H1 AOS
robert.schofield@LIGO.ORG - posted 18:02, Thursday 07 May 2026 (90162)
Status of baffle installation in HAM3

Mitchell & Robert

Mitchell and I installed baffles on the +X side of HAM3 and we installed the scraper baffle extension on the -Y side of the scraper baffle. We also removed the lower central piece of the MC baffle near HAM3. Pictures of all of these are in the attached pdf. We are stopping now for a couple of weeks until the SPI baffles have been installed to avoid interference. When we get back to this, we will install the baffles on the -X side of the table, install the central scraper baffle extension, replace dog clamps on PR2 with shorter clamps so they dont glint, install a POP path baffle, and make final adjustments of the baffles using beam-spot photos. 