Thu Feb 22 08:06:46 2024 INFO: Fill completed in 6min 42secs
TITLE: 02/22 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: Maintenance
Wind: 3mph Gusts, 2mph 5min avg
Primary useism: 0.05 μm/s
Secondary useism: 0.23 μm/s
QUICK SUMMARY: Calm morning, prep for HAM8 work today and some cleanup from CDS switch work yesterday.
Current issues:
Corner station HEPI pump controller EPICS IOC does not connect, we suspect network port issue with h1hpipumpctrll0. This is the reason for the 31 disconnected channels on the EDC.
Camera servers will be rebooted today to get all the digital cameras back online.
FMCS connection to the corner station maintenance building and chiller not operational, mech room switch replacement scheduled this morning.
Jonathan, Erik, Dave, Tony, Ryan, Patrick, Dan Today we transitioned to all the new switches in the MSR. The order was: sw-msr-ops - this is the workstation and FOM switch sw-msr-server3 - auxillary servers, epics gateways, WAP controller sw-msr-server2 - auxillary servers, back channel connections from the file servers sw-msr-core - the main core network Dan Moraru came up to help us make sure the file servers where is a safe state when before we touched switches related to them. On the network side we ran into a few configuration issues but have been able to fix those. A few ports didn't get put on the right vlan, that was fixed. We need to enable directed broadcasts on a number of networks to allow the EPICS channel access broadcasts to go through. The fmcs epics ioc machine had a bad default gateway, we had to correct that before it would work (we do not know why or how it worked yesterday). Some issues with loose cables that were causing connectivity issues for fmcs. Tony, Ryan, and Dave did some work on cleaning out old items from the racks. We removed an old fujitsu switch, a broken qlogic switch, the old (dead) router, some retired servers, and the old sw-msr-ops, sw-msr-spare, sw-msr-server1, sw-msr-server3 switches. Tomorrow we will remove the old core switch and do more cleanup. We may have short outages, of some systems, but do not expect a general outage. The mx, my, and mechancial room switches are passing data, but we are not able to log into them. They were working on the test bench last week. I have racked up a test switch and connected it to the core (via a temporary link on port 48) to try and replicate the setup of these switches and get this issue figured out. We went through the configuration of all the icx switches and made sure that we had a consistent spanning tree setup. This should help clear up some odd network issues we have seen in the past. We also moved the connection to the file servers directly onto the core switch. We had front end system crashes today. Dave or Erik will add a comment detailing those issues. Dave restarted the EDCU while we were doing recovery of the front end systems to force it to reconnect to EPICS channels while we worked on issues with the fmcs ioc.
h1seib1 h1seib3 h1seih7 h1asc0 h1lsc0 h1oaf0 all crashed at approximately 20:00 UTC while switches were being swapped out in the MSR.
h1susey h1seiey hsusex, historically touchy front ends, crashed while recovering the others. h1seiey got into a bad state, continuously logging dolphin errors whcih disrupted the timing of the models and had to be restarted.
After recovering the front ends, a dolphin timing glitch was trigged when "unfencing" dolphin ports. The glitch affected models across the corner station. Models on h1susb123, h1sush2a h1sush34 h1sush56 had to be restarted.
Today's activities: - HAM7 pumpdown status: ~9.7E-7 Torr - Corner pumpdown: HAM6 turbo was switched on, and valved in; it helps a lot - as anticipated - especially with the semi-isolated HAM6 volume. The pressure is ~1.1E-6 Torr, ~26 hours after the HV pumping started - EX pumpdown status: 3.1E-8 Torr: the post-vent RGA scan is ready; the results show that the chamber is OK - compared with past RGAs. Another bakeout is necessary, see details here: https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=75918. The GV will remain closed during FAC works (1-2 weeks) - HAM8 works: the chamber closing and pumping is now postponed to early-next week
I just ran a script that sweeps SHG crystal temperature. This test requires TTFSS, PMC, and SHG locked. PLEASE DO NOT TOUCH THE SQUEEZER. PLEASE WALK GENTLY NEAR SQZT0. The duration of the script is ~2hrs. Star time is 16:40.
The script sets the crystal temperature from 29C - 41C at 0.5C increment. We hope to replicate the phase matching curve done by a SURF student Nathan Zhao (P1400193 Fig 23). The script can be found in /opt/rtcds/userapps/trunk/sqz/h1/scripts/SHGphasematch.py
Here's our Sinc function. Not sure what's going on with the dip in the middle but I believe we have been operating at a good place (the right peak, ~36C). Although after the temperature scan the green production didn't come back to where it started. I moved the crystal temperature to the middle of the sinc function to confirm that the conversion efficiency really went down. I then moved the crystal temperature to the left peak of the sinc function (~34 C) and managed to recover 10mW of green.
Something else is drifting as well and it seems to have nothing to do with me. PMC PZT ran out of range this morning so I expanded the scan range down to 0V temporary (the current lock triggered at ~25 V). SHG PZT is still drifitng as I'm writing this alog while the green conversion goes down with it. For now I decidede to park the crystal temperature at 33.78C. Changes accepted in the SDF.
Attached a plot with SHG red transmission.
TITLE: 02/21 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
CDS work has largely concluded and suspensions/seismic have been put back into their normal GRD settings.
With some exceptions:
Additionally, the LVEA is now LASER SAFE
LOG:
Time In (PT) | Time Out (PT) | System | Name | Location | Lazer Hazard | Task |
7:50 | 8:30 | FAC | Kim, Karen | FCES | N | Technical Cleaning |
ONGOING | ONGOING | SAF | LVEA is Laser Hazard | LVEA | Yes | LVEA is Laser HAZARD |
8:30 | 8:50 | CDS | Jonathan | Mechanical Rm | N | CDS Work |
8:30 | 10:00 | FAC | Karen | EY | N | Technical Cleaning |
8:30 | 8:56 | VAC | Jordan | LVEA | Yes | Pump check |
9:00 | 9:15 | SUS | Randy | LVEA | Yes | Inventory Round |
9:02 | 10:41 | SUS | Jason | LVEA | Yes | West Bay FARO Work |
9:06 | 9:24 | SQZ | Preet, Camilla | LVEA | Yes | Change Hartmann Power Supply |
9:09 | 10:41 | SUS | Ryan C | LVEA | Yes | West Bay FARO Work |
9:12 | 11:12 | VAC | Janos | LVEA | Yes | Pump check |
9:15 | 11:03 | SUS | Randy | MX, MY | N | Inventory Round |
9:49 | 10:50 | SQZ | Julian, Camilla | Optics Lab | N | Spare SHG Build |
9:55 | 10:20 | Nutsinee | LVEA | Yes | Table Work | |
9:55 | 10:22 | FAC | Richard | LVEA | Yes | Walkabout |
10:13 | 11:34 | FAC | Kim | EX | No | Technical Cleaning |
10:15 | 11:10 | VAC | Jordan, Gerardo | LVEA | Yes | Climbing on HAM6 |
10:00 | 11:03 | FAC | Karen | LVEA | Yes | Technical Cleaning |
10:30 | 11:10 | SUS | Mitchell | EY, EX | N | Dust Monitor FAMIS Task |
10:54 | ... | SEI | Fil | FCES | N | Seismic Chassis Work |
11:03 | 11:30 | FAC | Karen | Wood Shop | N | Technical Cleaning |
11:30 | 11:42 | FAC | Karen | MY | N | Technical Cleaning |
11:38 | 15:41 | CDS | CDS OUTAGE | CTRL RM | N | CDS OUTAGE |
12:02 | 12:26 | VAC | Janos | LVEA | Yes | Pump check |
12:47 | 13:10 | VAC | Travis | LVEA | Yes | LVEA Laser Safe Transiiton |
13:16 | 14:16 | SQZ | Julian, Camilla | Optics Lab | N | SHG Work |
13:17 | ... | SUS | Randy | LVEA | N | Septum into High-Bay |
13:21 | 13:50 | VAC | Jordan | LVEA | N | HAM6 Gate Valve |
13:21 | 14:26 | VAC | Gerardo | LVEA | N | HAM6 Gate Valve |
13:27 | ... | VAC | Travis | LVEA | N | Relay Tube Assembly |
14:14 | 15:00 | CDS | Jonathan | Mechanical Rm | N | Switching Switches |
14:26 | 15:01 | VAC | Janos | LVEA | N | Pump Check |
14:30 | 14:34 | SUS | Austin | LVEA | N | Parts |
Randy, Jim, Eric, Mitchell, Tyler
Last week work on the EY wind fence wrapped up. Several of the horizontal cables came loose alog 75543 in the high winds back in January. This likely happended due to lack of proper torque on the cable clamps.
The horizontal cables were re-strung and then tentioned. All horizontal cables received a third cable clamp. Lock tight was added and the clamps were torqued to 45 foot pounds. In some cases the smaller cable that loops through the gromets and around the horizontal cable needed to be addressed. Although it looked bad there was very little damage. One panel had the veritcal edge torn away from the field of the panel. This means that the vertical looping cable is no longer connecting the panel to the upright post for about half the panel. The horizontal looping cable is still attached through the gromets and attached to the upright post.
WP 11707
SQZ Chassis 5 modified to add missing ground connection for binary input and output signals. Ground cable connected from EL2124 (Middle Rail, Terminal 2, Signal labeled "GND") to Adapter 6 (Pin 19).
Serial Number S2300256
F. Clara, D. Sigg
CDS Outages are Ongoing
Time In (PT) | Time Out (PT) | System | Name | Location | Lazer Hazard | Task |
7:50 | 8:30 | FAC | Kim, Karen | FCES | N | Technical Cleaning |
ONGOING | ONGOING | SAF | LVEA is Laser Hazard | LVEA | Yes | LVEA is Laser HAZARD |
8:30 | 8:50 | CDS | Jonathan | Mechanical Rm | N | CDS Work |
8:30 | 10:00 | FAC | Karen | EY | N | Technical Cleaning |
8:30 | 8:56 | VAC | Jordan | LVEA | Yes | Pump check |
9:00 | 9:15 | SUS | Randy | LVEA | Yes | Inventory Round |
9:02 | 10:41 | SUS | Jason | LVEA | Yes | West Bay FARO Work |
9:06 | 9:24 | Preet, Camilla | LVEA | Yes | Change Hartmann Power Supply | |
9:09 | 10:41 | SUS | Ryan C | LVEA | Yes | West Bay FARO Work |
9:12 | 11:12 | VAC | Janos | LVEA | Yes | Pump check |
9:15 | 11:03 | SUS | Randy | MX, MY | N | Inventory Round |
9:49 | 10:50 | SQZ | Julian, Camilla | Optics Lab | N | Spare SHG Build |
9:55 | 10:20 | Nutsinee | LVEA | Yes | Table Work | |
9:55 | 10:22 | FAC | Richard | LVEA | Yes | Walkabout |
10:13 | 11:34 | FAC | Kim | EX | No | Technical Cleaning |
10:15 | 11:10 | VAC | Jordan, Gerardo | LVEA | Yes | Climbing on HAM6 |
10:00 | 11:03 | FAC | Karen | LVEA | Yes | Technical Cleaning |
10:30 | 11:10 | SUS | Mitchell | EY, EX | N | Dust Monitor FAMIS Task |
10:54 | ... | SEI | Fil | FCES | N | Seismic Chassis Work |
11:03 | 11:30 | FAC | Karen | Wood Shop | N | Technical Cleaning |
11:30 | 11:42 | FAC | Karen | MY | N | Technical Cleaning |
11:38 | ... | CDS | CDS OUTAGE | CTRL RM | N | CDS OUTAGE |
12:02 | ... | VAC | Janos | LVEA | Yes | Pump check |
Yesterday we installed a new switch in the mechanical room but had to revert the setup due to issues with data drop outs. This appears that the fiber run to the switch is unable to support 10G. Today I moved the connections back to the new switch and am running the switch at 1G instead of 10G. When we put the new core switch in this switch (sw-mech-aux) will need a slightly different configuration. I have pre-programmed that on a different fiber port. So when we put the new core switch in we will need to go to the mechanical room and move the optic and fiber from port 1 to port2.
As a reminder we are continuing work on the CDS network today. Today is the day we are generally disruptive. The control room and will be impacted and unusable at times today. The main CDS network will also be interrupted for periods today. The main interruption of the network will not be first thing. However the control room workstations will interrupted in the first step.
Wed Feb 21 08:04:22 2024 ALERT: Fill done (errors) in 4min 19sec
Before the fill I noted the TCs were very high, +35C. I raised the trip temp to -60C, but as it happened it turned out not to be high enough and TC min was -56C. With the discharge line pressure up at 0.7 and the TCs flatlined, I manually canceled the fill.
Gerardo thinks there is ice build up, the dewar was filled yesterday and I noticed vapor at the discharge.
Today's activities: - HAM7 pumpdown status: ~1.1E-6 Torr - HAM7 Annulus system pumping cart has been switched off, it is pumped now only by its Ion-pump - Corner pumpdown: the OMC and Y-manifold Turbos have been switched on, roughing pump has been switched off; HAM6 turbo is coming tomorrow. The pressure is already ~4E-6 Torr - All the metal valves have been closed in the corner LVEA - EX pumpdown status: 3.2E-8 Torr: the post-vent RGA scan is ready, the results will be in the comment comment section, once they are published. The comparison with past RGAs is also coming next week. If the results will be considered satisfactory, the Ion-pump will be valved in. The GV will remain closed during FAC works - HAM8 works: the chamber was vented with purge air; the Annulus system was vented with Nitrogen; The Y+ door has been taken off; the Y- 12" blanks have been taken off
EX RGA scans added to the DCC at T2400018
The RGA tree was rebuilt and baked at 150C for 7 days, from the collected scans it looks like the RGA could use more baking at a higher temp. This a known issue with the new PrismaPro RGA that it takes a very high temp (250C or higher) to fully clean it up, but we are limited by the KF connections to the turbo pump on the RGA tree.
Baking will resume this week, and scans collected again next week.
Nutsinee, Vicky, Daniel, Naoki
We brought back the SQZ laser power (PMC input power) from 30mW to 670mW and locked the PMC with s-pol. The PMC trans power is 420mW and the PMC transmissivity is 60%. So all the power downstream of PMC reduced by 40%. The PMC TRANS DC POWERMON is calibrated into 420mW.
Then we aligned SHG. The SHG mode matching is 82%, which is slightly lower than before.
To increase the SHG IR injection power, we adjusted HWP for SHG path. The SHG IR injection power is now maxed out at 200mW. The SHG GR DC POWERMON is 37mW, which is lower than before 40-60 mW.
To increase the CLF power, we replaced the pick off mirror just before the CLF fiber from R=10% to HR mirror. The CLF power before the fiber is 135uW and the CLF REFL power in SQZT7 is 20uW. The CLF LAUNCH DC POWERMON is calibrated into 135uW.
Attached a quick power budget note of the current SQZT0, a new SHG scan, and a PMC transfer function locked with s-pol (2.3 kHz UGF). CLF alignment into the AOMs isn't great at the moment. We replaced MR5 with a mirror instrad of a 10% reflective optic. Seed and Pump fiber alignment hasn't been touched. A proper drawing to follow.
Squeezed in a few more power measurements before the Corner Station Boost Fest. It appears we have lots of back reflection rejected by the FI. The green could have confused the power meter that is set to 1064. Next time we could put a narrow band filter on to measure exactly how much green is coming back towards the FI instead of the launch fiber.
TITLE: 02/21 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
Primary Ongoing Activities
Control Room Log (02/20) so far..
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
19:22 | SAF | LVEA is Laser HAZARD | LVEA | Yes | LVEA is Laser HAZARD | 03:59 |
16:23 | VAC | Gerardo, Jordan | LVEA | Yes | Vacuum Checkup | 16:40 |
16:46 | CDS | Fil, Ryan S | EX | N | CDS Work | 18:21 |
16:47 | CDS | Tony, Jonathan | EX | N | CDS Work | 18:21 |
16:53 | CDS | Erik | Control Rm | N | Dolphin Fencing EX | 17:13 |
17:01 | VAC | Jordan, Janos, Gerardo | FCES | N | HAM8 Vent | 20:18 |
17:07 | FAC | Karen | EY | N | Technical Cleaning | 17:55 |
17:07 | VAC | Kim | EX | N | Technical Cleaning | 17:45 |
17:29 | SQZ | Camilla, Vicky | FCES | N | Move SQZT8 Out of the way | 18:29 |
17:44 | FAC | Kim | FCES | N | Technical Cleaning | 18:44 |
17:45 | SQZ | Nutsinee, Naoki | LVEA | Yes | SQZT Work | 20:15 |
17:55 | EE | Marc, Fernando | CER Mezzanine | N | Looking for a temp gun | 18:00 |
18:00 | EE | Marc | H2 Building | N | Looking for a temp gun | 18:03 |
18:17 | FAC | Chris | FCES | N | Helping tech clean | 21:13 |
18:21 | CDS | Tony, Jonathan, Fil, Ryan S, Dave | MX, EX | N | CDS Work | 19:28 |
18:38 | SQZ | Daniel | LVEA | Yes | SQZ Work | 20:15 |
18:57 | EE | Marc | LVEA | Yes | Checking on activity | 19:17 |
19:23 | FARO | Ryan C | LVEA | Yes | Water level check | 19:34 |
19:29 | CDS | Tony., Jonathan, Ryan S, Dave | FCES | N | CDS Work | 20:37 |
19:48 | CC | RyanC | CER | N | Handheld DM checks | 19:51 |
20:21 | VAC | Janos | LVEA | Yes | Tool Pickup | 20:28 |
20:29 | SUS | Jim | EX | N | BRS Centering | 21:14 |
20:38 | CDS | Tony, Jonathan, Dave | EY, MY | N | CDS Work | 22:40 |
21:01 | EE | Marc, Jabari | MY | N | Parts | 22:00 |
21:07 | VAC | Jordan, Gerardo, Janos, Travis | FCES | N | HAM8 Vent | 22:19 |
22:08 | CDS | Ryan S, Fil | EY | N | CDS Work | 22:08 |
22:20 | EE | Fil | FCES | N | Cable Repair | 23:16 |
22:25 | VAC | Janos, Gerardo | LVEA | Yes | Tubopump/Vacuum Stuff | 00:04 |
22:42 | CDS | Tony, Jonathan, Dave | Mechanical Room | N | CDS Work | 23:42 |
23:12 | FARO | Ryan C | LVEA | Yes | Faro prep for tomorrow | 23:22 |
23:17 | EE | Fil | LVEA | Yes | Terminating Beckhoff network cables | 00:17 |
23:23 | TCS | Ibrahim | Mech Room | N | Check TCS chillers | 23:52 |
The issue we had with sw-mech-aux appears to be an issue with the fiber. The fiber run is not capable of reliably running 10G at its current distance. I replaced the link with a 1G link and it appears to be stable with the new switch.
Fil, Luis, Camilla. FRS 26828#c11 Previous troubleshooting in alog 74951, 74750.
Today Fil went onto the HWS table and verified the HWS cameras are connected straight to the external power supply (photos in FRS26828#c8) via cables connected together. The HWS camera fiber CLink box is powered by the HWS breakout chassis D1200934 (originally designed to power cameras too).
Fil theorized that the HWS grounding is due to the power supply to fiber CLink connection grounding the cameras! With a multi-meter, we verified the HWS camera is grounded to the table when the CLink power cable is connected but when we disconnect CLink power, the camera is not grounded to the table (has Kapton tape and plastic bolts).
Step 1 (Completed): I removed the grounding cables from the HWS external power supply as Luis suggested in FRS 26828#c11, to avoid us holding the cameras negative terminal at mains ground. Photo of current connections attached.
Step 2 (Planned): After verifying step 1 doesn't effect the combs (need overnight "quiet" data), Fil will make a new cable to power both the camera and CLink's via the external supply (14V is fine for both).
Preet, Camilla
It appears changing the cabling of the external power supply has removed/reduced the comb: compare blue trace before cabling change to red trace afterwards change in attached plot.
To verify this, we undid the cabling change, back to the old configuration this morning at 9:30am and turned the camera back to 7Hz each, we'll later check if the comb reappears.
Preet, Camilla, FRS 26828
With the swap back to the old cabling, we confirmed that the comb came back, see Feb 22nd data in attached plot. This morning I changed the cabling back to the "quiet" version, photo attached.
Question for others, is the old cabling expected to push noise into DARM or is there an unknown coupling? Tagging PEM, CDS, Detchar.
Have you try using a different power supply or low the voltage to +12v? the camera also works with +12v and the rcx c-link only required +5v supply.
The previous timing master which was again running out of range on the voltage to the OCXO, see alogs 68000 and 61988, has been retuned using the mechanical adjustment of the OCXO.
Today's readback voltage is at +3.88V. We will keep it running over the next few months to see, if it eventually settles.
Today's readback voltage is at +3.55V.
Today's readback voltage is at +3.116V.
Today's readback voltage is at +1.857V.
Today's readback voltage is at +0.951V.
Today's readback voltage is at -2.511V
Naoki, Camille, Julian, Rahul
Summary: We measured beam profiles in HAM7 and HAM6 using the SQZ beam, after the PSAMs offloading work from 75677 75709 and the alignment work from 75732. We noticed that there is a lot of astigmatism on the beam in HAM6, but not in the HAM7 location that we were able to reach with the profiler.
Details:
In HAM6 we measured at three locations marked by the letters a,b,c in the sketch that Julian will attach. The red lines in the sketch show the irises.
Location 6A is 1.75 inches from the iris, Location 6B is 2 inches from the iris (closer to OM1). At location 6C we measured the beam in reflection off OM1, 23.25 inches after OM1. (The fast shutter is further in the -Y direction in chamber than what is shown in the CAD drawing). We also would like to measure at position 6D, once the second iris is removed.
We also measured beam profiles on the -X side of the HAM7 table, location 7A is 6.25" in the +X direction (closer to ZM5) from the iris, 7B is 8.25" from the iris in the + X direction, and location 7C is 12" from the iris in the +X direction. We weren't able to move the profiler further into the chamber without blocking the beam heading towards FC1.
We measured 13.5% widths, with A1 as the vertical axis and A2 as horizontal.
location | ZM4 PSAMs strain gauge [V] (PZT request [V]) | ZM5 PSAMs [V] | A1 Width [um] (standard deviation) | A2 Width [um] (standard deviation) |
6B | 0.82 (0) | -4.14 (0) | 1392 (8.7) | 1573 (9.9) |
6B | 4.38 (100) | -4.14 (0) | 1406 (7.3) | 1584 (6.3) |
7B | 4.39 (100) | -4.14 (0) | 2001 (6.4) | 2017 (6.1) |
7B | 1.0 (0) | -4.14 (0) | 1928 (5.6) | 1924 (5.9) |
7B | 0.98 (0) | -0.52 (100) | 2200 (8.2) | 2212 (9.4) |
7B | 4.31 (100) | -0.52 (100) | 2276 (9.5) | 2303 (9.3) |
7B | 8.49 (200) * | -0.52 (100) | 2363 (11.0) | 2412 (13.8) |
7B | 8.53 (200) | 3.57 (200)* | 2611 (9.0) | 2691 (7.2) |
7B | 5.74 (100) * | 3.59 (200) | 2539 (13.7) | 2603 (18.1) |
7A | 5.72 (100) * | 0.64 (100) | 2387 (13.5) | 2446 (13.1) |
7C | 5.715 (100)* | 0.63 (100) | 2374 (11.0) | 2415 (9.5) |
6A | 5.7 (100) * | 0.625 (100) | 2074 (9.9) | 1611 (7.4) |
6C | 5.7 (100) | 0.612 (100) | 1670 (10.2) | 1618 (7.0) |
* strain guage still drifting
Stll left to do:
Useful distances from Don:
Don Griffith sent us some useful distances in HAM7 which are useful for interpreting these measurements, based on the CAD model that he updated in in March 2022 based on the as built photos of HAM7 (D1900365-v1).
Attached are new and final sketches (these should be used for future analyses) of the beam profiler positions with distances.
Note: we measured a distance in HAM7 from the edge of the table to ZM5 of 1841.5mm, whereas Don Griffith CAD model shows a distance of 1822.7mm.
Attached are screenshots of the beam profile measurements. The screenshots are labeled to indicate position, ZM4 voltage, and ZM5 voltage.
Attached is the sketch of HAM6 and pictures of the beam profiler position.
Sheila, Naoki
We measured several distances as follows.
From first iris to OM1 in HAM6: 53.75''
From ZM5 to second iris in HAM7: 68.5''
From edge of table to second iris in HAM7: 4''
Then we removed the irises in HAM6 and measured the beam profile at the position of second iris, which is 13.5'' from OM1.
A1: 1285 (6.7)
A2: 1426 (9.2)
We also measured the seed power at several locations. The seed coming out of HAM7 is 1.05 mW and the seed in HAM6 is 0.71 mW, which makes sense since the SRM reflectivity is 68%. The seed reflected by OPO without dither lock in SQZT7 is 30.5 mW.
We tried to take a photo of the beam and the ruler in ZM5, but it was difficult to read the ruler by camera or our eyes so we roughly measured the beam position in the baffle of ZM5. The hole diameter of the baffle in ZM5 is ~3 cm and the beam is ~1 cm below the top of the hole so the beam in ZM5 is higher than the center of the hole of the baffle.
The beam profile measurement in 75770 was done at 6D in this figure. The ZM4 and ZM5 PSAMs strain gauge [V] (PZT request [V]) are as follows.
ZM4: 5.68 (100)
ZM5: 0.52 (100)