Displaying reports 1441-1460 of 82999.Go to page Start 69 70 71 72 73 74 75 76 77 End
Reports until 13:44, Thursday 17 April 2025
H1 SQZ
sheila.dwyer@LIGO.ORG - posted 13:44, Thursday 17 April 2025 (83953)
revisting arm power bounds from squeezing: 310kW- 353kW

In 82097 we got some constraint on the circulating power in the arm from the squeezer data set.  I'm working on looking at the data that Camilla took in 83660, and realize that with the higher nonlinear gain the frequency independent squeezing gives us a better constraint on the arm power.

Using known injection losses of 8.2%(google sheet),   and  6% extra HAM7 losses from 83070 gives 13.7% minimum injection losses for squeezing, and our known readout losses are 8.4%.  Based on 16.1dB of anti squeezing (for NLG of 19 as reported by Camilla) and -4.97 dB squeezing, the infered NLG is 18.7 and the total sqz efficiency is 0.694 (with 0 phase noise). This means that in addition to the 6% extra losses measured on the homodyne, we have another 12% unknown squeezer losses.  We can assign those 12.2% losses to either injection losses (unlikely since there isn't much between homodyne pick off point and injection into the OFI), readout losses that also impact the IFO readout, or squeezer readout losses that don't impact the IFO (SQZ to OMC mode matching). 

If the only IFO readout losses are the known losses, the IFO readout efficiency is 91.6%, and we can use the shot noise level without squeezing injected to estimate that the minimum arm power is 310kW.  Using the total squeezer efficiency and the known losses, we can place bounds on the readout efficiency between 80.4% and 91.6%.  The level of shot noise measured without squeezing mostly depends on arm power and readout efficiency, so this maximum readout efficiency gives us a minimum arm power of 310kW (all squeezer losses are injection losses, readout efficiency is 91.6% and arm power is minimum), while the minimum readout efficiency gives us 353kW (all unknown squeezer losses are common to IFO, which probably wouldn't be the case for mode mismatches). 

Images attached to this report
X1 SUS (SUS)
rahul.kumar@LIGO.ORG - posted 12:55, Thursday 17 April 2025 (83977)
A+ O5 HRTS (suspended configuration L1BHDM1) being transported from LHO to LLO

Ryan C, Rahul

L1BHDM1 which is the suspended configuration of HRTS (HAM Relay Triple Suspension) for O5 is now ready to be shipped to LLO (using ground freight). The suspension (all stages locked with EQ stops, torqued double nuts and tension removed from wires ) has been wrapped in several layers of clean foil/clean cloth and clean bag as shown here.

This shipment is expected to reach LLO sometime at the end of next week (25th April), if it leaves LHO today. The details of the shipment are given below,

Tracking Site Link: https://www.shipdbi.com/ HWB Number for TRK: 139289

FRS ticket - https://services1.ligo-la.caltech.edu/FRS/show_bug.cgi?id=33849

ICS (assembly record) - https://ics.ligo-la.caltech.edu/JIRA/browse/ASSY-D1900449-L1BHDM1

ICS (shipment load) - https://ics.ligo-la.caltech.edu/JIRA/browse/Shipment-13842

This is first of the total six HRTS which will be transported to LLO.

Images attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 11:11, Thursday 17 April 2025 - last comment - 16:13, Thursday 17 April 2025(83973)
h1isiham1 model restarts, DAQ restarts

Jim, Tony, Dave:

We restarted h1isiham1 model four times and the DAQ twice:

1. Internal wiring change to model, no DAQ retstart for that but new common part with "missing ADC chans" fix was included which did require a DAQ restart. No issues with DAQ restart other than gds0 needed a second restart.

2. A copy-paste binary parts issue was found, HAM6 parts were included in HAM1. BIO parts were renamed, no DAQ restart was neeed.

3. HAM1 differs from HAM6 in BIO inputs in that it reads 64 input channels instead of just 32. Upper32 channel BIO part was added, which added slow channels, so DAQ restart was required. No issues with DAQ restart other than gds0 second restart.

4. To minimize binary chassis hardware, HAM1 and HAM6 share the first BIO card's binary output chassis, HAM6 uses lower 32 chans, HAM1 uses upper 32 chans. h1isimodel was changed to use BIO-0 U32 for outputs. No DAQ restart was required.

Current BIO hardware as see by models:

wiring input block model   model output block wiring
from ham6 BIO-0 low 32 h1isiham6   h1isiham6 BIO-0 low 32 to ham6
not connected BIO-0 high 32 none   h1isiham1 BIO-0 high 32 to ham1
             
from ham1 BIO-1 low 32 h1isiham1   none BIO-1 low 32 no chassis
from ham1 BIO-1 high 32 h1isiham1   none BIO-1 high 32 no chassis

 

Comments related to this report
david.barker@LIGO.ORG - 11:27, Thursday 17 April 2025 (83974)

DAQ Changes

1st DAQ restart (correct missing ADC chans)

++: slow channel H1:ISI-HAM1_PMON_GS13_P3_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_GS13_P2_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_GS13_P1_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_GS13_D3_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_GS13_D2_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_GS13_D1_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_FF_L4C_P3_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_FF_L4C_P2_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_FF_L4C_P1_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_FF_L4C_D3_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_FF_L4C_D2_CTS added to the DAQ
++: slow channel H1:ISI-HAM1_PMON_FF_L4C_D1_CTS added to the DAQ
 

2nd DAQ restart (read H32 BIO-1 channels)

++: slow channel H1:ISI-HAM1_BIO_IN_GAIN_L4C_H1_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_GAIN_L4C_H2_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_GAIN_L4C_H3_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_GAIN_L4C_V1_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_GAIN_L4C_V2_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_GAIN_L4C_V3_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_INMON2 added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_TEST2 added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_TESTMON2 added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_WHT_L4C_H1_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_WHT_L4C_H2_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_WHT_L4C_H3_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_WHT_L4C_V1_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_WHT_L4C_V2_RB added to the DAQ
++: slow channel H1:ISI-HAM1_BIO_IN_WHT_L4C_V3_RB added to the DAQ
 

david.barker@LIGO.ORG - 11:31, Thursday 17 April 2025 (83975)

Thu17Apr2025
LOC TIME HOSTNAME     MODEL/REBOOT
09:09:41 h1seih16     h1isiham1   <<< model restart, fix wiring, add missing-adc-chans
09:12:10 h1daqdc0     [DAQ] <<< 0-leg
09:12:20 h1daqfw0     [DAQ]
09:12:21 h1daqtw0     [DAQ]
09:12:22 h1daqnds0    [DAQ]
09:12:29 h1daqgds0    [DAQ]
09:13:19 h1daqgds0    [DAQ] <<< 2nd gds0 restart
09:16:23 h1daqdc1     [DAQ]
09:16:33 h1daqfw1     [DAQ] <<< 1-lde
09:16:34 h1daqtw1     [DAQ]
09:16:35 h1daqnds1    [DAQ]
09:16:44 h1daqgds1    [DAQ]
10:10:21 h1seih16     h1isiham1   <<< model restart, change bio address
10:27:28 h1seih16     h1isiham1   <<< model restart, add BIO-1 H32
10:32:12 h1daqdc0     [DAQ] <<< 0-leg
10:32:23 h1daqfw0     [DAQ]
10:32:24 h1daqtw0     [DAQ]
10:32:26 h1daqnds0    [DAQ]
10:32:32 h1daqgds0    [DAQ]
10:35:28 h1daqgds0    [DAQ] <<< 2nd gds0 restart
10:36:21 h1daqdc1     [DAQ] <<< 1-leg
10:36:32 h1daqfw1     [DAQ]
10:36:32 h1daqtw1     [DAQ]
10:36:34 h1daqnds1    [DAQ]
10:36:42 h1daqgds1    [DAQ]
10:57:48 h1seih16     h1isiham1   <<< model restart, drive BIO-0 H32
 

david.barker@LIGO.ORG - 16:13, Thursday 17 April 2025 (83986)

Two more h1isiham1 model restarts, the first with an associated DAQ restart.

14:35 h1isiham1 binary output block was upgraded, adding slow channels to the DAQ. During DAQ restart gds0 and gds1 needed second restarts.

15:53 h1isiham1 input bus selector to binary output block was corrected, no DAQ restart needed.

14:35:41 h1seih16     h1isiham1   <<< new binary output block
14:37:30 h1daqdc0     [DAQ] << 0leg
14:37:40 h1daqfw0     [DAQ]
14:37:40 h1daqtw0     [DAQ]
14:37:41 h1daqnds0    [DAQ]
14:37:48 h1daqgds0    [DAQ]
14:38:22 h1daqgds0    [DAQ] <<< 2nd gds0 restart
14:41:43 h1daqdc1     [DAQ] <<< 1leg
14:41:54 h1daqfw1     [DAQ]
14:41:54 h1daqtw1     [DAQ]
14:41:55 h1daqnds1    [DAQ]
14:42:03 h1daqgds1    [DAQ]
14:43:00 h1daqgds1    [DAQ] <<< 2nd gds1 restart
15:53:57 h1seih16     h1isiham1   <<< correct input bus of binary output block
 

LHO VE
david.barker@LIGO.ORG - posted 10:45, Thursday 17 April 2025 (83972)
Thu CP1 Fill

Thu Apr 17 10:09:38 2025 INFO: Fill completed in 9min 34secs

 

Images attached to this report
LHO VE
janos.csizmazia@LIGO.ORG - posted 09:01, Thursday 17 April 2025 - last comment - 13:09, Wednesday 30 April 2025(83969)
2025 April vent - VAC diary
Late entry

4-16 (Wednesday) activities:
- The previously received, poorly packaged Inficon gauge has been tested, and found functional. These tests continue, and also the HAM1 vacuum interlock gauge will be installed soon
- The BSC8 Annulus Ion Pump - after some aux cart pumping - is now able to hold the annulus pressure, at the mid- E-6 Torr region
- The rough pumpdown of the corner has started at 16:20, at the OMC turbo station, with a pair of ISP-1000 mobile pumping carts. In 4 hours, ~185 Torr was achieved, which means 1930 l/s effective pumping speed, which well corresponds with the 2000 l/s theoretical speed of the pumps
- The rough pumping still needs to be terminated in the end of the days, and so it was at 20:20
- All the turbo stations have been prepared for the HV pumping at the corner
Comments related to this report
janos.csizmazia@LIGO.ORG - 13:09, Wednesday 30 April 2025 (84203)
The dew point of the blow-off air was -15 deg C.
H1 SEI
ryan.crouch@LIGO.ORG - posted 08:44, Thursday 17 April 2025 (83968)
ISI CPS Noise Spectra Check Weekly FAMIS

Closes FAMIS26039 , last checked in alog83802

Most of the HAMs looks more elevated than last time, due to the vent activities.

The BSCs look the same as when they were last checked.

Non-image files attached to this report
H1 General
anthony.sanchez@LIGO.ORG - posted 07:44, Thursday 17 April 2025 (83967)
Thursday Ops morning report

TITLE: 04/17 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: MAINTENANCE
    Wind: 5mph Gusts, 3mph 3min avg
    Primary useism: 0.02 μm/s
    Secondary useism: 0.20 μm/s
QUICK SUMMARY:
VAC team have been Pumping down the corner station volume for 15 hours now and H0:VAC-LX_Y2_PT180_MOD1_PRESS_TORR channel is reporting that we are below 200 torr in BSC8 chamber.

Expected work today:

 

H1 CDS
david.barker@LIGO.ORG - posted 07:35, Thursday 17 April 2025 (83966)
Model changes to fix missing ADC channels in MEDM

For each ADC a user model uses the RCG generates an ADC MEDM showing the raw counts for only those channels the model connects to. In order to make this MEDM more useful, for each channel the RCG attempts to find a named part in the simulink mdl and adds that name to the MEDM.

If the first simulink part found when traversing the model does not have a name (e.g. is a summation, gain, multiplier, etc.) currently the RCG leaves this channel off the MEDM. Future RCG versions will fix this by adding generic ADC names, but in the mean time we are taking the vent RCG upgrade as an opportunity to install named EPICS_OUTPUT parts where needed. Ideally the subsystem authors would give these parts descriptive names, but failing that we will give them generic ADC_x_y type names.

Jim has done this for the ISI HAM models, so when we restarted h1isiham2 and h1isiham5 on monday those models' ADC MEDMs were corrected. The attachment shows the ADC MEDMs for h1isiham2 (full) compared with h1isiham3 (partial).

Images attached to this report
H1 General
anthony.sanchez@LIGO.ORG - posted 17:15, Wednesday 16 April 2025 (83962)
Wednesday Engineering Ops day Shift report

TITLE: 04/17 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
The Vacuum team has started the Pump Down !
The SPI team has components on the table and are currently in an optomization stage.
I think Jim still has more work to do on HAM1.
 

Joe doing update of installed pydarm code.

At 21:38 UTC the water level sensor for the fire tank was restarted by Eric because it was reading as full but was not.


21:48 UTC the Water tank sensor was restarted to make the Water level sensor read correctly.

LOG:

Start Time System Name Location Lazer_Haz Task Time End
14:53 FAC Randy LVEA N Prepping for work 14:08
14:54 FAC Mitchel & Randy, Jim, Corey LVEA N Craning parts 18:54
14:54 FAC Kim & Nellie LVEA N Technical Cleaning 16:54
15:19 VAC Jordan LVEA n Purge Air checks 15:47
16:39 VAC Janos LVEA N Walkin the LVEA to get caught up on the  VAC Status 16:54
16:47 VAC Jordan LVEA N Check Turbo pump on BSC7 & Prep Turbos for Pump Down 18:57
16:52 IAS Jason LVEA N Setting up Surveying Equipmentr 19:07
16:53 PSL Ryan S PSL YES PSL checks and SPI work 19:59
16:53 IAS Ryan C LVEA N Surveying with jason 17:41
17:02 VAC Travis LVEA N LVEA ouput arm with HAM1 flanges 17:08
17:04 SPI Josh Optics Lab yes Getting parts for PSL SPI work 17:34
17:28 ISI Betsy LVEA N Checking on HAM1 crew 18:07
17:31 SPI Sina & Josh PSL Yes Installing SPI optics in PSL 19:58
17:45 FAC Tyler YARM backside n Check well line 18:35
17:46 SPI Keita OpticsLab YES Helping with PSL SPI work 20:26
17:58 SPI Jeff Optics Lab yes working on SPI optics 18:31
18:02 HAM1 Sheila LVEA HAM6 N Looking for parts 18:11
18:16 VAC Travis LVEA n Looking for Marristat bags 18:26
19:30 PCAL Tony PCAL Lab Yes transfer standard Measurement config change 19:37
19:48 HAM1 Betsy & Travis LVEA N HAM1 feed throughs 21:22
19:52 HAM1 Mitchel & Randy LVEA HAM1 N Installing HAM1 ISI accessories, Mitchell out Early 21:25
20:01 SEI Jim LVEA N Plugging in HAM1 Electronics 22:47
20:02 Vac Janos & Jordan LVEA N Prep turbo pumps for pump down 20:34
20:24 EE Fil LVEA N Workign on Feed Through with Betsy & Travis 21:27
20:33 SEI Jennie, Edgor, Sina LVEA N Taking a look at the HAM1 Work 20:50
20:35 SPI Josh Optics Lab & PSL YES Optics work for SPI system 21:00
20:46 PSL Ryan S, Sina, Josh PSL Yes SPI pickoff beam path from PSL 00:01
20:59 Safety Richard LVEA N Safety Checks 21:10
21:01 FAC Tyler LVEA N Checking on HVAC in Southbay 21:09
21:09 SUS Ryan C & Rahul LVEA HAM6 N Dropping off SUS & Optics 21:14
21:10 IAS Jason LVEA N Aligning 21:58
21:16 IAS Ryan C LVEA N Surveying 21:58
21:29 VAC Jordan Mid X&Y N Cap. Inventory 21:51
21:32 FAC Eric Water Tank N Resetting water Tank water level sensor 22:17
21:52 VAC Jordan LVEA N Turbo pump checks 22:39
22:50 Vac Janos & Jordan LVEA N Starting Pump Down 01:50
23:36 IAS Jason LVEA N Unplugging battery 23:40
23:42 Pcal Tony PCAL Lab Yes Checking PCAL config 23:47

 

H1 PSL
jeffrey.kissel@LIGO.ORG - posted 16:03, Wednesday 16 April 2025 - last comment - 11:35, Monday 21 April 2025(83961)
SPi Pickoff Path Install Day Two
J. Kissel scribing for S. Koehlenbeck, J. Oberling, R. Short, J. Freed
ECR E2400083
IIET 30642
WP 12453

Another quick summary aLOG at the end of the day, with more details to come:
- With the power in the ALS/SQZ pick-off path to 10 [mW] for beam profiling,
- Installed a two lens system to handle the unexpectedly different beam profile of the ALS/SQZ pick-off path
- Remeasured the resulting mode after the two lens system, and we're happy enough. We're gunna call them SPI-L1 and SPI-L2.
- Installed steering mirrors SPI-M1 and SPI-M2.
- Rotated ALS-HWP2 to increase the s-pol light in the ALS/SQZ/SPI path to return the power transmitted through SPI-BS1 going to the ALS/SQZ fiber collimator back to 50.5 [mW]. This set the SPI path to 186 [mW] with the PMC TRANS measured at 103.5 [W]. The ALS_EXTERNAL PD in transmission of ALS-M9 measured 31 [mW] ***. 
- Installed SPI-HWP1 and SPI-PBS01
- Measured the power at each port of SPI-PBS01, with the intent to optimize the SPI-HWP1 position to yield maximum p-pol transmission through SPI-PBS01.

*** We expect this is lower than the goal of ~45 [mW] (from LHO:83927) because we've not yet re-aligned the ALS/SQZ fiber collimator path after the install of the SPI-BS1, which translates the beam a bit due to the thickness of the beam splitter. We intend to get back to this once we're happy with the SPI path.
Comments related to this report
ryan.short@LIGO.ORG - 17:54, Wednesday 16 April 2025 (83965)

Small correction to above is after installing SPI-HWP1 and SPI-PBS01, we adjusted HWP1 to have 20mW in transmission of PBS1 (not maximum quite yet) to start alignment into the fiber. Using the two steering mirrors downstream of PBS1 and the collimating lens in front of the fiber, Sina maximized the transmission as measured with the output of the fiber on a spare PD. We then took power measurements of the input and output of the fiber:

  • Input: 19.4mW
  • Output: 13.5mW
  • Transmission ratio: 72.1%

This is a good start, but with a target ratio of >80%, there's still more work to be done here improving the beam into the fiber collimator. Out current mode-matching solution claims we should have 95% mode overlap into the fiber, so hopefully the issue is alignment, but it's entirely possible we'll revisit the mode-matching to see if improvements can be made there too.

The attached photo represents the optical layout as it stands as of where we stopped today, with the new SPI fiber in blue on the left (north) side of the table.

Images attached to this comment
jeffrey.kissel@LIGO.ORG - 12:10, Thursday 17 April 2025 (83976)ISC, SQZ, SYS
Re-post of Ryan's picture at the end of day 2, labeled with the almost entirely complete SPI pick-off path.

Critically here, this shows the PSL row/column grid, confirming that this whole ECR E1900246 ALS pick-off path is 2 rows "higher" in +Y than is indicated on the current version of the as built PSL drawing D1300348-v8.
Images attached to this comment
jeffrey.kissel@LIGO.ORG - 11:35, Monday 21 April 2025 (84024)
Ryan grabbed another picture I attach here. This shows the ALS pick-off path on this day in order to support the identification that the beamline between ALS-M1, through the faraday ALS-FI1 and ALS-L1, etc stopping at ALS-M2 (not pictured) is on row 25 of the PSL table *not* row 23 as drawn in D1300348-v8. I attach both the raw picture and my labeled version. So, ya, ALS-M1 should have its HR surface centered on Row 25, Col 117.

Note, the grid in the picture is labeling bolt holes. Because the optical elements are all ~4 inches above the table, the beams appear offset from the way they travel on along the grid given that the photo was taken at a bit of an angle from vertical. May the future updater of D1300348 bear this in mind.

Images attached to this comment
H1 SUS
oli.patane@LIGO.ORG - posted 14:21, Wednesday 16 April 2025 (83959)
Edit and restart of PR3 and SR3 models to fix crossed wires

Sheila, Oli, Jeff, Erik, Edgard, Brian

While looking at the pointing drift over the course of the vent for SR3, Sheila and I noticed a jump in the DAMP_P_INMON channel before vs after the SR3 model restart that was done yesterday (83906) (attachment1). We looked around trying to trace where the discrepancy started until we finally noticed that the 32 coming out of DITHER P was entering DRIVEALIGN as L (attachment2). This was confirmed as the discrepancy when we trended the DRIVEALIGN_L and DRIVEALIGN_P channels and confirmed that before the model restart, DRIVEALIGN_L was (correctly) 0 and DRIVEALIGN_P was (correctly) 32, but after the model restart they had been swapped (bottom middle of attachment1).

Looking at the 2nd and 3rd Simulink model screenshots that Jeff had uploaded in 83911, we see that the ADDFF block takes in LPY in the wrong order - as FF_P_In, FF_Y_In, FF_L_In, and then sends it back out in the wrong order as well - as PITCH_Out, YAW_Out, LONG_Out.

I've corrected these mistakes (attachment3, attachment4) and recompiled the PR3 and SR3 models, and Erik was available to restart both models for us. Everything looks good now! The discrepencies with DAMP_P_INMON and the Left and Right COILOUTs have been resolved.

Changes in model /opt/rtcds/userapps/trunk/sus/common/models/SIXOSEM_T_STAGE_MASTER_W_EST.mdl committed to svn as r31287.

Images attached to this report
H1 PSL (ISC, SQZ, SYS)
jeffrey.kissel@LIGO.ORG - posted 14:15, Wednesday 16 April 2025 - last comment - 11:36, Monday 21 April 2025(83956)
Beam Profiling the ALS / SQZ Fiber Distribution Pick-off Path in Prep for SPI Pick-off
J. Kissel scribing for S. Koehlenbeck, R. Short, J. Oberling, and J. Freed
ECR E2400083
IIET 30642
WP 12453

During yesterday's initial work installing the SPI pick-off path (LHO:83933), the first optic placed was SPI-BS1, the 80R/20T power beam-splitter that reflects most of the s-pol light towards the new SPI path. The pick-off is to eventually be sent into a SuK fiber collimator (60FC-SF-4-A6.2S-03), so we wanted to validate the beam profile / mode shape of this reflected beam.


The without changing any power in the ALS/SQZ/SPI pick-off path, the power now reflected from newly installed SPI-BS1 measured ~40 [mW] (see LHO:83946). This is too much for the WinCam beam profiler, so they used ALS-HWP2 to rotate the polarization going into ALS-PBS01, and thus reduced the reflected s-pol light in this ALS/SQZ/SPI pick-off path to ~10 [mW]. That necessarily means there's a little more of the ~2 [W] p-pol light transmitted and going toward the HAM1 light pipe, so they placed a temporary beam dump after ALS-M2 so as to not have to think about it.

The they set up a WinCam head on a rail and gathered the beam profile. With the WinCam analysis software on a computer stuck in the PSL, they simply gathered the profile information which I report here: 
# Distance[cm]	Radius[um]   Radius[um]
                   X             Y
    0.0           680.5         717
    17.78         465           504
    25.4          389           428.5
    30.48         346.5         368
    38.1          281.5         300.5

where "X" is parallel to the table, and "Y" is orthogonal to the table. The "0.0" position in this measurement is the "front" of the rail (the right most position as pictured in the attachment), which is Column 159 of the PSL grid. SPI-BS1 has the center of its reflective surface is set in +/- X position in Column 149 (within the existing ALS-PBS01 to ALS-M9 beam line). It's +/- Y position is set to create a reflected beam line along Row 30 of the grid, and the WinCam head and rail are centered in +/- Y on that Row to capture that beam.

Using this profile measurement, we find it to be quite different than expected from when this path was installed circa 2019 (see e.g. LHO:52381, LHO:52292, LHO:51610). Jason shared his mode matching solution from LHO:52292 with us prior to this week, and I've posted it as a comment to that aLOG, see LHO:83957.

We think we can trace the issue down to an error in the as-build drawing for the PSL:
- the whole beam path running in the +/-X direction from ALS-M1 to ALS-M2 is diagrammed to be on row 23 -- however, we find in reality, the path lies on row 25. That's 2 inches more between the (unlabeld) pick-off beam splitter just prior to ALS-M1 and ALS-M1 itself. Easily enough to distort a mode matching simulation.
- Jason confirms that he used the *drawing* to design the lens telescope for this ALS/SQZ fiber distribution pick-off path.

More on this as we work through a lens solution for the SPI path.

As of this entry, we elect to NOT create a new solution for the whole ALS/SQZ fiber distribution pick-off i.e. we *won't* adjust ALS-L1 or ALS-L5 in order to fix the true problem. But, we report what we found in the event that a case is better made to help mode matching and aligning into the ALS/SQZ fiber distribution pick-off easier -- as we have verbal confirmation that it was quite a pain.
For the record the fiber collimator used in the ALS/SQZ distribution pick-off is a Thor Labs F220 APC-1064.
Images attached to this report
Comments related to this report
jeffrey.kissel@LIGO.ORG - 14:32, Wednesday 16 April 2025 (83960)
Just a quick trend of the SM1PD1A EXTERNAL PD in transmission of ALS-M9 after they throttled the s-pol power in the ALS/SQZ/SPI path to ~10 [mW]. 
In that trend, you can see the different in "lights on" vs. "lights off" highlighted with the magenta vertical lines.

Note, as you can see in the picture, the reflection of ALS-M9 is dumped so as to not have to think about how much power is or is not going into the ALS/SQZ fiber distribution collimator (ALS-FC2), so the INTERNAL monitor PD that's in the distribution chassis itself is "correctly" unexpectedly reading nothing, so I don't show it.
Images attached to this comment
jeffrey.kissel@LIGO.ORG - 08:23, Friday 18 April 2025 (83993)
Correction to the last sentence of the main entry -- the ALS/SQZ fiber collimator is *not* an, but instead a Thorlabs Fiber Port PAF2-5A, pictured well in FinalInstall_ALSfiber.jpg from LHO:83989.

I had incorrectly assumed that this collimator would be a copy of ALS-FC1, which *is* listed in E1300483 as an F220 APC-1064.
sina.koehlenbeck@LIGO.ORG - 11:36, Monday 21 April 2025 (84023)

In the attachment you will find the fit with JAMMT to the measured beam profile data with offset correction:

  • Offset of measurement point to SPI-BS1: 10.2 cm
  • Offset of measurement point to beam profiler surface: 7.3 cm
Distance (cm) Radius horiz. (um) Radius vert. (um)
17.46 680.5 717
35.24 465 504
42.86 389 428.5
47.94 346.5 368
55.56 281.5 300.5
Images attached to this comment
LHO VE
janos.csizmazia@LIGO.ORG - posted 10:05, Wednesday 16 April 2025 - last comment - 10:40, Thursday 17 April 2025(83951)
Intentional pressure spike at the X-manifold
Janos - 9:50, LVEA

The X-manifold is valved out from the main volume both sides, the main turbo is pumping on it.
On the X-manifold I slightly opened up the suspicious blanked-off small Varian gate valve (see photo), to find out if it is opened or closed.
I moved very slowly the hand-actuator, and the pressure spiked up to the E-5s, then it immediately started to go down, now it is already at ~3E-7 (the initial value was ~1E-7).
So, the valve was closed and blanked off, therefore it wasn't stored appropriately, thus at the next opportunity (when the X-manifold will be vented), it will be removed, and blanked off.
Images attached to this report
Comments related to this report
janos.csizmazia@LIGO.ORG - 10:40, Thursday 17 April 2025 (83971)
The handler of this valve was torqued, and the pressure in the X-manifold fell to 8.14E-8 Torr, and it is seemingly stabilized. Before poking with this valve, the pressure was 1.04E-7 Torr (and still rising), so there was indeed a leak from this valve to the system, as this torquing means ~20% reduce in gas load.
We do a comprehensive leak check on the X-manifold during the rest of the week, so this valve with all adjacent flanges will be bagged and leak checked.
We are also considering putting an adapter on the valve instead of a blank, and pump it down, so the lower pressure in the outer side of the valve could help, if there is still some communication between the valve and the system - but of course, it depends on the result of the leak check.

Finally, the handler of this valve was LOTO-d - it was simply taken off, so there will be no accidental moving of this valve anymore.
Images attached to this comment
H1 SUS
oli.patane@LIGO.ORG - posted 17:11, Tuesday 15 April 2025 - last comment - 17:32, Wednesday 16 April 2025(83939)
New SR3 Top2Top TFs with damping loops on

Back in August 2023 the damping gains for SR3 were reduced from -1 down(up?) to -0.5 to help with noise in DARM (72130). Since that change, we had never taken a set of transfer functions with the damping loops on with these new gains, so today I took those. The resulting transfer functions don't show too much damping, which is expected.

The data can be found in ../HLTS/H1/SR3/SAGM1/Data/2025-04-15_2000_H1SUSSR3_M1_WhiteNoise_{L,T,V,R,P,Y}_0p01to50Hz.xml, and has been committed to svn as r12228.

The results can be found in ../HLTS/H1/SR3/SAGM1/Results/ as 2025-04-15_2000_H1SUSSR3_M1_ALL_TFs.pdf and 2025-04-15_2000_H1SUSSR3_M1.mat, and have been committed to the svn as r12229.
 

Non-image files attached to this report
Comments related to this report
oli.patane@LIGO.ORG - 17:17, Wednesday 16 April 2025 (83963)

Linking analysis pdf showing cross coupling between all DOFs

Non-image files attached to this comment
oli.patane@LIGO.ORG - 17:32, Wednesday 16 April 2025 (83964)

Also adding a comparison between this measurement and the last time that we took damped transfer functions since those previous measurements would have been taken with a different set of damping gains.

The last time a damped measurement was taken was back in 2015, and those transfer functions look a lot different than the model and this recent measurement, so I also looked at the next previous damped measurement, from 2014. This one was in phase 2b, so not in chamber, but here at least we see that these damped measurements match up pretty well both with the model and with the recent measurement.

This PDF along with a zoomed in version of some of the plots can be found at /ligo/svncommon/SusSVN/sus/trunk/HLTS/Common/Data/ as

     allhltss_DampingOnComparison_H1SUSSR3_M1_Apr25vsFeb15vsMar14_ALL_TFs.pdf

     allhltss_DampingOnComparison_H1SUSSR3_M1_Apr25vsFeb15vsMar14_ALL_ZOOMED_TFs.pdf

and have been committed as r12251.

Non-image files attached to this comment
H1 PSL (ISC, PSL)
georgia.mansell@LIGO.ORG - posted 18:55, Thursday 03 October 2019 - last comment - 09:29, Thursday 17 April 2025(52292)
ALS pick-off update

Jason O, Georgia M

 

ECR 1900246

 

This week we have been in the PSL installing a new fiber pick-off for the ALS and squeezer lasers. The old pick off is on transmission of the reference cavity while the new one is on the ALS bypass, after the PMC. Peter K started this work a month ago (alog 51610).

 

We currently have installed a mode matching lens (f=200mm f=150mm) between the beam splitter and the steering mirror, and achieved ~73% ~82% power transmission through the fiber so far.

 

We think we can get more light through the fiber by tweaking the mode matching lens position. We will need to go back into the PSL again to finish this work and feed the fiber and photodiode cable out to the rack. 

 

Once the layout is finalised I'll update the psl table layout document (D1300348).

 

Modifications to the fiber distribution box are also ongoing.

Comments related to this report
jeffrey.kissel@LIGO.ORG - 12:38, Wednesday 16 April 2025 (83957)
J. Kissel for J. Oberling

As we work through the history of the ALS pick-off path in order to augment it and create an SPI pick-off path within (ECR E2400083), Jason shared a screenshot of his beam-profile model from JAMMT when he suggested placement of ALS-L5 (the f=150 mm lens mentioned abov). I post it here for historical reference.

For the record the fiber collimator used in the ALS/SQZ distribution pick-off is a Thor Labs F220 APC-1064.
Images attached to this comment
jason.oberling@LIGO.ORG - 13:18, Wednesday 16 April 2025 (83958)

So there is clarity here for future reference, I created that quick-and-dirty JamMT model from the as-built LHO PSL table layout in March 2024, not when the ALS pickoff was installed in October 2019.

Further, the SPI pickoff install team discovered that the as-built PSL table layout has had an error in the ALS beam path since the IO side of the PSL table was installed during aLIGO PSL installation in the 2012 timeframe.  The beam line from ALS-M1 to ALS-M2 is misplaced on the as-built layout; the layout shows the beam line along table row 23 but in reality it is along table row 25, 2 inches further +Y (using the IFO coordinate axes) than the layout indicates.  Corey took pictures of the PSL table in 2013 (D1301029) that show ALS-M1 in line with the 2nd ISS turning mirror, which is along table row 25.  Because of this the distances shown on the JamMT model are too short by 2 inches, rendering the beam waist size and location results given by that model incorrect.  In addition, the overall ALS path is longer by 4 inches than the as-built layout implies. 

I will correct this when I update the PSL as-built layout after the SPI team is done.

jeffrey.kissel@LIGO.ORG - 09:29, Thursday 17 April 2025 (83970)
Right! The mode-matching model that Georgia put together can be found in an other file in the ECR E1900246, specifically PMCtoFiberMM.png.
Displaying reports 1441-1460 of 82999.Go to page Start 69 70 71 72 73 74 75 76 77 End