The IOP model ran for 24 hours after the one-stop fiber optic cable was replaced Tue. At noon today I started the user models (SUS FMY and FMX). So far, so good, but a bit early to declare victory.
We have all the lifting gear attached to the ISI and the Transport Rails positioned at the Chamber. The Spacers are attached to the Support Tubes. We will fly the ISI from the Diagonal to the South Bay in the morning and I expect to have the chamber all covered (I-Beams removed) by lunch. We didn't have any trouble positioning/rolling the A-Frames. We sealed up the chamber as best as possible with the rails in place--See photos: DevilDog Ed shows how easy it is to move the A-frames (001). Zack connects the back end of the Rail being steadied by Caleb to the Frame (005) followed by Ed securing the rail to the Middle Frame (006). The Chamber is now ready for the ISI to be nested in between the rails before the Front Frame is connected up (008). Meanwhile, MarkD confirms we are using Bumax bolts on the lifting pads while Scott double checks their location followed by precise torquing (004). Randy ran the crew & crane. Thanks-H
Today while working on the post creak bake realignment of HSTS PR2, we noticed a magnet was missing from the upper right position on the Intermediate mass. As far as we know, this magnet was not bumped, snagged by a wire, or was hit by a tool. The dumbbell is still firmly attached to the mass. There is no magnet material left glued on the dumbbell, suggesting the glue joint failed as opposed to the magnet being broken off. A replacement magnet will need to be installed on this mass.
- Richard/Dave/Vincent make H1 software changes, several reboots of front-ends and DAQ. - HAM2 ISI insertion: Cleaning began today. ISI will be inserted tomorrow or at a later date. - VE: EY pump-down ongoing. - PSL: Laser shut down intermittently today. New speakerphone installed. - H1 electronics area: Rolf running software tests. - EY: Richard's contracter has finished. - Ops: Ignore the "gpg: gpg-agent is not available in this session" message when decrypting files. - UniFirst did not arrive as scheduled yesterday, and I did not notice them at the gate today. - Thomas aligning OpLev at EY. - No safety meeting. - OSB doors locked at 16:15.
(corey, eric, hugo, jim)
#6
Horizontal L4Cs were installed and then Actuators were installed. Here are the S/Ns:
Actuators
Horiz L4C
Cabling was pinned out and connected for (4) of the Actuators
#7
Lockers assembled (not installed). Horiz L4Cs were staged on Stage0 (this will make installation of them much more easier than in-situ post Stage-1 install).
Horiz L4C
log-log plots - Turbo only in both cases. Some of the ENDY annuli are still vented.
Here are the two relevant pumpdowns underway. BSC8 (LVEA) has been under vacuum for 20 days. BSC6 at ENDY has been pumping only one day.
For comparison a 1999 pumpdown is also attached.
I will include log-log plots in a seperate alog entry.
Jonathan B.'s ops summary yesterday accurately described the status of the transit event through 18:00. We caught a break, however, and obtained unobstructed views during the span between 18:30 and 20:30. The attachment shows solar scope-meister Greg Mendell assisting some guests. Roughly 150 community members attended. Many came late in the day as the western sky cleared.
Bubba Gately took some nice shots of the BSC1 stack extraction that show the relationship between the piers, the crossbeams, the support tubes and the stack. View the collection in ResourceSpace.
Thanks to the Apollo crew-Zack MarkL Caleb & Randy No issues. The Support Table slipped right out and the stack is mostly separated and headed to the recycler. That is all the iLIGO stacks from the LVEA, just the two H1 ETMs remain.
- Cheryl, Mark, Zack, Mick, Chris, other support from Apollo The iLigo H1 ITMY was removed from BSC1 yesterday. The operation went without any major glitches. The minor glitch was that the adaptor plate was no where to be found, so we used 3 dog clamps to bridge the gap between the top of the lift table and the base of the optics cage, which worked well. The optic/cage combo is in the OSB optics lab, on the table with other deinstalled optics.
I built the IOP models for the following front ends: h1seih16, h1seih23, h1sush2a, h1sush2b. Unfortunately when starting these new front ends, the DAQ data from the PSL system was corrupted for several minutes at a time until we restored the H1 DAQ. For tonight we have turned off all the new front ends and are just running the h1psl0 system on H1. Only the PSL DAQ data was corrupted, the front end models themselves were not affected. The IO Chassis for these front ends are being constructed in the H1 EE room. A timing fanout was installed which runs off the new H1 timing master in the MSR (h1psl0 still runs from the H2 master).
The latest change to h2susb78 (FMY front end) was to swap out the one-stop PCI bus extender fiber optics cable between the IO Chassis and the computer. The IOP was restarted at noon, it is still running after 10.75 hrs.
Attached are plots of dust counts > .5 microns.
- BSC1: moving garbing room, setting up lazy susan. Cheryl de-installed ITMY, preparing it to be sent to KAGRA. ICC will commence from north side of biergarten. - BSC6: Long pump-down begins today, with Gerardo leading. - Praxair delivery for CP6 and CP8. - Electrical contractor working on DC power supplies at EY. - FMY electronics still misbehaving...Richard addressing. - Apollo grouting at H2 input, HAM7, MC legs. - PSL working on controls, DAQ. - Platt Electric makes delivery for Richard. - One Apollo delivery in the afternoon. - Transit of Venus broadcast in Control Room. Some visitors on site expected for LHO's special event. Unfortunately, the sky was overcast for the entire day, so the sun was not visible at LHO as of 18:00. Check back here on 8 Dec 2125, LHO's next chance. - OSB doors locked at 16:45.
I noticed condensed water vapor collecting at the exhaust of the QDP80 -> My measuring of the purge air dew-point prior to pumping yesterday was of the air exhausting into the room from the check valve (acting as a point-of-use pressure relief). This had been the nominal procedure until recent years after we had observed that the purge air drying towers could be "starved" in a maximum demand case, such as full-open purge air valves in conjunction with one or more chamber doors being removed. We found then that the measured dew-point of air sourced only from the VE (during pressure equalization "blow-down" prior to pump-down) could be different than that of the air sourced only from the purge air header. This could result from those scenarios where the drying towers were starved at the time that the door(s) were reinstalled. Once the doors are installed, there is minimal air exchange between the relative "wet" air in the VE and the relatively "dry" air that the, now not-starved drying towers, were supplying to the header. This has not been observed at the Corner Station as we haven't been able to "starve" the drying towers with nominal purge air demands. We intended to make it standard practice to measure the dew-point of the air exhausting into the room during the "blow-down" step when preparing to pump down a -mid or -end volume.
See if I can post a plot......
Attached are plots of dust counts > .5 microns.
Powered down HEPI valve drive chassis and ±24V power going to HEPI Interface modules. Replaced R13 from a 2 KOhm resistor to a 33.2K Ohm resistor on D080521 units. This changes the gain of the L4C channels from 22 to 333, per document E1200420-v1. Tested units after mods, gain ~330. Serial Numbers of units modified: S0900178, S0900236, S0900202, and S0900234. Will reinstall units tomorrow morning.
All units reinstalled and powered up.
The set of 6 horizontal L4Cs received in shipment load #3880 were huddle tested this morning,
We noted a few points that we need to be careful about in order to perform this test correctly:
Spectra are attached.
Attached is a photo of the lined-up L4C set up.
Results are posted under the SVN at:
https://svn.ligo.caltech.edu/svn/seismic/Common/Data/aLIGO_L4C_TestData_LHO/