H1 SEI (DetChar, PEM, SYS)
jeffrey.kissel@LIGO.ORG - posted 10:46, Tuesday 05 August 2014 (13211)
H1 EX BRS Installation, Day 1
J. Kissel, K. Venkateswara, E. Shaw

Krishna and Eric arrived yesterday, and we've begun installation of the Beam Rotation Sensor at H1 EX. Pictures attached!

Some quick notes -- the center of the platform is roughly 41" WEST (+Y), and 9" SOUTH (-X) of the GND T240, and aligned with the IFO's X-axis, parallel to the line formed by the GND T240 and PEM Guralp. 

I also attach a screen shot of the custom overview screen I created.