TITLE: 05/19 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 4mph Gusts, 1mph 3min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.19 μm/s
QUICK SUMMARY: No alarms overnight, temperatures and dust counts looking normal. More alignment work in HAM2 planned for today along with continued prep on the BBSS in the LVEA west bay. CR workstations and wall FOMs are finishing their restarts.
Workstations were updated and rebooted. This was an OS packages update. Conda packages were not updated.
J. Freed
Update from last time 90231:
1. The funny set up from 90231 (IMG_0627.jpg) Was removed! *Clap*. The Spitter was moved lower on the rack and attached on the side of slot 11 with zip ties Photoon5-18-26.jpeg Photoon5-18-26at317 PM.jpeg. Note: The metal of the splitter was not separated from the metal of the rack, unsure if nessisary. Attinuators were added on each side of the splitter.
2. The 4096 Hz CDS DAC signal was tested and connected to the Double Mixer, the double mixer output was quickly checked on an osciloscope and nothing looked different from testing.
3. The current expected RF power going into the SPI prep chassis is 31.6dBm for both the meas and ref paths (Using 2x 10dB and 2x 2dB attinuators) which is slightly underpower of the expected 32 dBm. Screenshot2026-05-18at52906 PM.png I figure a slight underpower is better than an overpower. But will add a comment here if that changes. Will also check to be sure once the 2W amp is installed
4. Found a box of SPI cables that we bought, (whoops forgot about those). All cables in the current set up were replaced with the bought ones. All cables were also labeled.
SPI_HAM3_Linear_ish_Layout.png: I realized now the Screenshot2026-05-18at52906 PM.png picture is impossible to read clearly. I made a more "linear" and hopefully clearer picture of RF chain.
[Keita, Rahul, Elenna]
Today I moved IM2 and IM3 to bring the beam back to our reference position on IM4 trans QPD and center it on ISS QPD after Keita's move of the mode cleaner mirrors in 90259. This requires some iteration back and forth on both suspensions.
Our desired positon on IM4 trans is P = 0.22 and Y = -0.06. On ISS QPD, it is centered, so P=0 and Y=0.
We are driving MC2 in length, so the mode cleaner is flashing, and there are bright flashes on the QPDs. I am pausing ndscope on a flash and measuring the height of the peak in the fast channel and calculating the pit and yaw position from each QDP segment.
| Start | End | ||
| IM2 P slider | 765 | IM2 P slider | 810 |
| IM2 Y slider | -187.7 | IM2 Y slider | -88.7 |
| IM3 P slider | -560.7 | IM3 P slider | -614.7 |
| IM3 Y slider | 320 | IM3 Y slider | 385 |
| IM4 trans PIT | 0.390 | IM4 trans P | 0.268 |
| IM4 trans YAW | 0.450 | IM4 trans Y | 0.010 |
| ISS QPD PIT | -0.379 | ISS QPD PIT | -0.059 |
| ISS QPD YAW | -0.455 | ISS QPD YAW | 0.08 |
Unfortunately, this still results in clipping on the baffles Keita notes above, so we will keep going.
At the nominal IM4 trans position, yaw is pretty well centered. I then moved IM2 to both edges of IM4 trans QPD.
I changed the IM2 yaw slider to -250.7, which brought the yaw position on IM4 trans to 0.85. This made the clipping worse.
I changed the IM2 yaw slider to 90.3, which brought the yaw position on IM4 trans to -0.88. This was still not good enough to fix the clipping on the baffle.
By making a very large move to IM2 yaw slider value of 710.3, this centered the beam in the IM4 baffle. This is a ~800 urad move according to the osems and slider. The IFO REFL beam is still clipped.
I undid the 800 urad move, so the IM2 yaw slider is back to -88.7 for now.
Keita and Rahul went out to measure the position of the beam on MCs 1,2 and 3. We think that we need to make a move of these three mirrors to see if we can unclip the beam on these baffles that way.
We want to note that the positive yaw move of IM2 corresponds to unclipping on the IM4 baffle, this is consistent with the beam motion observed in chamber in the -X direction. However, this is contradictory to the sign on IM4 trans QPD, which was moving to negative yaw when we did this move. We suspect that the segment defintion must be wrong somewhere.
Keita will say more later once we have a chance to analyze the positions in chamber.
To clarify, the slider values of IM2 and IM3 are left at the "end" positions on the table above.
R. Crouch, B. Weaver, I. Abouelfettouh, J. Oberling, R. Thompson
Today we placed and aligned the BBS SUS cage on the WBSC2 ISI. In the morning we rough placed the SUS, and thought we had done a really good job on the first attempt. However, that was fed by a misread of how the Build/Inspect function in PolyWorks, well, works, and upon doing a more thorough measurement (directly measuring a constraining plane to inform SMR radius compensation instead of letting PolyWorks handle it automatically) we found there was a position and rotation error to the cage.
In the afternoon we moved the SUS cage around until things looked really good. We were well within our +/-1.0 mm XYZ tolerance, but once the SUS had been fully dog clamped to the ISI things shifted (as they do). In this case, it was roughly 0.5 mm in the +Y direction. All of our measurement points except one are within tolerance, so we called this good enough for SUS cage placement. To end, Ryan and I measured the circle that's defined by the lower section of the Figure 8 (the round section of the SUS cage that surrounds the BBS) on both the HR and AR sides of the cage. The first attachement shows the position deviations of the 4 points we used for cage placement/alignment and the current position of the HR and AR Figure 8; all except the Y axis position of 1 point are within our tolerance. The second attachment shows the rotation of the SUS cage w.r.t. the ISI; the angles listed are in degrees and are measured from the positive axes they are associated with (so X Ang is measured from the +X axis). These 2 lines show that the SUS cage is rotated roughly 400 - 500 µrad CCW (top-down view) from nominal.
Next up is to set up a total station looking at the AR face of the BBS to precisely align the optic to the ISI.
Ibrahim, Betsy, Randy, Jason, Ryan C
Today, we lifted the BBSS into the ISI. We then secured and aligned it with the help of IAS (Ryan C and Jason - seperate alog which will be linked later).
We used the aluma lift and dog clamps with the help of teflon pads to move the strucutre about the lift within dog clamp boundaries to align it to the ceiling to the model.
The alignment was done by touching the FARO SMR to the corners of the top of the lower structure to determine if translation or rotations were needed on the structure.
We also inspected BBS01 and found some particulate on the center of S1. Thankfully, it blew off using the N2 Top Gun.
Particle counts were checked in cleanroom periodically and were below 50 consistently.
See pictures.
TITLE: 05/18 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Alignment work continued in HAM2 today, along with more prep of the BBSS and IAS surveying on the test stand. Since SPI alignment is ongoing on the optics lab, the laser remains on and running unattended with appropriate barriers and signage up.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 19:43 | SAF | LASER HAZARD | LVEA | YES | LVEA IS LASER HAZARD | Ongoing |
| 14:50 | FAC | Kim | LVEA | - | Technical cleaning | 16:09 |
| 15:19 | VAC | Jordan | LVEA | - | Pump checks | 15:26 |
| 15:55 | FAC | Randy, Jeff | LVEA | - | Moving IOT2L a little | 16:16 |
| 15:55 | SPI | Jeff | Opt Lab | Local | SPI prep | 18:28 |
| 16:29 | IAS | Jason, Ryan C | LVEA | - | BS FARO surveying | 19:55 |
| 16:30 | ISC | Keita | LVEA | - | Opening lightpipe | 16:44 |
| 16:46 | SUS | Betsy, Ibrahim | LVEA | - | BBSS work | 18:34 |
| 16:52 | TCS | TJ | LVEA | - | Checking on TCSY water lines | 17:10 |
| 17:09 | SUS | Randy | LVEA | - | BBSS work | 20:09 |
| 17:18 | SPI | Josh | LVEA | - | SPI work at SUS-R2 | 18:32 |
| 18:04 | ISC | Keita | LVEA | Y | HAM2 beam alignment | 18:28 |
| 19:26 | SPI | Jeff | Opt Lab | Local | SPI alignment | 21:53 |
| 19:37 | ISC | Keita | LVEA | Y | HAM2 beam alignment | 19:47 |
| 20:10 | SEI | Fil | MER | n | HEPI electronics work | Ongoing |
| 20:10 | SPI | Josh | LVEA | - | SPI work at SUS-R2 | Ongoing |
| 20:11 | SUS | Betsy, Ibrahim | LVEA | - | BBSS work | Ongoing |
| 20:28 | SUS | Randy | LVEA | - | BBSS work | 21:38 |
| 21:06 | IAS | Jason, Ryan C | LVEA | - | BS FARO surveying | Ongoing |
| 22:24 | ISC | Keita | Opt Lab | - | Looking for parts | 23:02 |
| 22:44 | ISC | Rahul | Opt Lab | - | Looking for parts | 23:02 |
| 23:03 | ISC | Keita, Rahul | LVEA | Y | HAM2 beam alignment | Ongoing |
J. Kissel Picking up from last Friday (2026-05-15, LHO:90253), today I: - Secured D_R_P1 and D_M_P1 and confirmed that TFP REFL beams went into the dumps - Started aligning REF path and migrating optics over from the D2400107-v4 breadbord's CVM100 mounts into / onto D2400107-v5 IXM100 mounts: . R_M1 migrated. . Re-set up the power meter gantry assembly (since its only me, and I need the power meter stable for maximizing throughput thru irises) . Placed irises in holes 83 and 84, adjusted R_F1 and R_M1 to walk and align the beam thru irises, confirming with IR camera view of iris holes and power meter thru-put. . Secured R_F1 and R_M1 IXM mount 8-100 alignment screw shaft set screws, since these optics shall not move again. . R_B1 migrated. . Aligned beam through holes 86 and 95, repeating process above, but only adjusting R_B1. . Uncapped IFO_REF A and B PDs, PWRIN_REF PD and hooked them up to the o-scope (discovering a minor re-cabling issue; see LHO:90268) UNSOLVED SIDEQUEST (1) :: PWRIN_REF PD has a ~120 Hz oscillation on it. . R_B2 migrated. . Aligned beam through holes 98 and 99, repeating process above. UNSOLVED SIDEQUEST (2) :: Now, with D_FBR_PWRIN_REF so far away, the known issue with its PD seating within the generic enclosure means the PD reflected beam is ~2 inches above the board. Tried a huge 2"x3" dump but that was too big. . R_B3 migrated. . With nothing to align, just checked that beam went through irises in holes 100 and 97, and that beam looked well centered on PD. They did. . Migrated D_IFO_REF_B and D_IFO_REF_A, confirmed PD reflection landed on there and it did. Done for the day! The MEAS PATH alignment tomorrow!
Regarding UNSOLVED SIDEQUEST (2) :: Now, with D_FBR_PWRIN_REF further away [...] the PD reflected beam is ~2 inches above the board. Here're some picture to aide the discussion. I say "this is a known issue," because we'd encountered this particular PD's pitch of the diode when assembling the CVM100 version of the ISIK transceiver, D2400107-v4, but in that layout, the PD was angled away from the incoming beam in the opposite direction and the the dump was closer. We didn't have room behind R_B2 to have the same dump location with the upgrade to IXM100 mounts. None of the other PDs have this issue, the beam reflects back at the same 1 [inch] beam height that's the beam height for the board. We were in too much of a rush and had too little experience/expertise with these to consider cracking open the Generic PD enclosure (D1600083) to try to fix it. We suspect, in this Type 3 assembly for the FFD200 PDs, that either - the PD (line item 12 T1000573) is not seated well in its retaining ring (line item 4 D1600082), - there's a defect or something stuck between the retaining and its seat in the enclosure housing (line item 1 D1600079) - the retaining ring is not *exactly* the same size as the Q3000 for which it was designed and there's some slop in the assembly, or - the PD's pins were soldered into the PCB at an angle (line item 11 D1700116) But we're just guessing. This is S2401094, whose assembly technique is discussed in CIT:837 and record of completion is mentioned in CIT:898. Starting up the conversation with CIT.
Regarding UNSOLVED SIDEQUEST (1) :: PWRIN_REF PD has a ~120 Hz oscillation on it. See attached o-scope picture -- channel 3 (purple). 2V peak-to-peak wobbly 120 Hz oscillation on a 4.5 [V] mean. We've not tested this PD since we updated its transimpedance circuitry (see LHO:90105, and TIA Variant 3 D1002481 instantiation S2500713), so there may be a grounding issue there. Hard to believe it's the TIA op-amp itself, given that the RC feedback impedance we installed yields a 13.497 [kHz] pole. I've only tested the IFO MEAS and IFO REF channels of the Variant 2 chassis with light so far, but they don't show any issue. Laser power level on this PD during yesterday's test is the expected ~0.8 [mW]. I checked (but didn't re- or triple-check) that the electrical ground situation is well-managed. As in March 2026, the electrical ground of power supply feeding the TIAs banana'd-to-BNC'd-to-clip-doodled to the shield the o-scope's clip-doodle dongle whose signal is reading out PD ADC output voltage from a breakout board. Nowhere along this adpater/doodle/breakout/cable chain is metal touching metal. I'll look through the chain again, try reading it out differentially, and consult with local experts. It isn't a high priority right now, but we need to understand this before the transceiver leaves the optics lab.
FAMIS 63899
No major events of note; things looking very stable recently.
In preparation for testing out the BOSEMs on the BBSS, I've updated the OSEM2EUL and EUL2OSEM matrix values from the suspension projection values for the BSFM's geometry to projection values from the BBSS's geometry.
OSEM2EUL
before (BSFM projections), after (BBSS projections)
EUL2OSEM
TITLE: 05/18 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 12mph Gusts, 6mph 3min avg
Primary useism: 0.03 μm/s
Secondary useism: 0.15 μm/s
QUICK SUMMARY: No alarms over the weekend, temperatures looking normal, dust counts low as well. The same 31 channels are disconnected from the EDC since the CS HEPI pump controller is still down.
Likely continuing with alignment work in HAM2 today following the ISS array replacement.
TJ and I cleaned the BSC2 aluminum floor, the bottom of the chamber below that, feedthrough nozzles, support tubes and their nozzles (see figure for photo of cleaning and some of the stuff we found). The particulate level while walking around gently did not change significantly from before to after the cleaning (see table below). This and the other cleaning experiments reported in the table suggest that, at the current state of cleanliness, the dominant source of suspended particulate is the people and the things we bring in rather than dust that we stir up by moving around.
The dust counts generally returned to low levels a minute or two after the activities in the table.
Just as patting clothes produces more dust, we found that rapid movements produce more dust in the chamber than slow movements. The linked video shows the movement speed and the wiping speed that produced the lower levels in the table below: slow chamber speed.
Recommendations:
1. The chambers are currently clean enough that general cleaning is probably counterproductive.
2. Move slowly when possible. This can reduce the particulate suspended from your bunny suit by an order of magnitude.
|
Activity |
Particulate per cubic foot* |
|
|
0.3 um |
0.5 um |
|
|
Standing still in chamber |
0 |
0 |
|
Walking around gently in BSC2 before cleaning |
150 |
80 |
|
Walking around gently in BSC2 an hour after cleaning aluminum floor, bottom of chamber, and all nozzles |
170 |
85 |
|
Wiping aluminum BSC chamber floor |
200 |
50 |
|
Wiping feedthroughs and their nozzles |
200 |
70 |
|
Cleaning support tubes and their nozzles |
100 |
60 |
|
Slow wiping of BSC floor under aluminum floor towards center (lowest part) |
200 |
50 |
|
Fast wiping of BSC floor under aluminum floor towards center (lowest part) |
800 |
500 |
|
Deploying vacuum hose and accessories |
1000 |
800 |
|
Vacuuming up material wiped to center of BSC floor |
200 |
50 |
|
Vacuuming bellows with tube accesory that fits between them |
600 |
150 |
|
Vacuuming walls in spool piece |
200 |
50 |
|
Vacuuming aluminum floor in chamber while hose assembly is dragging |
600 |
200 |
|
Waving hand up and down while standing still outside the chamber |
150 |
50 |
|
Waving hand up and down while standing still inside the chamber, monitor at same relative position |
200 |
70 |
* Particle counts are aproximate averages, mostly of 1 minute samples. Repeats suggested that differences in the table of a factor of two or greater are significant. Quiet controls were taken in between reported measurements to ensure that measured levels were not significantly affected by previous activities. Monitor: Met One GT-521S laser particle counter
TJ and Robert
Clipping on IFO REFL baffle is gone.
The problem of IFO REFL beam clipping by the last IFO REFL baffle in HAM2 (see alog 90251, especially this picture) seems to have been caused by a huge PRM change in the PRM alignment sliders made on Monday May/11/2026 past 1700 local time (that none of us knew/remembered/understood).
Once Sheila reverted PRM back to March/2026 alignment, changing the IFO REFL beam path (but not the alignment into ISS path), IFO REFL was not clipped any more even though it looked low on the baffle (IFOREFL_baffle.mp4). LSC and ASC REFL sensors on HAM1 ISI saw the flashes right away without any adjustment of RMs, and the flash peaks were already reasonable. According to Sheila, compaing to a time when DRMI was acquiring in November:
All of these were a good sign.
Forward-going beam into the IM4 is clipped by the baffle in front of IM4, and the IFO REFL beam is clipped by the baffle at the -Y edge of the IFI.
Unfortunately I've found that there were two other clipping points that I must have missed yesterday using IR viewer. See clipping.png, sorry for a blurry through-IR-viewer picture shot from the distance. Go back to HAM2layout_annotated2.png to figure out which baffle is what.
There's a baffle in front of IM4 between IM4 and IM3, and the forward-going beam is slightly clipped at the +X edge of that baffle.
Also the IFO REFL beam is clipped by the baffle installed at the -Y edge of the IFI. I know this is IFO REFL because the bright spot goes away when I block the beam on PRM by a sheet of aluminum. I cannot quite tell from the picture which edge of the baffle is clipping, but I think it's also +X edge.
In the past, when PRM spot position was measured with full IFO, it was like a mm off according to Sheila, so it's hard to imagine that the beam was clipping on the baffle in front of IM4.
Changing IMC alignment (trial 1, didn't fix clipping).
We decided to back off the changes we've made for MC1, 2 and 3 since Monday and revert back to in-vac March alignment. If we have to make a huge adjustment to JM3 to follow the IMC, maybe the beam coming from JM3 is suspect (which means that the MC2 trans path is somehow suspect too).
Before I did anything, the starting point was captured in alignment_2026-05-15_16-14-21.png.
MC1/2/3 was reverted just based on slider values and not using OSEM readings as per alignment_2026-03-18.png.
Then JM3 was adjusted in PIT and YAW to give the maximum transmission measured in IM4_TRANS_NSUM. Actually I didn't move JM3 as much as I expected.
That alone couldn't recover a good 00 mode flashing so I moved MC2 and MC3 to follow the input beam. MC2 moved back closer to the position this morning.
After that I felt as if it was somehow easier to optimize further using MC1 as well as MC3, thinking that it would be a minor adjustment but somehow ended up moving MC1 by a large amount after iterations.
My end point is captured in alignment_202605151726_sliders.png.
Without IM3 and IM2, the beam was still on IM4_TRANS as well as ISS QPD, the flashes were good, so I looked at the clipping on the baffle in front of IM4 as well as the baffle at the -Y edge of the IFI, and they were still there. IFO REFL baffle was still not clipping.
Will have to think about what these all mean.
Ibrahim, Betsy, Oli
Today, we installed BBS01 into the BBSS successfully.
BBS01 was on a table. BBSS was on the aluma lift. We picked BBS01 using the ERGO arm and slowly came into the optic. In this process, we:
On top of pictures below, 2 videos:
Wahoo! Congrats, y'all!
Note, current status as of last Thur was handoff to FARO IAS (Jason/Ryan C) who are up for mapping and guiding us into place. CAD files from CIT arrived Thur so quite literally just in time to get on it.
Also, thanks Travis for all the pictures.
J. Kissel SPI Wiring Diagram: D2400111-v6 In-chamber in-vac cable routing: In-vac Cable Routing Plan from G2401479-v3 I never aLOGged our choice of cable-table bracket floor assignment down when we originally assembled and signal-checked the D2400107-v4, so during disassembly in prep for upgrade to D2400107-v5 (LHO:90225) I took the time to write down the cable routing, cable serial number assignment, and cable table bracket (CBT) floor assignment: Path PD Name PD SN Duopus D9 CBT Name / Floor Quadrapus D25 CBT Name / Floor |----------D2600001--------| D1600083 Type 2 D2400341 D2000492 D2400343 D2000492 S2500512 IFO REF A/B S2401096/S2401095 S2500516 CBT 2 / 2nd of 2 cable E CBT 1 / 1st of 2 IFO MEAS A/B S2401097/S2401098 S2500514 CBT 2 / 1st of 2 cable D CBT 1 / 1st of 2 FBR PWR REF/MEAS S2401094/S2401093 S2500515 CBT 3 / 2nd of 2 cable C CBT 1 / 1st of 2 PD SN Monopus |----------D2600002--------| D1600083 Type 3 D2400340 OL ISIK QPD B S2401091 S2500518 CBT 3 / 1st of 2 cable B CBT 1 / 1st of 2 First and Second of the attached pictures are of the CBT 2 cable routing. I needed two pictures because the D9 end's two-part backshell of IFO REF cable was assembled with its serial number stamped on one side of one part, and the other side of the other part. C'est la vie. Third picture is of CBT 3's cable routing. The 2x D9 CBT assemblies (since the "type" we've assembled is not explicitly drawn in D2000492) are - QTY 1x D2000519 baseplate - QTY 1x D2000520 "Type 2" two-floor uprights, with - QTY 2x D2200443 D9 adapters, - QTY 2x 1/4"-20 x 0.625" L captive SHCS (95966A512) for securing to the HAM table (rather than the 3/8"-16 captive SHCS that are used to secure to the BSC tables) - QTY 2x #6-32 x 0.375"L SHCS (92200A146) for securing the baseplate to the upright - QTY 2x per D9 adapter (4x total) #4-40 x 0.224"L ("2D"; 1185-04EN224) nitronic 60 helicoils for each of the upright holes - QTY 2x per D9 adapter (4x total) #4-40 x 0.5"L captive SHCS (95966A140) for securing the adapters to the upright For the single D25 2-floor CBT that holds the D25 ends of the PD and picomotor quadrapuses, we used the standard D2000492 Type 2 configuration.
Pictures of the D1600083 Generic PD enclosure ends of the D2600001 Assemblies In order of their appearance in D2400111-v6 page 3: - IFO_REFA - IFO_REFB - IFO_MEASA - IFO_MEASB - FBRPWRIN_REF - FBRPWRIN_MEAS - QPD_B
The main aLOG's table of cables and the pictures of the cables are correct BUT my *labels* of the picture are wrong for the Cable Table Bracket #2 (also, I abbreviated Cable Table Bracket as CBT rather than CTB). I attach new versions of the pictures correctly labeled. Found this after re-achieving light the REF PDs today, as the IFO REF PD signals appeared on the SPI TIA Variant 2 ADC output CH3 and CH4 which should be the IFO MEAS PDs (per LHO:89775). Sure-enough, I had paired the IFO MEAS PD duopus S2500514 with the E leg of the S2500512 quadrapus, and the IFO REF duopus S2500516 with the D leg, because I'd followed the *labels* of the picture to reconstruct the cabling. All fixed now in the D2400107-v6 assembly (and I confirmed that the C and B legs are hooked up correctly to the FBR_PWRIN and QPDB correctly and match the table, pictures, labels and ADC CH assignment.).
We started with yesterday's alignment. I checked flashes in ISS array PDs and didn't like that the balances between them were very much different from how they were when IMC was locked back in March.
Then we started changing IM2 and IM3 to see if we can get back, but I was appalled that the flashes became stronger and stronger on array PDs as we aligned, which probably means that the beam was almost falling off of the PDs when we started.
That shouldn't have stopped us because we don't know where the beam was on the array PDs when MC was locked (people gave up optimizing that path because things didn't make sense), it could have been falling off of the diode (because each diode is 2mm, QPD is 3mm, the beam size is ~250um or so, and the beam was almost in one quadrant of the QPD). But I started thinking about many what-ifs and wasted time.
After all, since IM4 TRANS and ISS array QPD are both reasonably close to March 2026 position, we know that the beam position as well as angle of the beam injected into ISS path from IM4 are already close to those when IMC was good in vacuum.
What we should do is this:
Other things to note:
This is not required for the alignment but it's helpful to know how much we can move the beam on QPD. In an unlikely event where we somehow lose the beam in vacuum on the array QPD after IMC is locked, we might be able to scan IM3/IM2 to regain the beam on QPD, and slowly move IM3/IM2 back to the nominal position while pico-ing so the beam isn't lost on the QPD. If the beam is not clipped, the beam displacement on the QPD is ~3mm per 1mrad of IM3 rotation using parameters collected from various documents, see attached script.
The same script shows you that the Gouy phase separation between two pico mirrors is 10 degrees (if we use the beam parameter in Matt Heintze's alog 12537, which was probably obtained by the measurement of the bypassed beam) or about 20 degrees (if we use IMC eigenmode parameter propagated to the ISS path using D1200693).
Another thing is, if we believe the design eigenmode number rather than the measured bypassed beam in Matt's alog, the beam waist will be smaller and at about 20cm upstream of the PDs. The beam size on the PDs is about twice as large as it should be (470um rather than 250um). I cannot measure the beamsize of the flashes so we won't do anything, but that's something to remember. If IM3 has enough actuation range, we can later lock the IMC, scan the beam across the PD until the beam falls off, see how sharp the fall-off is, and use the diameter of the PD (3mm) to determine the size of the beam. Maybe a good project for a fellow.
One of the things that bothered me (that isn't directly related to ISS alignment) is the fact that we had to rotate JM3 by a huge amount, i.e. negative 200um in PIT to "center" the MC2 trans QPD. This is the equivalent of the negative YAW rotation of the beam in IMC's coordinates (clockwise seen from the top). Since the distance between MC2 and JM3 is ~19m according to E2400218, this means that the MC2 beam position was moved by about ~7.6mm in -Y direction on MC2. This seems to roughly corroborate with the pictures in alog 90203 ("before" picture and "after", hard to tell how much it actually moved due to parallax but there's no doubt that the motion was large).
What if this is because something is wrong with the MC2 trans path? Like the pico mirror in front of the QPD was bumped (by a huge amount, however unlikely it is). My conclusion is that we can lock IMC in vacuum, use WFS with MC2 centering, measure the centering on MC2 using dither, and figure it out. If QPD center is grossly off from the MC2 center, we can pico.
Sorry the script in the above alog didn't work because it was missing one line.
Attached is a working version. You need a la mode matlab package https://github.com/nicolassmith/alm.