H1 TCS (TCS)
thomas.vo@LIGO.ORG - posted 19:49, Wednesday 13 November 2013 - last comment - 10:28, Monday 18 November 2013(8522)
TCS ITMX In-Vacuum Mirror Alignment
Alastair H. Greg G. Robert S. Thomas V.

We were able to complete the alignment of this set of mirrors tonight. One of the 10-24 vented SHCS on the back of the SM2 mirror in BSC2 got bound up and broke at the head but we decided to move forward with the installation and were able to get the mirror secured.  Although all the bolts are tightened down to their capacity on both mirrors, the alignment is still vulnerable to being bumped.
Comments related to this report
mindy.jacobson@LIGO.ORG - 10:28, Monday 18 November 2013 (8603)
The location of the broken and the loose bolts are identified in the attached sheet (2) of the assembly drawing
Non-image files attached to this comment