Displaying reports 1-20 of 88735.Go to page 1 2 3 4 5 6 7 8 9 10 End
Reports until 17:25, Monday 03 August 2026
H1 PSL
ryan.short@LIGO.ORG - posted 17:25, Monday 03 August 2026 (91377)
PSL 10-Day Trends

FAMIS 63910

Last Tuesday's interlock work and brief time in the enclosure are clearly seen on many trends, and essentially everything came back as expected. One item of note is the PMC, which relocked at a slightly higher temperature, which seems to have caused the transmitted power to be a bit lower while the reflected power is a bit higher.

Images attached to this report
H1 ISC
elenna.capote@LIGO.ORG - posted 16:58, Monday 03 August 2026 (91376)
SRY locked with different BS alignment

[Keita, Elenna]

Sheila and I struggled to lock SRY last Friday, 91360. Keita and I revisited today.

To start, I ran the usual SR2 alignment, which centers the beam on AS_C, and the AS centering which centers OM1,2 on AS A and B.

Then, we could see a large beam at the center of the AS AIR camera, and a strange fringing beam at the top edge of the camera. We swept SRM in both pitch and yaw to both edges and saw the beam disappear. This convinced us that we were seeing the two beams we needed to overlap in SRY, however, there was not an SRM alignment that could overlap the two beams.

Keita first moved ITMY 10 urad in pitch, and was able to overlap the two beams. He then undid that alignment and moved the beamsplitter instead. We were able to achieve the SRY fringing and then lock SRY with the guardian. The resulting beam ended up on the top edge of th AS AIR camera view.

Using that beamsplitter alignment, we then relocked MICH dark, which required a large movement of ITMX, since we had decided to maintain the beamsplitter and ITMY alignment. ITMX is now at P: -135 and Y: 113.1 on the sliders. This means it has been moved relative to where it should be according to a previous arm alignment we achieved.

We can still see the MICH fringes on the ISCT1 refl camera with this alignment.

We can also lock PRX, with a movement of PRM. We still see no beam on POP A or B, so Keita is scanning the input alignment.

The attached screenshot shows the alignment sliders after we locked SRY, MICH, and PRX.

I'm not sure if we are happy with this alignment overall, since we're not sure if this is where we want the ITMs.

Images attached to this report
H1 DAQ
jonathan.hanks@LIGO.ORG - posted 16:37, Monday 03 August 2026 - last comment - 16:46, Monday 03 August 2026(91374)
WP 13472 - new frame writer software on h1daqfw0 + OS upgrade

Per WP 13472  updated h1daqfw0 to use the new auto-reconfiguring frame writer.  This is the same code has been running on h1daqfw2 for months in a test mode.

I also did an inplace upgrade of h1daqfw0 to Debian 12, which is what h1daqfw2 is running and what we have tested as.

Erik helped with package wrangling for Debian 12.  I had been running h1daqfw2 from the experimental repository (which is a snapshot of the continous integration system).  We were able to move this from using the experimental repository to the unstable repository.  We will move it up to production later.  We don't have a full Debian 12 release of advligorts as we are not planning on supporting the rcg and real time code on Debian 12.

Dave and I will be watching the timings and checksums to make sure everything looks good.  The IO setup is a bit different between h1daqfw2 and h1daqfw0 (fw2 writes to local disk, fw0 to a NAS).

 

Comments related to this report
jonathan.hanks@LIGO.ORG - 16:46, Monday 03 August 2026 (91375)

As the new framewriter is a different piece of software, we track different metrics.  So we will need an updated edc capture list and a daqd restart.

A note about what this system brings in.

 * It automatically changes its configuration when there is a channel list.  It is a step towards not having daqd restarts (those don't go away while we have the daqd in other places).

 * When we restart the daqd we usually have a gap of several frames.  We hide this from the outside world by having two frame writers and only restarting one at a time.  This reconfigures the channel list and does not have gaps unless you actually restart the program.

* It is also being used in the ngdd work to write derived frame data, so that we have a common frame writer (we just change the input type).

H1 General
anthony.sanchez@LIGO.ORG - posted 16:35, Monday 03 August 2026 (91373)
Ops Monday report

TITLE: 08/03 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: CALM
    Wind: 11mph Gusts, 7mph 3min avg
    Primary useism: 0.01 μm/s
    Secondary useism: 0.07 μm/s 
QUICK SUMMARY:
The well pump was not working today due to some electrical issue. Last I heard FAC had a contractor on site to check on the well. So there is limited amounts of water here. Many folks were asked to work from home if they can. 

GRB-Short E644098 @ 17:29 UTC

Jonathan started working on the FrameWrite0 today, installing Deb12 OS. 

End stations were misaligned today to some tests that Camilla was doing.

ITMX ISI Stage 1 & 2 WD tripped twice today. Jim went out to the CER today to fix this.

Vac Team did some work on the GV6 Gate Valve today and GV6 is currently Open on the Y arm, But GV5 is still closed so the corner volume is still not open to the Arms yet. 

 

Start Time System Name Location Lazer_Haz Task Time End
15:10 FAC Kim LVEA y Technical cleaning & resupply 17:00
15:41 CDS EJ Remote N Test on OAF 15:42
15:43 FAC Tyler, Eric, & contractors EY N Working on the well 20:39
15:48 SQZ Camilla LVEA HAM5 YES Opening ViewPort on HAM5 15:55
16:10 FAC Kim Mid X N Tecnical Clkeaning & resupply 17:01
16:11 SEI Jim LVEA n working on SEI near BSC2 18:08
16:41 VAC Jordan & Travis LVEA GV6 N Working on the Gate Valve 18:39
17:20 SEI Jim remote CER N Tests on HAM2 & looking at Wiring 18:22
17:25 VAC Gerardo LVEA N Checking on GV6 work 19:25
17:45 CDS Partick MSR N CDS work? 18:06
18:39 FAC Kim HAM Shaq N technical Cleaning & Resupply 19:07
19:05 CDS Jonathon Remote N Re-imaging FW0 22:04
19:59 SEI Jim Remote N Tests on HAM3 21:25
20:03 VAC Jordan LVEA N Getting pics of GV6 20:07
20:51 VAC Travis & Gerardo End Y N Using the pump cart for Anulus work. 21:28
21:10 SQZ Camilla & Ryan S LVEA HAM7 YES Beam Profiling with M2**2 profiler. Ryan Out early 23:10
21:12 SEI Jim CER N troubleshooting ITMX ISI WD trips. 21:24
21:43 VAC Jordan LVEA GV6 N Checking on GV6 status 22:28
22:41 VAC Jordan & Gerardo LVEA GV6 N Opening GV6 00:11
22:46 SQZ Sheila LVEA HAM7 YES Working on the Power budget 00:16
H1 ISC
elenna.capote@LIGO.ORG - posted 16:15, Monday 03 August 2026 (91372)
Dark offsets run

Keita and I took an opportunity while JAC was offline to run all the dark offsets. I ran the usual dark_offsets_exe.py from userapps isc/h1/scripts/dark_offsets

I did not visually check all of them but the ones I compared before and after in SDF looked reasonable.

Some of the whitening gain settings have been set strangely for the vent, so this should help fix that now that we have reset the proper settings.

SDFed, see screenshots.

After we ran, Keita and I realized the whitening settings for POP B were still wrong, so I corrected them and reran the offset for the POP B segments. Added screenshot.

Images attached to this report
H1 SQZ
camilla.compton@LIGO.ORG - posted 15:44, Monday 03 August 2026 (91371)
SQZ OMC Scans and M^2 Measurements with new ZM4 ZM5 PSAMS Preloadings

Sheila, Ryan S, Camilla

We spent the morning repeating 90783, now that ZM4 preloading has been adjusted (90951) and ZM5 has been swapped and now has a different preloading than our O4 ZM5 (91292):

Sheila then used her script to run OMC scans at a grid (below) of PSAMS locations. These initially look great, showing sqz to omc mode mismatch is as good as 1%. with some alignment fluctuations. Ndscope of data taking attached. 

PSAM_VALUES_V5 = [-8, -5.5, -3.3, -1]
PSAM_VALUES_V4 = [-3.2, -1, 1.2, 3.4] 

Ryan then took M^2 measurements on SQZT7 of a slightly different grid:

PSAM_VALUES_V5 = [-8,  -6.75, -5.5, -4.5, -3.3, -1]
PSAM_VALUES_V4 = [-3.2, -1, 1.2, 3.4] 
Images attached to this report
H1 ISC (SUS)
elenna.capote@LIGO.ORG - posted 10:44, Monday 03 August 2026 (91368)
BBSS model with MICH ASC

Following a similar process for the length control as in 91028, I used both the BSFM and BBSS model to construct a model of the MICH ASC and check the crossover frequencies.

The most recent ASC OLG measurements of MICH P and Y are in userapps asc/h1/templates/MICH. MICH P UGF is roughly 2 Hz, MICH Y is roughly 0.7 Hz. Using the BSFM model and this information, I once again assumed the optical gain of the MICH ASC would be the same and calculated a rad/ct calibration factor to use with the BBSS model. Note that these UGFs are from full power lock, so I'm not certain what the MICH ASC OLGs look like in DRMI lock.

The BSFM model also says that both P and Y have a 22 mHz crossover between M1 and M2.

Using these calibration factors show that we might have some trouble running with the exact same MICH ASC design with BBSS. I think this is because the MICH ASC design contains a pretty extreme BSFM plant inversion. We could replace it with a BBSS inversion, or use this opportunity to move to a slightly different design principle that doesn't require precise plant inversion.

The model also suggests that the yaw crossover from M1 to M2 will be about 22 mHz as before, but shows the pitch crossover would now be 8.5 mHz. I need to confirm I am using the correct lever arms for the calibration to make sure I haven't made a mistake there. Either way, we can confirm the crossover with an injection.

Just as with length, we would need to slightly adjust the locking filter design if we want to move to M1 and M3 actuation, but in principle I don't see any issue with driving from M3 instead of M2 for ASC as well. This would be in line with how we drive all other triple sus for ASC.

First attachment shows the MICH ASC in the BSFM model, second in the BBSS model.

Images attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 10:42, Monday 03 August 2026 (91370)
Greened up h1iopomc0 timing card status on CDS Overview

Post upgrade the CDS Overview was showing an issue with h1iopomc0's timing card. On further investigation we found that this timing card is a very early rollout of the V5 firmware, upgraded back in Feb 2025 for DT-frequency changes. The actual issue is that RCG5.65 is more accurately calculating the duotone crossing for h1omc0's low-noise ADCs. This value was +0.1uS pre-upgrade and now is -5.625uS with only nano-second variation. The CDS overview was using the DT crossing time as an indicator of timing card firmware version. V3 had DTs between +7uS and +8uS, V5's are in the -1uS to +1uS range.

I've changed the CDS Overview to extend the lower limit of acceptible DT timings to -6uS. No further action is required.

H1 CAL (CAL)
rachel.langgin@LIGO.ORG - posted 10:16, Monday 03 August 2026 (91369)
O4b DARM Loop Design Comparisons and Critiques

Rachel and Elenna: 

The goal of this project is to better understand the DARM loop design that was used during O4b and evaluate how well it performed. By identifying where the design worked well and where we observe limitations, we can gain insight into potential improvements for future DARM loop designs.

To do this, I recreated the pydarm.plot.critique() function using valid O4b calibration reports (H1: 20250111T193645Z and L1: 20250102T163026Z). I then broke the DARM loop down into its individual components to understand how each stage contributes to the overall control performance.

The analysis includes comparisons of the open-loop gain (OLG, (G)), the suppression function (1/(1+G)), the digital_out_to_displacement actuation transfer functions, the lock_in_to_displacement actuation transfer functions, annotated crossover frequencies, and the frequency ranges over which each actuation stage dominates. 

Several notable differences emerge between the H1 and L1 DARM loops. H1 has a lower unity gain frequency (72.2 Hz vs. 86.0 Hz), a lower low-frequency OLG magnitude, and substantially less phase margin (22.5º vs. 34.3º). The reduced phase margin is also reflected in the larger gain peaking observed in the suppression function. Regardless of how future DARM loops are offloaded, increasing the available phase margin should be a primary design objective.

The actuator comparisons show that the overall stage hierarchy is similar between the detectors, with the UIM dominating at low frequencies before the TST becomes dominant above approximately 17 Hz. However, the lock_in_to_displacement transfer functions reveal more complicated interactions between the UIM, PUM, and TST at low frequencies than are apparent from the digital_out_to_displacement transfer functions alone.

See: LIGO-G2601606 for slides.

H1 General
anthony.sanchez@LIGO.ORG - posted 08:09, Monday 03 August 2026 (91365)
Monday Ops Morning report

TITLE: 08/03 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: CALM
    Wind: 4mph Gusts, 2mph 3min avg
    Primary useism: 0.01 μm/s
    Secondary useism: 0.09 μm/s 
QUICK SUMMARY:

IFO status: Currently Unlocked. Both GV5 and GV7 are shut..... for now.
Corner pump down continues.
Spool cameras work to reinstall IR cameras.
More Distributed acoustic  sensing DAS system.

H1 CDS
david.barker@LIGO.ORG - posted 08:12, Saturday 01 August 2026 - last comment - 09:59, Saturday 01 August 2026(91363)
no h1sush12 IPC errors since fiber/SFP swap

Following yesterday's swap of h1sush12's IPC fiber and switch-SFP (port3) 23 hours ago there have been no IPC errors from this frontend. Also the 25GE switch (sw-msr-ipc0 port3) shows zero packet errors.

Comments related to this report
david.barker@LIGO.ORG - 09:59, Saturday 01 August 2026 (91364)

h1syscsauxsdf had gotten stuck, I restarted it on h1ecatmon0.

H1 IOO
sheila.dwyer@LIGO.ORG - posted 17:36, Friday 31 July 2026 - last comment - 10:15, Monday 03 August 2026(91361)
JAC heater and HAM1 pressure

Keita turned on the JAC heater this afternoon.  Attached plot has the first cursor at the time of 91296, the second cursor at the time when Keita turned on the heater, they both happened at the same point in the diurnal pattern where the termperature rises.  

Keita has now turned the heater off before people leave for the weekend, because we can't say it's not causing the pressure to rise.  Let's repeat this earlier in the day on Monday.  

Images attached to this report
Comments related to this report
keita.kawabe@LIGO.ORG - 10:15, Monday 03 August 2026 (91366)

Actually I turned the heater back on shortly after I turned it off on Friday because the pressure rise that some were worried about looked like diurnal change to us and it was already peaking at the time.

I monitored the pressure on Friday evening and it was good, it was good on Saturday too so I kept the heater ON over the weekend. No need to turn it off from this point on.

Images attached to this comment
LHO General
thomas.shaffer@LIGO.ORG - posted 16:31, Friday 31 July 2026 (91359)
Ops Day Shift End

TITLE: 07/31 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
SHIFT SUMMARY: The final bits of the CDS upgrade continued today, as well as some SQZ and michelson commissioning. The LVEA is currently in Operations SAFE. 

The corner station continues to be pumped down, pressures are around 4e-7torr. The HAM1 pressure has been a concern when using the JAC heater this week, but I think we may have been scaring ourselves. The HAM1 pressure changes diurnally regardless of whether the heater is on or off. We have seen a pressure response from turning on the heater, but this diurnal effect might be the dominating factor. Looking at LVEA temps around HAM1 it tracks well with the local temperature. 


LOG:

Start Time System Name Location Lazer_Haz Task Time End
13:33 DAS Jenne, Wanda, Shoshana, Gizem Yarm, Xarm inside N Hitting things with hammer 17:09
16:05 CDS Jonathan MSR n Troubleshooting iopsush12 16:13
16:12 FAC Kim LVEA n Tech clean 17:13
16:21 SUS Ryan C CR (Ends) n EX & EY sus charge meas. 18:03
16:38 SQZ Sheila, Rahul LVEA LOCAL SQZ alignment with refurb ZM5 19:38
17:37 VAC Gerardo, Travis EY n BSC6 annulus work 18:25
17:39 VAC Gerardo LVEA n Grabbing lifting hardware for EY 17:49
17:57 ENG Betsy Opt Lab n Parts 18:03
18:01 SAF Ryan C LVEA N -> n Transition LVEA from Upgrade laser safe to Operations lasre safe, open light pipe 18:31
18:08 DAS Wanda EX, vertex n Looking for glasses 18:31
18:20 SQZ Daniel LVEA LOCAL Look at ZM4 electronics 18:49
19:31 FAC Randy LVEA n Measuring around BSC1 19:58
19:37 SEI Shoshana LVEA n Turning on CRS laser 19:41
20:43 VAC Gerardo, Travis LVEA n Checking on HAM2 pumps, disconnecting 20:56
20:45 SQZ Sheila, Rahul LVEA LOCAL Open HAM7 to HAM5, check alignment 21:45
20:52 CDS Dave CER, CUR n iopsush34 troubleshooting 21:50
21:34 CDS Richard CER n Checking in on iopsush34 work 21:35
Images attached to this report
H1 SQZ (SUS)
rahul.kumar@LIGO.ORG - posted 15:51, Friday 31 July 2026 - last comment - 11:43, Monday 03 August 2026(91358)
HAM7 Squeezer beam alingment work, power budget estimation and beam injected into HAM5.

Sheila, Rahul

We got back into HAM7 for beam alignment work after ZM5 was repaired and, up & running. Listed below are the things we did to check and improve the alignment in HAM7 chamber and also on the SQZT7 irises. 

1. Checked the incoming beam on ZM5 from ZM4, found it to be off in yaw by few mm - hence we translated ZM5 (pushing it in the direction towards SQZT7 table) to center the beam on the PSAMS. 

2. Checked the reflected beam from ZM5 on the iris (which Camilla had set last week) - it was off in Yaw and was too high as well. Hence, I mechanically adjusted the pitch and yawed the suspension cage to center the beam on the iris. Sheila then checked the beam on the two irises in SQZT7. Using sliders we were able to center it nicely on the two irises, however several times while doing so we were eating up on DAC output. Hence iteratively we were using sliders and mechanically offloading Pitch/Yaw by adjusting the pitch adjuster or yawing the suspension cage.

3. Sheila also used ZM4 sliders to fine tune the alignment on the irises on the table.

Current status - we have centered the beam on the two irises in SQZT7 but we might have to mechanically offload ZM5 or perhaps ZM4 as well. ZM5 has all four dog clamps attached and baffle installed as well. 

We removed the yellow viewport cover (and guillotine) from HAM5, removed the foil and opened the gate valve on HAM7 viewport (going towards HAM5) and then confirmed that the beam is injected  into HAM5.

Sheila, is fine tuning the IFO alignment before aligning the two beams (IFO and squeezer) in HAM6 photodiode.

We also did some power measurements in HAM7 chamber, mainly on the OPO and then compared it against SQZT7 table. Sheila will posting the numbers later on.

Comments related to this report
sheila.dwyer@LIGO.ORG - 17:39, Friday 31 July 2026 (91360)

Power budget:  We measured 1.35mW out of the OPO, and 1.2mW on SQZT7.  we struggled as usual with the reliablity of the power meter measurements, but it seems like the return beam through SFI1 has higher loss than it should, and there also seems to be power missing between the beam leaving the VIP and the beam arriving on SQZT7.  If we believe this measurement we have too much loss, with 12% measured loss in HAM7 where we should have 4-5%.  

I did walk the alignment of ZM1/2/3 a little bit, we could try this more to see if we can fix clipping that way. Screenshot of where I left the sliders is attached. 

Elenna and I put SR3 back to where it was in O3,  aligned SR2 to center on AS_C, and ran the AS centering + offloaded.  We then tried to align SRY, but could not get the fringes as high as they should be. We paused on SRY alignment to inject sqz into HAM6. 

The sqz beam was on the HAM6 QPDs, we ran the AS WFS to ZM4+5 loops descirbed in 90742.  This is close to saturating ZM4 + 5 but is within the range.  (We would like to increase the range on these as was done at LLO to make things easier).   

We set the OMC PZT offset to 0,  decided to scan the psams through strain gauge values of 

PSAM_VALUES_V5 = [-8, -5.5, -3.3, -1] 
PSAM_VALUES_V4 = [-3.2, -1, 1.2, 3.4] 
 
and engaged the strain gauge servos.  I did not tune the OMC ASC offsets carefully as described in 90783, perhaps that needs to be done to get a good estimation of the mode matching.  
A set of OMC scans for different psams is running now.  
Images attached to this comment
H1 CDS
david.barker@LIGO.ORG - posted 15:16, Friday 31 July 2026 (91357)
fix h1susb2h34 DAC MEDM and verify correct drive of DACs

WP13479 Move last ADC in h1susb2h34 in front of the LIGO-DACs

Erik, Jonathan, EJ, TJ, Dave:

The 3rd ADC, which was after the LIGO-DACs on the PCI bus, was moved to be before the LIGO-DACs. EJ found that if a General Standards card followed the LIGO DACs, and there are other General Standard DACs in the chassis, then the DAC mapping became ambiguous. This was first discovered by TJ when he noticed that the LIGO-DAC card temperatures was being reported as -1C (not being read). We then found that model's LIGO-DAC drive counts were being reported by h1iopsusb2h34 on the wrong DAC MEDM.

A quick fix as to move the ADC inside the IO Chassis from after to before the LIGO-DACs

The original card layout (BIO not shown):

empty empty empty ***ADC2***   LIGO-DAC1 LIGO-DAC0 20bit-DAC1 ADC1   20bit-DAC0 ADC0 empty Timing
A3-4 A3-3 A3-2 A3-1   A2-4 A2-3 A2-2 A2-1   A1-4 A1-3 A1-2 A1-1

The new card layout (BIO not shown):

empty empty LIGO_DAC1 LIGO-DAC0   empty ***ADC2*** 20bit-DAC1 ADC1   20bit-DAC0 ADC0 empty Timing
A3-4 A3-3 A3-2 A3-1   A2-4 A2-3 A2-2 A2-1   A1-4 A1-3 A1-2 A1-1

 

I was able to shuffle the cards without disconnecting any rear cables except ADC2 (SUS_HAM_209) and the MTP. The cables had enough slack to pull the chassis out to access the card screws. At the rear I was able to push the h1susauxb2h34 chassis forward to access the interface cards.

Internally only ADC2's ribbon cable needed to be disconnected.

TJ methodically started driving the top stages for MC2, PR2 and BS. We verified the model's and IOP's MEDM reported the correct channels being driven.

I trended the ADC2 channels from before and after its move to verify it is connected correctly.

LHO VE (VE)
jordan.vanosky@LIGO.ORG - posted 17:10, Wednesday 29 July 2026 - last comment - 18:37, Monday 03 August 2026(91314)
Seal Replacement on GV6 Air Cylinder

Travis, Gerardo, Jordan

During the closing of GV6 back in May, we noticed that there was some blow-by in the pneumatic system when trying to hard close the valve, see alog 90093

We were able to hard close the valve eventually but as preventative maintenance we wanted to replace the air cylinder seals, similar to GV7.

Prior to disassembly we measured the locations of the reed switches from the top surface of the bottom plate to the bottom surface of the reed switches:

Bottom Switch: 1 1/8"

Top Switch: 49 1/4"

We then disassembled the air cylinder and replaced the seals following procedure/notes collected during the GV7 repair. During cleaning of the old grease on the piston head, we noticed there were two burrs on the top of the piston, we did not notice any damage to the inside of the cylinder, but as a precaution we used a small flat file to remove the burrs. We also chased the threads on the four threaded rods with a die to aid with reinstallation. After cleaning and inspection of the cylinder tube, we found no issues or damage so we decided to continue to use that cylinder and keep the new one as a spare.

No other issues encountered, we removed the old seals, cleaned the grooves, added copious amounts of the supplied grease to the o-rings, seals and the inside of the air cylinder, and then re-assembled the cylinder tube. Pictures posted below and a final procedure is in progress and will be posted to the DCC.

We did not get a chance to cycle the valve after the seal replacement, so we will continue tomorrow with cycling the valve.

 

Images attached to this report
Comments related to this report
jordan.vanosky@LIGO.ORG - 16:04, Thursday 30 July 2026 (91333)

We were unable to fully open GV6 today after the cylinder repair. We heard the clunk of the gate camming over at 45 psi, but it did not start to raise until 55 psi, at which point we could hear air blow-by at the solenoid manifold, and up at the cylinder itself.

So we stopped trying to open the valve any further and slowly reduced the regulator output in order to bleed out the accumulated pressure on the bottom side of the piston. This lowered the gate back down and we heard the gate touch down indicating it is soft closed.

We will have to disassemble to air cylinder again and see what may be the issue. We still have 4 sets of replacement seals and one brand new air cylinder on hand if needed.

The valve remains soft closed until we are able to troubleshoot and repair the cylinder.

jordan.vanosky@LIGO.ORG - 17:45, Monday 03 August 2026 (91378)

8/3/2026

Travis, Gerardo, Jordan

Today we again disassembled the GV6 air cylinder with the valve soft closed to try and see what may have been causing the air blow-by which prevented us from fully opening the valve last week.

We did not find anything immediately obvious such as a seal that had jumped out of the groove, so we measured the ID of the original air cylinder, which was re-used, and found that it was ~0.01" larger than the ID of the spare cylinder (original ID ~8.015", spare ID ~8.005"). We then elected to use the spare cylinder instead to make sure there is good sealing contact with the cylinder wall, so we re-distributed the grease on the new cylinder and attempted to install over the piston, but the tube seemed to be slightly out of round and would not fit over the piston. So we flipped the tube 180 degrees and measured that side of the tube and found it was better. We again added grease to that side of the cylinder and installed it over the piston, ensuring the seals and wear band stayed in place, Then we re-installed the threaded rods, torqued the nuts, installed the reed switches and installed the air lines.

To verify all the new joints/connections were ok, we put ~10 psi to the top of the cylinder and then to the bottom to see if there were any leaks. There were none so we started to open the valve by increasing air pressure at the regulator, once we got to ~25 psi we could hear and feel air coming out of the bottom plate/adapter flange below the cylinder assembly, see picture below the area where air is coming out of is circled in red, at which point we stopped trying to open the valve and closed the quarter turn isolation valve to the air line.

We spoke with a GNB rep who advised we try to to open at a higher pressure and see if the bottom seals, so we then tried to open the valve again. This time we started at 20 psi and followed our normal opening procedure with the exception of increasing by 5 psi instead of 10 and waiting 3 minutes between increases. At ~35 psi, air stopped leaking out of the bottom flange, there was no air blow-by in the cylinder and we could hear the carriage starting to move. The gate fully opened at ~48 psi and Gerardo was able to take a video where you can hear the piston incrementally move up the cylinder. We increased the holding pressure to 58 psi and verified the MEDM screen showed the valve status as green.

Images attached to this comment
Displaying reports 1-20 of 88735.Go to page 1 2 3 4 5 6 7 8 9 10 End