Rick and I went to EndY to do the PCAL Tx module maintanence today.
We followed Mostly followed the procedure outlined in DCC doc T1600436-v11 which was printed out and attached to the ALOG.
I have also updated the PCALTxMaintenanceLogBook spreadsheet with the latest information from today's activity. This is information is now in the DCC with an updated version number.
Attached a picture of the OLTF taken with the SR785 .
And a beam spot with both beams after we were finished cleaning and measuring.
[Rahul Betsy Keita Ali Koji]
The extraction of the old OMC (Unit #3) and installation of the new OMC (Unit #1) went exceptionally well.
= OMC Extraction =
Tuesday morning, we resumed HAM6 work from the OMC extraction.
Rahul and Koji went into the chamber. Rahul positioned close to HAM5, and Koji was on the other side.
They followed the extraction procedure (E1600164) after some rehearsals.
During the OMC extraction, assistance from two others was very effective in supporting wires from both HAM6 openings, preventing the wires from touching the OMC. (The procedure to be updated)
The extracted OMC was placed in the fixture on the ISI and moved back to the work table for further action.
= Balance Mass Migration =
Balancing masses were transferred from the previous OMC to the new one (Attachment 1). At the same time, a Viton ring and a 10g mass were added to each corner for the body mode damping (See T1700471).
The mass distribution differed from what Koji had figured out from the past unclear photos. But the masses could be fixed to the OMC using various 1/4-20 screws that were prepared for this.
Only light torque was applied to the fixing screws to avoid delamination/fracture of the mounting brackets below the mass mount.
= Final OMC cleaning =
All the optical surfaces were cleaned by FirstContact except for a couple of surfaces where the access was quite limited. (Attachment 2)
We let the FC paint dry during lunch and then resumed peeling them off, combined with discharging with Top Gun.
The surfaces were checked with a flashlight to find any residual.
A FC residual was located not on the optical surface but on the corner of a tombstone prism. It was cleaned with additional FC paint.
In parallel with the cleaning work, Ali and Keita worked on the review of DCPD-related cable shielding in HAM6.
= OMC Installation =
The reverse process of the extraction has been performed.
When inserting the clamps into the clamp hooks, sometimes incomplete mating happens due to friction between the copper cone and the frosted glass cup.
This can be fixed by pushing the clamp into the slit by a small flat-head driver, while the tension on the wire was released by lifting that side of the OMC.
= EQ stop release =
Reverse process of the OMCS mass clamping.
This made the OMC free. Rahul quickly checked the transfer functions of the OMCS as well as the damping control.
We decided to stop here. (Attachment 3)
Next Steps:
The attached PDF shows the previous and current balance mass configurations.
The highest mass has the height of 2 7/8" from the mating plane of the fixture, while the fixture has 3" clearance,
So we still could close the lid with the gap of 1/8".
Wonderful, CONGRATS!!!
Koji, Keita, and Rahul in HAM6.
Tagging EPO for photos
[Julian, Naoki, Camilla, Sheila, Vicky]
Summary to get SQZ alignment beam: Launched 76mW into seed fiber, ~25 mW incident on opo cavity, ~0.85 mW transmitted through opo cavity. Had to find opo transmission past the VIP, for this we used green SK path as a reference. This ~0.85 mW opo transmission was bright on an IR card at the HAM5 gate valve, and enough to iris the SQZ beam in HAM7 and HAM6 (for OMC work 75512). DC 3/4 centering loops engaged easily, then OMC A/B QPD's saw the sqz beam.
----------- Notes from today ------------------------------------------
Launched power into SEED fiber (SQZT0): 76 mW
OPO IR REFL (CLF_TRIG_REFL_DC_POWERMON @ SQZT7): 24.8mW (when opo is dither-locked).
Fiber rejected power PD in HAM7 (CLF_REFL_REJ) is 5.3 mW.
--> Seed fiber coupling: ~34% of the seed fiber launched power was incident on the opo cavity.
--> 40% coupling through fiber, ~6% mispolarized and rejected after fiber. This is similar to recent fiber alignment 75344, even after more recent on-table work 75486.
We had to find the OPO IR transmitted beam after the VIP. Nothing at first despite restoring suspensions 75502. Notes to self on what worked to find the SQZ beam post-vent:
OPO IR TRANS (OPO_IR_PD_DC_POWERMON @ SQZT7): 0.85 mW -- Just before opening the HAM7/5 gate valves. Opened the beam diverter, SQZ beam was bright on an IR card held at the HAM5 gate valve.
After opening gate valve, immediately saw the beam on AS A/B/C QPDs.
ASC-AS_A/B_DC_SUM_OUTPUT ~ 60. ASC-AS_C_NSUM_OUT16 ~ 0.65-0.67.
HAM6 crew irising SQZ beam, 75512.
HAM7 crew irising SQZ beam. Julian has some photos of HAM6 and HAM7 irses. Sheila -- looks like there is some clipping on the VIP (we have not totally optimized FC_REFL path slider alignments post-vent, just found the beam). Revisit this FC REFL alignment later.
Engaged DC 3/4 centering. It just worked. Control signals near 0.
We see the beam on the OMC QPD's, power is consistent with ASC-AS_C power, around 300-400e-6 on each OMC QPD A/B. Power goes away when SQZ beam diverter is closed. See omc powers screenshot with as_wfs powers.
TO-DO SQZ work later:
tagging for EPO
Accepted ZM1,2,3,4,5,6, FC1,2 OPTICALIGN sliders in sdf. Attached is the photo so we'll know where to bring them back to after pumpdown.
ZM4,5,6 are not monitored - should remember why that is....
Camilla, Naoki, Vicky
Next day 1/23, we tried to help check OMC alignment, but after turning the SQZ laser back on, we didn't find the beam past the VIP at first.
To re-find the sqz beam, we had to move FC1 quite a bit (pitch slider by 100 counts, yaw slider by 65 counts). See FC1 SDF's of today's move, compared to what Camilla just accepted in SDF after we first found the beam yesterday 75517.
Naoki checked FC1 and ZM1-2-3-4-5-6 SUS, and did not see any anomolous movements of the optics.
We left FC1 with an alignment that maximizes signal on both HAM7 FC WFS (RLF QPD's). Both QPD's are now saturated with 75mW into the fiber. With 5mW into the fiber to un-saturate, both QPD's are close-ish to centered.
Hopefully this is enough to use AS A/B WFS centering tomorrow. Today when we tried it, DC3 worked, but DC4 railed as the beam wasn't hitting AS_B well.
Sheila, Camilla, Vicky
We re-found the SQZ beam in HAM6 this morning after opening the ham5 gate valve. Steps taken this morning 1/24, after yesterday using FC1 to align onto the HAM7 FC WFS QPD's:
For convenience while vented, I made the following guardian changes so far:
All guardian edits (+sqz angle servo flag in sqzparams.py) commited to svn revision 27088.
Attached Julian's photos of the iris locations on HAM6 and HAM7.
Today's activities: - The RGA tree at EX was leak-checked, and multiple flanges were leaky, possibly because of some overheating during a bakeout in the past. The gaskets will be redone, and the all-metal angle valve will be also replaced - EX was vented - The VPW vacuum chamber was opened, after the 2 stuck screw was removed - Both 2 spare roughing stations are entirely finished - All the Hepta header filter works were finished in the LVEA
Measured the purge air dew point at the corner station with no usage from other groups, no people in chamber, measured -41.3 degrees C.
Measured the purge air dew point at EX, no open ports, before vent, measurement was done at the purge valve area, measured -45.4 degrees C.
TITLE: 01/23 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
Late entry. Activities on Jan 22nd: - The HAM7 X+ and X- doors have been removed - The purge air was switched on at EX - GV20 (at EX) was closed - the GV struggled with closing, but in the end it seems to be OK - Electrically 1, mechanically both 2 spare roughing stations are finished - VPW C+B door issue - 2 screws stuck, tomorrow will open it: this load has some blanks and new Hepta headers, which will be also needed
At 10:33 the DAQ 0-leg was restarted, followed at 10:38 by the 1-leg. The DAQ restart was for two EDC changes: Daniel's new slow controls CS_SQZ channels and Patrick's additional FMCS channels.
The EDC was restarted at 10:33.
A new SQZ SDF monitor.req file was installed the and h1syscssqzsdf service was restarted.
Tue Jan 23 10:06:58 2024 INFO: Fill completed in 6min 54secs
Gerardo confirmed a good fill curbside.
Addressed TCS Chillers (Tues [Jan23] 855-910pm local) & CLOSED FAMIS #26166:
TITLE: 01/23 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: EARTHQUAKE
Wind: 6mph Gusts, 3mph 5min avg
Primary useism: 0.22 μm/s
Secondary useism: 0.15 μm/s
QUICK SUMMARY:
Workstations were updated and rebooted. This was an OS package update. Conda packages were not updated.
[Rahul, Keita, Betsy, Koji]
Preparation work to extract the existing OMC has been completed. We will continue with the OMC extraction tomorrow morning.
The overall work procedure for the OMC replacement is summarized in G231106 https://dcc.ligo.org/LIGO-G231106.
= OMC shroud panel removal =
While waiting for the beam from the squeezer to come, we started the removal of the OMC shroud panel in parallel. The work was done along with the procedure E1600164.
The removed panels were placed on a stainless steel table in the HEPA booth of HAM6 (Attachment 1). The panels were not covered to prevent accidental placement of objects on them.
During the work, a beam dump was removed from the table to make the removal work possible. This beam dump is to kill one of the weak transmissions of the OMC.
Betsy took the photo record of the location, but it is safely trivial how it should be aligned.
= SQZ beam marking and alignment =
The beam was delivered to HAM6 and was pinned down with two irises on the ISI table.
The irises were placed just after the beam entered HAM6 (next to OM2) and just before OM1 (next to the fast shutter).
This means that these indicators are not affected by the alignment in HAM6.
They were placed by eyeballing, so their precision was as such. By default, both the irises were set to the maximum opening.
Next, the beam alignment was servoed towards the WFS heads using the DC centering ASC loops.
As soon as the control was applied, both QPDA and QPDB of OMC showed significant signals with total light level of ~1e-3 (Attachment 2).
When the light was blocked (at the squeezer?), the value dropped to almost zero, confirming that this was a real beam.
This is very good news as we'll be able to find the beam arrival using the OMC QPDs when we try to align the new OMC.
= Holding suspension mass =
Next, we proceeded to hold the suspension masses. Rahul and Koji worked in the chamber on the ISI table for the following operations.
To hold the intermediate mass:
Then, moved onto fixing the OMC:
= Removing the electronic cables from the OMC =
Upon removing the electronics cables, one person held the cable harness on the OMC breadboard to prevent the OMC from wobbling too much.
The removed cables were wrapped around the top part of the suspension frame to keep them out of the way of the further work.
At this point, it was just at 5pm, so we exited from the chamber.
Next Steps:
The following high voltage power supplies were powered on this morning:
1. HAM7 - PZT and P-Sams
2. HAM6 - PZT and Fast Shutter
The pressure interlock system bypassed.
We also turned back on the HAM7 SQZ OPO TEC servo, turned off for vent as described in M1300464.
The reasoning for the TEC servos being turned off is to protect them from trying to keep a stable temperature while vent rather than because they are High voltage.
I forgot to revisit this in 2022 so the HAM7 SFI1, SFI2, and HAM6 OFI TEC servos were left on during this vent. We'll look at at their behavior to see if this should be kept in the procedure.
Ibrahim, TJ, Camilla, Naoki,
Looking at how the ZM4,5,6 alignment has shifted both with the vent and recent temperature changes in the LVEA.
Attached is ZM4/5 P/Y alignment since the last time we were SQZing to vented now, there is large changes of ZM5 (470urad in Pit and 230urad in Yaw). Alignment sliders haven't changed but SQZ ASC would have been changing some alignment when the IFO was locked.
ZM6 has large changes (1300urad in Pit and 280urad in Yaw). Currently DAMPED but alignment sliders are the same. Edit: DAMPED turns off the alignment sliders, once Austin brought back to ALIGNED it had moved <100urad.
We expect some changes from bouyancy of air. The HAM7 SUS are currently "aligned" with the doors being taken off HAM7. Jim hasn't locked the ISI yet. Looking at ZM4,5,6 alignment, last vent, IFO locked, and now.
Ibrahim is looking at temperatures and alignment since our last vent.
Vicky found that the SQZ beam was different on the RLF QPDs and not on the SQZT7 H1:SQZ-OPO_IR_PD_DC_POWER. Sheila checked that the OPOS doesn't seem to have changed much (<5um, 0.005urad if channels are calibrated), plot attached
Details of realignment and finding the beam in 75509.
Vicky Daniel
Today we swapped the beamsplitter in the squeezer laser path that transmits a sample beam to the IR PD (which monitors the laser power). The old splitter was 98:2 for p-polarization and transmitted about 0.1% in s-polarization. We replaced it with a 98:2 meant for s-polarization that transmitted just shy of 1%. After a turning mirror, another 50:50 splitter was installed. The transmitted beam is used for the IR PD, whereas the reflected beam passes through a half wave plate, a polarizing beam splitter, a quarter and a half waveplate, and two additional turning mirrors into a fiber coupler. The other end of the fiber was connected to the squeezer laser input of the fiber beat note box. We also moved the fiber PSL sample beam from the table feedthrough to the PSL input of the fiber beat note box. This allowed us to lock the TTFSS with the new setup.
A slight realignment was required for the CLF, seed and SHG paths. The power coupled into these fibers came back to near the values where they were.
The channels H1:SQZ-FIBR_TRANS_DC and H1:SQZ_FIBR_REJECTED_DC are now monitoring the power in the fibers of the PSL and squeezer lasers, respectively.
The squeezer laser has been turned off and locked out again after the work was finished.
The power out of the PSL fiber was measured to be 0.925mW. The DC readback of the 1611 then read 785mV. The DC readback is not recorded at the moment. This requires a slow controls software update.
The IR PD had to be recalibrated:
Following the plan in T2300300, here are some photos of the fiber TTFSS path we installed today, with the path and powers labelled and with the path lengths marked, to update H1's SQZT0 optical layout D1201210.
We took the pico waveplates from free-space TTFSS for this fiber TTFSS path, and got the 160 MHz SQZ-PSL beatnote power up to 3.6. In observe, it was ~2, so this beatnote is usable for locking.
To-do later - improve this fiber coupling, currently it is only ~30-40% with some variation between fibers. Moving the lens and collimator +/- 1 inch from design only changed the fiber coupling by a few %, so different lenses might be needed. Can revisit this fiber coupling later.
Currently we have
Camilla, Naoki, Sheila, Nutsinee
We did a repeat of the measurement set from 73621 with OM2 cold. For a summary, Camilla's plot shows 200V/200V PSAMs setting with solid lines and 120V/120V as dashed lines. There is a stronger frequency dependence for the 120V/120V settings, which confirms what we saw with OM2 hot, that 200V/200V has better mode matching and less frequency dependent SQZ rotation. (This plot is a direct comparison to October's data. )
The third attachment is a plot that shows that the squeezing angle that maximizes the squeezing at 2kHz is not the same as the one that maximizes the squeezing at 200Hz, (green traces are optimized for 2kHz, blue traces are optimized for 200Hz, solid is 200V/200V and dashed is 120V/120V), you can see that the frequency dependence is larger for 120V/120V.
The fith attachment compares OM2 hot vs OM2 cold for antisqueeze and squeezing, with PSAMS at 200V/200V. There is less anti-squeezing with OM2 hot, which could be due to a difference in nonlinear gain or reduced readout losses. The green traces show that the squeezing level is similar, although the no sqz spectra is also different between the two times.
times:
Since our ASQZ with PSAMS 200/200 was a little lower than with 120/120, and that seemed inconsistent with our sqz data and our previous measurement with OM2 hot, we went back to SQZ with PSAMS 200/200, ran ASC then turned it off, and checked the sqz angle carefully. This did give a little more anti-sqz to replace the reference 20 above:
Camilla saved these references in userapps/sqz/Templates/dtt/DARM/PSAMS_tests_Dec2023.xml
[Vicky, Sheila, Kevin]
Summary: In O4a at LHO, maxing out the ZM4/5 PSAMS to 200/200V corresponded to the best squeezer mode-matching, as judged from the flatter frequency-dependence of the squeezing angle. We didn't see a clear signature of freq-dep squeezing losses. It's possible the squeezer was better mode-matched with hot OM2, while the IFO was better mode-matched with cold OM2. So, both situations ended up comparable, and neither was fully optimal (LHO:74916, these plots). Hopefully we can repeat these PSAMS tests and reach even flatter sqz / better mode-matching in O4b, after offloading psams during the break.
To evaluate the different SQZ-IFO-OMC mode-matching configurations, Sheila suggested we can try comparing the frequency-dependence of squeezing losses and sqeezing angle across different active optics settings. This is comparing some of the SQZ metrics from Lee's paper, for various mode-matching situations (see bottom panels of Figure 3 from P2100050). If flat squeezing across all frequencies is a good figure of merit for good matching, in O4a, railing PSAMS 200/200 consistently produced the flattest squeezing (small dots) regardless of OM2.
We compared these two PSAMS datasets as a function of OM2 temp: 74935 - Dec 2023 - cold OM2, and 73621 - Oct 2023 - hot OM2. Changing OM2 temp varies the IFO-OMC mode-matching, while changing the PSAMS voltage varies the SQZ - IFO/OMC mode-matchings.
This the main takeaway plot - it shows the squeezing angle's frequency dependence as we varied PSAMS settings (ie, squeezer beam shape), at two different OM2 temps (ie, different IFO-OMC path mode matchings). Smaller dots == PSAMS 200/200, bigger dots == PSAMS 120/120. Dots = data, lines = moving average of data (not a fit) to guide the eye.
---> Traces with 200/200 (smaller dots) have less degrees of sqz angle rotation across the band, i.e. they are flatter. We could interpret this flatter sqz as better squeezer mode matching.
For the process: this screenshot shows all the DARM PSAMS data we started with, and the squeeze dBs from all the configurations after subtracting classical noise. From this squeeze dB data, at each frequency we ues standard sqz equations: for anti-sqz we fit losses, for +/- mid-sqz and sqz data we fit the squeeze angle. Altogether, we get the above main plot of freq-dep losses and angle variations.
To add to this analysis -