Gerardo pointed out that the HAM1 pressure had been rising for about an hour. Ryan checked that the JAC heater guardian was off. However, the JAC heater was still on at steady power. I called Jennie, and she turned the JAC heater power to zero. It had been set with a value of 0.749, which is not high compared to its usual value. We will monitor HAM1 pressure to see if it turns around.
TJ, Camilla, Tyler. WP 13451
The ITMY camera that was removed from A-1F VP3 in 90917 has now been reattached to A-1F VP2. The camera can extender needed to be reduced in thickness, Tyler did this. Camera can D970211-014, camera Balser, lens Rainbow H20X15M and adjustable post Giotto MH1303, are originally from ITMX, swapped so height would work better. CDS camera was down so we could not yet check and adjust pointing.
The ITMX reworked camera can is still too wide to for between the VP and Oplev Pier 91160, will now re-work the newer D1300705 type instead which will be more convenient with side access.
FAMIS 63909
Ignoring the past couple of hours when the laser went down due to interlock work and Jason and I went into the enclosure (alog91287), things are looking pretty good. The FSS RefCav transmission is drifting down and has generally been lower than we've seen it, so at some point before IR01 we'll go in and realign the FSS path. Next week I'll compare things after the PSL is recovered in the next couple of days.
I reconnected the vacuum lines used to pull air through the dust monitors that are stationed in the PSL laser room and ante room. Back in September 2025 (alog87005) they were disconnected because the old pump had been running in reverse after a power glitch and the carbon graphite vanes blew air through the lines as well as little bits of the vanes. Since then we have replaced all of these pumps with ones that cannot contaminate the areas they are trying to sample. The corner station is running on a scroll pump with a automated back flow valve and the end stations are on diaphragm pumps.
Dust counts in the PSL laser room and ante room should now be considered real.
TITLE: 07/28 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Ryan C
SHIFT SUMMARY:
Today was the first main day for the RCG Upgrade (so lots of systems are down for this work). The RCG work will definitely continue tomorrow!
LOG:
Ryan C, Rahul
The broken PSAMS unit has been replaced (again for the 2nd time in the last two weeks) with a repaired one (ZM5-SN4, repaired by CIT and characterized by Camille). Once the PSAMS optic was installed in ZM5 suspension, we suspended all stages and balanced it and laced the mighty mouse cable. ZM5 was then re-installed in HAM7 chamber and dogged down by two dog clamps for now.
Inside the chamber, the PSAMS and BOSEM cables are now connected to the electronics chain and all stages of the suspension are set free.
I will take health check measurements once the front end comes back online.
In the meanwhile we tested the PSAMS near the SQZ racks and the results are given below,
SG (Strain Gauge) resistance was measured to be 355.7 ohms (pin 11&24) and 707 ohms (pin 12&24).
We were able to drive the PZT voltage from 0 to 200V and obtain the strain gauge voltage ranging from 0.365V to 5.41V.
Attaching latest pictures of ZM5 below after it has been re-installed in the chamber.
J. Oberling, R. Short, T. Shaffer
This morning we swapped the temporary SPI shutter cable, for the shutter in the SPI pickoff path on the PSL table, with the permanent one. Once the old cable was removed we fed it out of the PSL enclosure wall penetration to TJ, who then fed the permanent cable into the PSL enclosure for us (thank you, TJ!). The cable was secured in the same was as the temporary cable was, see attached pictures. We tried to physically move the cable into the ALS beam path and were unable to do so; at rest the cable is ~2.5" from the ALS path and the closest we could get it was ~2", so the cable is well secured and unable to drift into the ALS path. This cable had been successfully tested with a spare shutter before installation, but due to the ongoing CDS upgrade we were unable to test it with the installed shutter; this will be done once everything is back up and running. This completes LHO WP 13464.
TITLE: 07/28 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 4mph Gusts, 2mph 3min avg
Primary useism: 0.03 μm/s
Secondary useism: 0.13 μm/s
QUICK SUMMARY:
Big item today/next few days is the RCG Upgrade, followed by access system work (taking down lasers), and this morning is cleanroom moving around Biergarten.
Last night, Betsy transitioned the LVEA to Laser Safe (Operations Phase...lasers can be on, VAC/Tables CLOSED). This Morning for the Access System work, we will be full on Laser Safe (Upgrade Phase...lasers OFF, VAC/Tables CLOSED)
IMC OFFLINE / JAC is DOWN. Just took SEI_ENV to MAINTENANCE. Will need to take SUS & SEI to desired states for the RCG work when we get the word.
WHOOPS!
Just noticed I forgot to hit "POST" for my Summary yesterday (We were transitioning to Laser Safety at "shift change"...and I was also trying to figure out how we shift change...since this is the first EVE shift I've had a hand-off for for a while! :)
TITLE: 07/27 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Ryan C Oli
SHIFT SUMMARY:
Today was last full day before the big CDS RCG work starting tomorrow. With that, JAC crew worked on final checks. There were checks on subsystem SDFS. HAM7 SUS work continued. CDS did prep work for tomorrow. Toward the end of the shift Betsy worked on transitioning the LVEA to SAFE. And I'm handing off to Oli.
LOG:
Pending Filter Files:
h1calcs had a modified filter file waiting to the loaded. The running filter file was last loaded 16jul2026, H1CALCS.txt was modified at 10:52 27jul2026 and not loaded. I made a local copy of the modified file, then removed the changes by doing a subversion revert. This cleared the CFC flag on h1calcs.
SDF Diffs:
Several models have outstanding SDF diffs (screen shots attached below)
| model | num diffs |
| susmc2 | 2 |
| susam | 8 |
| susomcab | 6 |
| susom1ab | 16 |
| susom2ab | 8 |
| susom3ab | 16 |
| isibs | 11 |
| isiham3 | 1 |
| isiham7 | 54 |
| calinj | 1 |
| calex | 1 |
Got some screen shots of a few different SDF Diffs.
I took these screenshots after Corey had already taken the SUS to SAFE state.
Also the LASER Stop button had already been pressed.
From what I can tell, I think we are mostly in a good spot for SDFs. The few items to note:
The two SDF screens we have are out of date. There have been many models added or names changed that we have not kept up with, and made this a bit harder. We will update these asap.
Elenna, Oli
We spent some time figuring out SDFs for the BBSS. It should be all good to go.
A couple of notable channels that will need to be figured out at some point are:
I've attached a pdf with the full list of sdf diffs that we accepted. The notable channels listed above are highlighted as * and **
Just want to add a note that for MICH locking we have been doing so successfully without oplev damping. We'll have to monitor once we get to PRMI and DRMI locking, but for now leaving the OLDAMP gains at zero is ok.
The Y2L gain seems like a spot position change, but I'm not aware of any spot position control on the beamsplitter specifically.
Ryan C, Rahul
In preparation for our second replacement of the PSAMS, we have taken SUS ZM5 out of HAM7 chamber and staged it on the table next to it. We took the bottom stage PSAMS out of the suspension cage - this unit has wires shorting inside the mirror housing.
Tomorrow morning we will start replacing it with the unit CIT has shipped us - which was originally installed in ZM5 (LHO) but broke down two weeks ago (Strain Gauge wire leads got loose inside), then got fixed at CIT and re-shipped to us with 65 in-lb torque.
Camilla, Rahul
SUS ZM2 in HAM7 chamber needed a pitch offload since it was using up a lot of DAC output. This morning we went to HAM7 chamber and at first confirmed the beam alignment and its position on the irises. Then I entered in HAM7 chamber and locked the suspension and unlocked the pitch adjuster screw. At first I gave it a full 1 turn anti-clockwise making ZM2 pitch down (and then unlocked the suspension) and Camilla confirmed that the alignment looked better but perhaps we overshot by a small amount. I retracted by 1/4 turn (thus making 3/4 turn anti-clockwise in total) and then the beam looked good on the iris. Before exiting the chamber I locked the screw for pitch adjuster and checked if all EQ stops were set free from the suspension chain.
Finally Camilla adjusted the alignment sliders on ZM2 for fine tuning it.
I took a quick chamber side transfer function measurements and the suspension was found to be healthy.
Here is Rahul inside HAM7, next to ZM5.
While I was fine tuning the alignment after this offload, I realized that the PSAMs setting was wrong. It appears that while this ZM2 work was happening that the ZM2 strain gauge reading has been shifted. We still have the same ΔV of 5V but the range used to be 1.2 to 6.2V plot and now is 4.6 to 9.6V plot. CIT has possibly seen this before in T2300426 but the effect was less.
Our nominal was 3.15V before, now I'm assume it should now be 6.55V (4.6V + (3.15V - 1.2V)). We will confirm this with beam scan measurements in chamber.
Ryan and I went to ZM2 PSAMS strain gauge at 6.55V and took data in 2 similar locations to in 91142. The beam size lis very similar to expected so we think ZM2 is fine, just the strain gauge now has an offset. Will look at the data in more detail tomorrow.
The data we took is attached. This plot shows the old data with SG at 3.15V in light/dark green and yesterday data at 6.55V in red/orange, It is very close. Also attached is the data taken 0.5V above and below the nominal SG values, both before when nominal was 3.15V (in blue/green colors) and now when it is 6.55V (in orange/purple/red colors). We conclude that the new nominal is << 0.5V from the old nominal. We are fine to stick with 6.55V as ZM2 PSAMS and can treat this as the old 3.15V.
Alignment sliders for the "new ZM2 position" are now P +300, Y -155.. Maybe we could do a little more fine tuning of the retrorefection and need to measure the power through the OPOS.
Ryan S, Camilla
Rahul, Sheila
We measured distances in HAM7 on the VIP. For optic names see D2000021 (A:L2 and A:L3 are actually one lens, we will call it A:L2)
Drawing showing where OPO M1 is relative to the edge of the box: D1500296 (71.949 mm-24.104 mm)/cos (12 degrees) = 48.9mm
Summarizing these measurements above in terms of the distances needed in the finesse file:
HAM1 pressure appears to be dropping now.