configuration control system.

H2 INS
david.barker@LIGO.ORG - posted 12:01, Tuesday 11 January 2011 (468)
aligo CDS updates and reboots

performed upgrades and reboots of:

cdsnat0 (strawberry)

cdslogin

cdswiki

Routing tables on the nfs clients is being handled by the configuration control system (puppet)

MSR UPS was moved from the 10.1.0.0 iligo network to the new aligo admin lan.

LHO FMCS
kyle.ryan@LIGO.ORG - posted 10:58, Tuesday 11 January 2011 (467)
Removed BSC7 east door

John, Kyle -> Noted dome flange position shear relative to chamber flange for future reference (This dome had position-dependent annulus leak historically.  Will attempt to approximate position when joining dome back to chamber)

Kyle -> Decoupled cords and cables from gauge pair and annulus ion pump located on BSC7 dome.

Kyle, Chris -> Removed BSC7 east door.
LHO FMCS
mark.lubinski@LIGO.ORG - posted 07:35, Tuesday 11 January 2011 (465)
FMCS
Started a second stage of heaters in X and Y mid stations
Repaired broken temperature sensor(wall mount)in LVEA.
H2 General
jonathan.berliner@LIGO.ORG - posted 17:42, Monday 10 January 2011 (464)
Monday Ops Log
- Interwest Communications (?) comes to assist in running single-mode fiber optic line from OSB MSR to LSB LDAS.
- Oscar finishes baling tumbleweeds at ~13:20.
- Bolts loosened on BSC7
- Cleaning around BSC7 and HAM12
- Cryopump 1 is constantly alarming.  Kyle reports that it may be due to a crow chewing on a valve and subsequent freezing of the part.  Cryopump alarms are serious!  Whereas some Ion Pump alarms may be ignored during pumping, Cryopump alarms are always serious and should be reported immediately, to Kyle.
- One of the LVEA Zone 5 thermostats was malfunctioning, as it was reporting that the temperature jumped to >250 degrees F.  This was also confusing the HVAC servos.  Ski investigated and fixed the problem.
LHO FMCS
kyle.ryan@LIGO.ORG - posted 16:29, Monday 10 January 2011 (463)
Ice problems for CP1 and CP2 LLCV actuators
CP1 and CP2 experiencing problems with icing of the LLCV actuation components -> thawed using heat gun as temporary fix.  Will address as permanent fix as time permits.
LHO FMCS
kyle.ryan@LIGO.ORG - posted 16:25, Monday 10 January 2011 (462)
XBM vent
Kyle - Connected aux. pump cart to GV7 annulus and am pumping against closed valve*Spun-up XBM MTP*Vented XBM

Chris - prepped BSC7 east door for removal tomorrow
H2 INS
corey.gray@LIGO.ORG - posted 15:53, Monday 10 January 2011 (461)
BSC7: Installed Stop Links On Scissors Table .. & .. Dome/Door Bolts Removed
(Chris, Corey, Jim, Rodney, & Zach)

In preparation for this week's BSC7 iLIGO BSC SEI extraction, the Dome & Door bolts were pulled out of BSC7 (except for four for each connection).

John asked to check the orientation of the BSC Dome once we have bolts out (there were issues with the O-ring when this Dome was last installed).  From the top and referencing bolt holes, the Dome is roughly rotated counter-clockwise.  A side note is that the outer diameters of both flanges on this connection must have not had high tolerances, because these diameters aren't very circular---i.e. sections of Dome flange overhung the Chamber flange in non-circular ways.

As with BSC8, the Scissors Tables for the chamber were set to their midpoints and Scissors Table Stop Links were installed to keep them there.

Jim's pair of fall-arrest plates were installed on the Clean Room.
Logbook Admin General
jonathan.hanks@LIGO.ORG - posted 08:36, Monday 10 January 2011 - last comment - 08:34, Tuesday 11 January 2011(460)
aLOG update on 11 Jan 2011
The aLOG will be updated tomorrow.  This update will include the addition of a WYSIWYG editor, so you will be able to easily format your entries.

The LHO alog (alog.ligo-wa.caltech.edu/aLOG/) will be inaccessible for 5-30min on 11 Jan 2011 starting at 8:15 Pacific time.

The LLO alog will also be updated on 11 Jan 2011.  The GC admins at LLO will coordinate the time of that update.

A copy of this notice will be entered into the aLOG.
Comments related to this report
jonathan.hanks@LIGO.ORG - 08:34, Tuesday 11 January 2011 (466)

The update is complete. Please let me know about any issues that may come up. You may post them in the log under the section 'Logbook Admin' task 'bug'. There is a test logbook setup if you want to play with out touching the official record.

See https://gold.ligo-wa.caltech.edu/aLOG/

LHO FMCS
kyle.ryan@LIGO.ORG - posted 10:26, Saturday 08 January 2011 (459)
Can't view Vaccum Screen from Home
I can log onto blue remotely but can't view the vacuum screen displayed on VE terminal in control room???  
H2 INS
corey.gray@LIGO.ORG - posted 17:18, Friday 07 January 2011 (458)
BSC8 Scissors Tables Locked At Centered Position
(Corey, Hugh, Jim, Mitchell)
The Scissors Tables (and basically the entire Seismic Isolation System) were vertically adjusted such that the Scissors Tables were set to their "mid-point" elevations.  Shipping/Llot Links were installed to hold the Scissors Tables here (as we did for the H2 HAMs).  The Scissors Tables were actuated manually via a rod attached to a motor underneath the Scissors Table.  We needed a special key-ed tool to turn the crank and actuate the Scissors table.

We will do BSC7 next time we get a chance.
H2 General
michael.rodruck@LIGO.ORG - posted 16:03, Friday 07 January 2011 (457)
Ops Day Summary
Sock replaced on BSC7
KingSoft water on site for monthly service
Terri and Christina cleaned BSC7 and performed vacuum tests - we will need more tests next week
Richard to MX and EX
H2 General
jonathan.berliner@LIGO.ORG - posted 16:05, Thursday 06 January 2011 (456)
Thurs Ops Log
Highlights:
- HAM10 Door Re-Hung, Cleanroom moved to HAM12, doors taken off of HAM12
- Kyle notices LN2 issue

Other, times in PST:
0926 - "QMA" calls Control Room to solicit business
1032 - CS Air Handler Hot Deck Alarm (~90deg F)
1421 - Oscar done with tumbleweed bailing
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:17, Thursday 06 January 2011 (455)
HAM 10, 12 doors
Kyle, Chris, Jodi, Zak, Rodney, Ski -> 

Hung HAM10 North door, moved cleanroom from HAM10 to HAM12, removed HAM12 South and North doors. 
Displaying reports 82481-82500 of 82933.Go to page Start 4121 4122 4123 4124 4125 4126 4127 4128 4129 End