[Rahul, Keita, Betsy, Koji]
Preparation work to extract the existing OMC has been completed. We will continue with the OMC extraction tomorrow morning.
The overall work procedure for the OMC replacement is summarized in G231106 https://dcc.ligo.org/LIGO-G231106.
= OMC shroud panel removal =
While waiting for the beam from the squeezer to come, we started the removal of the OMC shroud panel in parallel. The work was done along with the procedure E1600164.
The removed panels were placed on a stainless steel table in the HEPA booth of HAM6 (Attachment 1). The panels were not covered to prevent accidental placement of objects on them.
During the work, a beam dump was removed from the table to make the removal work possible. This beam dump is to kill one of the weak transmissions of the OMC.
Betsy took the photo record of the location, but it is safely trivial how it should be aligned.
= SQZ beam marking and alignment =
The beam was delivered to HAM6 and was pinned down with two irises on the ISI table.
The irises were placed just after the beam entered HAM6 (next to OM2) and just before OM1 (next to the fast shutter).
This means that these indicators are not affected by the alignment in HAM6.
They were placed by eyeballing, so their precision was as such. By default, both the irises were set to the maximum opening.
Next, the beam alignment was servoed towards the WFS heads using the DC centering ASC loops.
As soon as the control was applied, both QPDA and QPDB of OMC showed significant signals with total light level of ~1e-3 (Attachment 2).
When the light was blocked (at the squeezer?), the value dropped to almost zero, confirming that this was a real beam.
This is very good news as we'll be able to find the beam arrival using the OMC QPDs when we try to align the new OMC.
= Holding suspension mass =
Next, we proceeded to hold the suspension masses. Rahul and Koji worked in the chamber on the ISI table for the following operations.
To hold the intermediate mass:
Then, moved onto fixing the OMC:
= Removing the electronic cables from the OMC =
Upon removing the electronics cables, one person held the cable harness on the OMC breadboard to prevent the OMC from wobbling too much.
The removed cables were wrapped around the top part of the suspension frame to keep them out of the way of the further work.
At this point, it was just at 5pm, so we exited from the chamber.
Next Steps:
TITLE: 01/22 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC (covering for the latter half of the shift)
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: HAM7 irises are in place, OMC work in HAM6 is ongoing.
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
16:32 | fac | randy | lvea | n | furniture moves & misc | 19:29 |
16:35 | fac | karen.kim | ham | n | cleaning around HAM7 | 18:21 |
16:36 | vac | jordan.VAC_crew | HAM7 | n | HAM7 doors finishing | 19:34 |
16:39 | Site | jason.ryanC | WestBay | n | FARO surveying | 19:58 |
16:48 | ee | fil | east bay | n | cable search | 17:28 |
16:52 | LHaz | LHO | EX | YES | Laser HAZARD!! | 17:57 |
16:59 | isc | camilla | optics lab | n | prep for HAM7 | 17:45 |
17:25 | Pcal | tony | EX | n | PCal closeout | 18:07 |
17:40 | CC | mitch | HAM6.7 | n | Distrib. Contam Control kit | 17:41 |
17:49 | sus | rahul | remote | n | HAM6 SUS meas | 18:57 |
18:03 | SLiC | mitch | EX | n | Prep for Baffles | 18:44 |
18:51 | sei | jim | HAM7 | n | Locking HAM7 | 19:02 |
18:59 | omc | koji | HAM6 | n | Prep for OMC swap | 19:56 |
19:08 | isc | camilla | lvea | y | LVEA to laser HAZARD!!! | 19:47 |
19:36 | sus | rahul | HAM6 | n | prep for OMC swap | 19:56 |
19:44 | SUS | austin | remote | n | Moing ZM for HAM6 work | 20:18 |
19:46 | ISC | ISC | LVEA | YES | LVEA laser HAZARD!! | 01:46 |
19:48 | isc | daniel | HAM6 | y | laser for HAM6 alignment | 20:23 |
20:20 | SQZ | Sheila.Julian.Naoki.Vicky | HAM 7 | YES | SQZ work and HAM7/SQZT7 | 23:58 |
20:28 | sus | rahul | remote | n | HAM6 sus TFs cont. | 20:59 |
20:59 | FAC | Randy | EY | n | Moving equipment to EY for wind fence | 23:15 |
21:03 | eng | Betsy, Ibrahim | LVEA | y | Vent help | 21:39 |
21:15 | CDS | Fil | EY | n | Checking on equipment | 21:54 |
21:38 | FAC | Tyler | Outbuildings | n | 3IFO inventory | 23:58 |
21:42 | IAS | Jason, RyanC | LVEA - W | y | FARO work | ongoing |
22:01 | ISC | Koji, Keita, Rahul | LVEA - HAM6 | YES | OMC swap | ongoing |
22:02 | ENG | Betsy | LVEA | YES | Vent help | ongoing |
22:20 | LAZ | Tony | EX | N | Transition VEA to upgrade laser safe | 23:18 |
22:53 | VAC | Janos, Travis | MX | n | Hepta filter install and test | 23:05 |
23:06 | VAC | Travis | LVEA | - | Purge air | 23:12 |
23:14 | - | Richard | LVEA | y | Support | 23:26 |
23:14 | VAC | Gerardo, Jordan | EX | n | GV20 close and purge on | ongoing |
23:16 | PEM | Robert | EX | n | Setup vibrometers | ongoing |
23:58 | SQZ | Naoki, Vicky | LVEA - HAM6 | YES | Vent work | ongoing |
The following high voltage power supplies were powered on this morning:
1. HAM7 - PZT and P-Sams
2. HAM6 - PZT and Fast Shutter
The pressure interlock system bypassed.
We also turned back on the HAM7 SQZ OPO TEC servo, turned off for vent as described in M1300464.
The reasoning for the TEC servos being turned off is to protect them from trying to keep a stable temperature while vent rather than because they are High voltage.
I forgot to revisit this in 2022 so the HAM7 SFI1, SFI2, and HAM6 OFI TEC servos were left on during this vent. We'll look at at their behavior to see if this should be kept in the procedure.
Camera 20 failed and was restarted. The server runs on h1digivideo1, but was not being monitored by monit. That's been corrected.
The Calibration group has been working hard to produce and release the LHO uncertainty budget for the first half of O4a. The case at LHO has proven to be significantly more involved than LLO's for a variety of reasons.
20230620T234012Z
and regenerating the uncertainty envelope and the consistency check with the systematic error lines at GPS 1371394818 resolves the discrepancy. See uncertainty_consistency_check_H1_1371391218_1371394818_GDS-CALIB_STRAIN.png.
TITLE: 01/22 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
Big Tasks Of The Day: (1) HAM7 doors taken off, (2) HAM7 work begins, & (3) Laser Hazard in LVEA / EX is back to SAFE
LOG:
When looking over flows and temperatures at the LVEA, I noticed that the supply of AHU 2 was low and Supply Fan 4 was manually disabled. The most likely cause of this is from our quarterly lubrication which took place last week and the fan most likely never got brought back up. I physically visited the fan to verify it was all-clear and brought it back into service. T. Guidry
Ibrahim, TJ, Camilla, Naoki,
Looking at how the ZM4,5,6 alignment has shifted both with the vent and recent temperature changes in the LVEA.
Attached is ZM4/5 P/Y alignment since the last time we were SQZing to vented now, there is large changes of ZM5 (470urad in Pit and 230urad in Yaw). Alignment sliders haven't changed but SQZ ASC would have been changing some alignment when the IFO was locked.
ZM6 has large changes (1300urad in Pit and 280urad in Yaw). Currently DAMPED but alignment sliders are the same. Edit: DAMPED turns off the alignment sliders, once Austin brought back to ALIGNED it had moved <100urad.
We expect some changes from bouyancy of air. The HAM7 SUS are currently "aligned" with the doors being taken off HAM7. Jim hasn't locked the ISI yet. Looking at ZM4,5,6 alignment, last vent, IFO locked, and now.
Ibrahim is looking at temperatures and alignment since our last vent.
Vicky found that the SQZ beam was different on the RLF QPDs and not on the SQZT7 H1:SQZ-OPO_IR_PD_DC_POWER. Sheila checked that the OPOS doesn't seem to have changed much (<5um, 0.005urad if channels are calibrated), plot attached
Details of realignment and finding the beam in 75509.
Mon Jan 22 10:04:41 2024 INFO: Fill completed in 4min 37secs
In order to further test out the environment automation for the SEI_ENV node, I've removed all state requests of its subborndinate nodes to allow this node to make it's transitions without actually doing anything. In other words, SEI_ENV will change state, but nothing will actually be changing outside of this node. We will run it like this for the duration of the break.
If there are model restarts for any of the ISI models, it would be a good idea to re-request the SEI_CONF state of SC_OFF_NOBRSXY to verify that we are still in the correct sensor correction state.
FAMIS 20012
Temperatures all around have been less than stable recently, but that's not terribly surprising with ongoing vent activities.
The FSS TPD signal has plummeted in the past 10 days; we may need to touch up the FSS path on-table to fully fix this, but we'll likely wait towards the end of the commissioning break.
TITLE: 01/22 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 6mph Gusts, 4mph 5min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.24 μm/s
QUICK SUMMARY:
After site closure due to weather Fri, today the site is OPEN and road conditions were much less treacherous. There was No 8am Coordination Meeting (items were discussed last week).
Alarm Handler audible Alarms this morning:
Not that it matters for O4Break, Microseism has taken a big drop DOWN from 0.5um/s to 0.2um/s.
Attached below are the snapshots of the transfer function measurements I took yesterday before we kick start the in-chamber work next week. The suspensions look healthy and is currently in air.
The templates are stored at the following location,
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Data
2024-01-20_2350_H1SUSOPO_M1_WhiteNoise_L_0p02to50Hz.xml
2024-01-20_2350_H1SUSOPO_M1_WhiteNoise_P_0p02to50Hz.xml
2024-01-20_2350_H1SUSOPO_M1_WhiteNoise_R_0p02to50Hz.xml
2024-01-20_2350_H1SUSOPO_M1_WhiteNoise_T_0p02to50Hz.xml
2024-01-20_2350_H1SUSOPO_M1_WhiteNoise_V_0p02to50Hz.xml
2024-01-20_2350_H1SUSOPO_M1_WhiteNoise_Y_0p02to50Hz.xml
/ligo/svncommon/SusSVN/sus/trunk/HXDS/H1/ZM5/SAGM1/Data
2024-01-20_2340_H1SUSZM5_M1_WhiteNoise_L_0p01to50Hz.xml
2024-01-20_2340_H1SUSZM5_M1_WhiteNoise_P_0p01to50Hz.xml
2024-01-20_2340_H1SUSZM5_M1_WhiteNoise_Y_0p01to50Hz.xml
/ligo/svncommon/SusSVN/sus/trunk/HXDS/H1/ZM4/SAGM1/Data
2024-01-20_2330_H1SUSZM4_M1_WhiteNoise_L_0p01to50Hz.xml
2024-01-20_2330_H1SUSZM4_M1_WhiteNoise_P_0p01to50Hz.xml
2024-01-20_2330_H1SUSZM4_M1_WhiteNoise_Y_0p01to50Hz.xml
/ligo/svncommon/SusSVN/sus/trunk/HXDS/H1/ZM3/SAGM1/Data
2024-01-20_2320_H1SUSZM3_M1_WhiteNoise_L_0p01to50Hz.xml
2024-01-20_2320_H1SUSZM3_M1_WhiteNoise_P_0p01to50Hz.xml
2024-01-20_2320_H1SUSZM3_M1_WhiteNoise_Y_0p01to50Hz.xml
/ligo/svncommon/SusSVN/sus/trunk/HXDS/H1/ZM2/SAGM1/Data
2024-01-20_2320_H1SUSZM2_M1_WhiteNoise_L_0p01to50Hz.xml
2024-01-20_2320_H1SUSZM2_M1_WhiteNoise_P_0p01to50Hz.xml
2024-01-20_2320_H1SUSZM2_M1_WhiteNoise_Y_0p01to50Hz.xml
/ligo/svncommon/SusSVN/sus/trunk/HXDS/H1/ZM1/SAGM1/Data
2024-01-20_2310_H1SUSZM1_M1_WhiteNoise_L_0p02to50Hz.xml
2024-01-20_2310_H1SUSZM1_M1_WhiteNoise_P_0p02to50Hz.xml
2024-01-20_2310_H1SUSZM1_M1_WhiteNoise_Y_0p02to50Hz.xml
/ligo/svncommon/SusSVN/sus/trunk/HSTS/H1/FC1/SAGM1/Data
2024-01-20_2300_H1SUSFC1_M1_WhiteNoise_L_0p02to50Hz.xml
2024-01-20_2300_H1SUSFC1_M1_WhiteNoise_P_0p02to50Hz.xml
2024-01-20_2300_H1SUSFC1_M1_WhiteNoise_R_0p02to50Hz.xml
2024-01-20_2300_H1SUSFC1_M1_WhiteNoise_T_0p02to50Hz.xml
2024-01-20_2300_H1SUSFC1_M1_WhiteNoise_V_0p02to50Hz.xml
2024-01-20_2300_H1SUSFC1_M1_WhiteNoise_Y_0p02to50Hz.xml
The suspensions were set to ALIGNED state after the measurements were complete.
Also, when I logged in on Saturday morning I found the seismic watchdogs of HAM7 chamber to be tripped. I did a reset and sent a text message to Jim. During the measurements the WD tripped again (perhaps due to too much suspension excitation?). I left the ISI to be in damped state.
Dave, Rahul (HAM6 saturations)
I had plans to perform similar measurements in HAM6, however this was not possible due to very strong purge air causing the suspensions to saturate (lots of ADC overflows and WD tripping on OM1). There was also an FPU error, which as per Dave was also caused due to the overflows.
I am planning to perform this measurement on Monday morning once the purge air flow is reduced.
Sun Jan 21 10:05:17 2024 INFO: Fill completed in 5min 13secs
A sputtery fill, TC temps were noisy. Standard and zoomed in trends attached.
Procedure M1300464
The following high voltage power supplies/electronics were powered off in preparation for the corner vent.
1. CER Mezzanine - ESD HV
2. CER Mezzanine - Fast Shutter
3. CER Mezzanine - OMC PZT
4. CER - SR3 and ITM heaters
5. LVEA - Fast Shutter Driver Chassis - Disabled and powered off
6. MER Mezzanine - HAM7 PSAMS
7. MER Mezzanine - HAM7 Piezo