Janos, Gerardo, Dave:
Following some alarms overnight we have decided to remove the LVEA gauges from VACSTAT for the duration of the vent. The other gauges which will remain under vacuum continue to be monitored, but without the increased sensitivity settings.
In order to keep the EDC green, a vacstat_dummy_ioc.py is running on opslogin0 to simulate the channels associated with the removed gauges (HAM1, HAM6, BSC2, BSC3).
The cell phone alarms to the vacuum group on multiple vacstat detections has also been disabled.
HAM1 alarms have been removed from the system for the duration of the vent.
TITLE: 04/02 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 6mph Gusts, 4mph 3min avg
Primary useism: 0.17 μm/s
Secondary useism: 0.17 μm/s
QUICK SUMMARY:
IFO is in PLANNED ENGINEERING for the vent.
Today's vent tasks:
Work safe!
WP 12424
The field cabling for RM1 and RM2 was disconnected in the CER and field rack. Cables were pulled back from ISC-R4 to SUS-R1. Cables were installed early on and buried in the cable tray. It was decided to cut the connector to ease cable work. Ends will need to be re-terminated. The PM1 field cables arrived onsite and will be installed tomorrow. Work will be outside the HAM1/2 clean room.
WP 12393
The SEI field cables were pulled to the following HAM1 flange locations:
Corner 1 (GS-13, L4C, ISI Coil Drive) to Flange D1
Corner 2 (GS-13, L4C, ISI Coil Drive) to Flange D5
Corner 3 (GS-13, L4C, ISI Coil Drive) to Flange D3
HEPI Corner 1&2 to Flange D5
HEPI Corner 3 to Flange D3
WP 12421
Cabling to IOHT2L and ISCT1 was disconnected. Both sets of cables were pulled out of the clean room, clear of any HAM1 activities. The safety interlock system was tripped when cables were being moved off ISCT1. Safety system was restored. The field EtherCAT field boxes EL1908 and cables are located on top of HAM1. They should not interfere with door removal/install.
WP 12422
The vertical cable tray, conduit and part of the floor cable tray was removed to clear the HAM ISI Installation Fixture. Cables to ISCT1 are now routed along the cable tray outside of the clean room.
We took time to pull out various DB cables, fibers, RF cables ect that were not being used. Area around HAM1 is now clear. Let us know you see or need anything else moved/cleared for the ISI install.
F. Clara, O. Patane, M. Pirello
- The corner station clean air supply (Kobelco) was started up - The following GVs have been closed: GV5, GV2, RV1, FCV1, FCV2, FCV3, FCV4, FCV5 - The IPs adjacent to this part of the corner volume have been valved out: IP1, IP2, IP3, IP4, IP14 - The replacement of the HAM6 gauge was attempted, but the electronics of the brand new Inficon replacement gauge is faulty, therefore another one will be installed tomorrow - The Y-manifold turbo has been valved in with a leak checker backing, and the following flanges have been leak checked (no leaky flanges yet): - Y-manifold flanges: - X-; Y+ flanges (3 pcs.) - Vent port (1 pc.) - BSC8: - X- HEPI bellows (2 pcs.) - X- collar flanges (4 pcs.) - X+ Y+ side flanges (3 pcs.) - X+ door flanges (5 pcs.) - HAM2-HAM3 spool: - X+ Y+ side flanges (5 pcs.) - X+ bottom flange (1 pc.) - HAM3: - Y+ door flanges: (5 pcs.) - X- bottom flange (1 pc.) - Y+ bellows (2 pcs.)
TITLE: 04/01 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
IFO is in PLANNED ENGINEERING for VENT
Extremely productive first vent day in which the following planned tasks were completed:
As always, check out the trello for the most up to date vent news.
Guardian states are in the configurations attached in the screenshot
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
14:39 | FAC | Eric | Woodshop | N | Activate Fire Pumps | 16:21 |
15:05 | EE | Fil | LVEA | N | HAM1/2 Table Enclosure Disconnect | 23:52 |
15:10 | FAC | Kim, Nellie | FCES | N | Technical Cleaning | 15:39 |
15:12 | OPS | TJ | LVEA | N | LVEA to Laser Extra Safe (Keys, Light Pipes etc) | 15:30 |
15:34 | PCAL | Tony | PCal Lab | Local | Meas. Setup | 16:47 |
15:39 | FAC | Kim | EX | N | Technical Cleaning | 17:00 |
15:40 | FAC | Nellie | EY | N | Technical Cleaning | 16:22 |
16:09 | AOS | Betsy | OptLab | N | Power meter | 16:22 |
16:24 | FAC | Tyler, Eric | LVEA | N | Scissor lift, Crane Work | 18:27 |
16:24 | SAF | Camilla | LVEA | N | Guillotine for viewports | 19:05 |
16:26 | VAC | Janos, Gerardo, Travis, Jordan | LVEA | N | Corner Vent Prep | 19:25 |
16:26 | EE | Betsy | LVEA | N | Checking on Fil team | 17:11 |
16:36 | AOS | TJ | LVEA | N | Wrap Bag Tag Help | 19:05 |
16:46 | SEI | Jim | LVEA | N | Locking HAM HEPIs | 18:01 |
17:01 | FAC | Kim, Nellie | LVEA | N | Technical cleaning | 18:49 |
17:30 | FAC | Richard | LVEA | N | HAM1 Conduit | 17:45 |
17:43 | AOS | Ibrahim | LVEA | N | Moving ISC tables | 19:05 |
17:51 | FAC | Betsy | LVEA | N | Looking at cabling | 19:05 |
18:09 | ISC | Rahul, Mayank, Siva | OptLab | Local | ISS array work | 22:56 |
18:20 | CAL | Tony | PcalLab | Local | Measurement setup | 18:30 |
18:25 | SEI | Jim, Mitchell | FCES, Ends | N | Picking up parts and FAMIS tasks | 21:20 |
19:17 | FAC | Chris, Eric, Tyler, Randy | LVEA | N | Cleanroom move | 20:52 |
19:35 | EE | Oli | LVEA | N | Helping Fil | 22:29 |
19:43 | VAC | Gerardo | LVEA | N | Cleanroom move help | 22:06 |
19:58 | AOS | TJ, Camilla | LVEA | N | Move Scaffolding by HAM1/2 | 20:34 |
20:07 | VAC | Janos, Jordan | LVEA | N | Leak Checks | 22:06 |
20:14 | PCAL | Tony | PCAL Lab | N | PCAL Meas. | 20:20 |
20:46 | ALS | TJ | EX, EY | N | Turning on ALS | 21:27 |
20:56 | FAC | Tyler | LVEA | N | Sock Swap | 21:38 |
21:33 | TCS | Matt, Camilla | OptLab | Local | CO2 Table Work | 22:56 |
21:52 | SEI | Mitchell | LVEA | N | Seismic Assy Size Verification | 21:58 |
21:53 | AOS | Betsy | LVEA | N | Walkabout | 22:33 |
22:06 | EE | Marc | LVEA | N | Helping Fil and Oli with HAM 1/2 Table Enclosures | 00:05 |
22:07 | VAC | Janos | LVEA | N | Leak Checks | 22:41 |
22:41 | VAC | Travis, Gerardo, Jordan | LVEA | N | 23:41 | |
22:42 | FAC | Tyler | LVEA | N | Rigging Transportation | 22:53 |
23:14 | AOS | Betsy | LVEA | N | 23:25 | |
23:29 | OPS | Ryan C | LVEA | N | Dust monitor connectiom | 00:29 |
TJ, Ibrahim, Betsy, Camilla, WPs 12428, 12414
We added guillotines to all VPs, removed the bellows and added yellow VP covers. IOT2 bellows were very tight so couldn't be removed until we moved the table an ~inch away from HAM2. The tables bellows adapters were covered with ameristat and the bellows were covered with foil and placed on a nearby rack. Photo.
We moved the small garbing cleanroom up against the TSCY / the HAM3 cleanroom. We moved ISCT1 and IOT2 next to it on the other side of the racks, leaving space and a pallet for the HAM1 door. Photo.
TJ and I removed and disassembled the HAM2 scaffolding and stored it with the other scaffolding in the High bay.
Tue Apr 01 10:12:47 2025 INFO: Fill completed in 12min 43secs
FAMIS 24833
pH of PSL chiller water was measured to be between 10.0 and 10.5 according to the color of the test strip.
Eric, Dave:
Bypass will expire:
Tue Apr 1 11:52:44 AM PDT 2025
For channel(s):
H0:FMC-CS_FIRE_PUMP_1
H0:FMC-CS_FIRE_PUMP_2
Alarms has been reconfigured to expect GV2 and GV5 to be in the hard-closed position and alarm if not.
Added PT114 (CP1)
Bypass will expire:
Tue Apr 1 12:40:00 PM PDT 2025
For channel(s):
H0:FMC-CS_FIRE_PUMP_1
H0:FMC-CS_FIRE_PUMP_2
H0:VAC-LY_Y3_PT114B_PRESS_TORR
Added GV5 position alarm to bypass
H0:VAC-LY_GV5_ZSM159A_VALVE_ANIM
We are getting multiple VACSTAT alarms as gatevalves are being closed, so for now I've bypassed those cell phone alarms.
H1:CDS-VAC_STAT_GLITCH_DETECTED
TITLE: 04/01 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Lock Acquisition
OUTGOING OPERATOR: TJ
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 8mph Gusts, 4mph 3min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.22 μm/s
QUICK SUMMARY:
IFO is in NLN and OBSERVING, but not for long.
H1 was running PEM Mag injections when I walked in, which finished and went into OBSERVING thereafter. I will induce a lockloss and set IFO to PLANNED ENGINEERING shortly.
Today is the first day of our planned Vent Break! Here is a summary of today's planned activities, also found on Trello Coordination Page
Work safe everybody!
Workstations were updated. This was an OS packages update. Conda packages were not updated.
Just had a ~3min drop from OBSERVING due to SQZ, but it cameback automatically.
Did notice the SQZ_OPO_LR node has the familiar User Message:
"pump fiber rej power in ham7 high, nominal 35e-3, align fiber pol on sqzt0"
It's been trending up the last 5 days when it was last touched up on 3/26 (alog83570). Looks like it moved above 0.35 counts at 10am (local time) this morning. See attached.
It's been a few minutes and one can see H1's range took a step down about 6Mpc after this SQZ drop.
Camilla, Sheila.
The drop was because the OPO PZT ran out of range, see t-cursor on attached plot. It's a known issue that the SQZ angle (and alignment) changes with different PZT1 voltage.
It seems like that the sqz angle was set for 60-70V and was bad once we relocked at 100V. This would have been improved by taking SQZ_MANAGER to SCAN_SQZANG_FDS so it can find the best sqz angle again. If we were running the SQZ_ANG_ADJUST servo, this may have improved itself as you can see the ADF reported SQZ angle change at the time.
With the higher (19 vs 11) NLG 83665, the range and 350Hz SQZ (yellow BLRMS) does seem to be improved, but the high frequency SQZ did seem to be less stable as we thermalized.
[M. Todd, C. Compton]
Camilla and I made several knife edge measurements of the L5 CO2 laser in the optics lab after she got back from her trip to Access. The beamwidth estimates are consistent with tests done by Gabriele and Camilla
Measurements:
Fits to both the numerical derivative and cumulative yield similar estimates of the beamwidth (1/e^2 radius) : around 1.3mm at 16cm from the aperature is consistent with the beam profiles done in Gabriele and Camilla's test, which estimated the beam waist to be around 1.2mm.
Code for analyzing this data
Follow up to LHO alog 83200 and LHO alog 80863.
Brian and I thought of a better way of getting the M1 OSEMs in PR3 calibrated relative to the HAM2 GS13s: Use the ISI drives in L, T, V for frequencies above the suspension resonances to get an absolute calibration.
We can use the measurements Jeff took in LHO alog 80863 and project them in the OSEM basis, then use the translational (Longitudinal, Transverse, Vertical) drives to calibrate the OSEMs. Since the GS13s are calibrated to [m] all of the transfer functions (shown in the first attachment) are in [OSEM meters]/[GS13 meters]. At high frequencies (sufficiently above the resonances) the OSEMs should just be measuring (-1)*ISI motion, because the suspension is isolated. The calibration error will depend on how well we are able to drive L,T,V from the ISI without cross-coupling to any other DOF.
Figure 1 attached shows the 6x6 transfer matrix between the ISI drives and OSEMs (inputs are columns, and outputs are rows). We highlight the 6 translational transfer functions that can be used to calibrate the OSEMs in red. The drives seem decoupled enough to do the calibration (for example, we expect to see a length drive only in LF and RT, no motion anywhere else).
Figures 2,3, and 4 show a detail of the 6 transfer functions we will use for calibration, all of them should be scaled to 1 [OSEM m]/[GS13 m]. The scalings are:
Adding here the phases for the TFs used for the calibration. There's a 20 to 25 degree phase loss after the last resonance up to 20 Hz. I'm not sure what more to make out of it, I thought the phase loss would be an artifact of the OSEM readouts, but maybe someone with more knowledge can chime in.
One way to fix the cross-coupling without having to get the absolute calibration is to slightly modify the M1 PR3 osem gains. They currently sit at:
T1 T2 T3 LF RT SD
1.161 0.998 1.047 1.171 1.163 1.062
Their new values would be at
T1 T2 T3 LF RT SD
1.164 0.903 0.866 1.073 1.199 0.942
This change will still leave a scaling factor of 1.54 m/(OSEM m), but at least it should fix the L-Y and the V-P-R cross couplings.