Displaying reports 1-20 of 87662.Go to page 1 2 3 4 5 6 7 8 9 10 End
Reports until 17:41, Thursday 14 May 2026
H1 PSL (INS, IOO, ISC, PSL)
keita.kawabe@LIGO.ORG - posted 17:41, Thursday 14 May 2026 (90251)
Done with ISS array alignment, not yet ready to go laser safe due to IFO alignment mystery (Rahul, Elenna, Keita)

Good news is that we're done with the alignment of the ISS path. Pictures and details are to follow.

Then I reinstalled the last IFO REFL baffle right in front of the HAM2-HAM1 septum window. (The baffle was removed after marking the exact position using three temporary dog clamps on the ISI on day 1 because it was in the way, I was supposed to record that in alog 90158 but forgot. I'm absolutely sure that the position of the baffle was restored within 0.1mm of the original position.)

Bad news is the IFO REFL was clipped on that baffle. 00 mode flash isn't clipped that much but horizontal modes certainly are. That was not THAT surprising because the IMC alignment was/is not great (see my comment 90224). This looks to me that the uncontrolled degree of freedom of the IMC is wrong regardless of the reason why a huge alignment change had to be made to center the MC2 TRANS QPD.

Good news is the ISS path alignment is not impacted by that, at least greatly, because we made sure that the beam hit the right location of IM4 TRANS as well as ISS array QPD before we did anything in the ISS path. Note that the baffle clipping the beam is not in the ISS path.

In other words,

However, since we don't want to revisit HAM2 once we close it, I'd like to understand what's going on for the IMC/IFO alignment. 

H1 SEI
jim.warner@LIGO.ORG - posted 17:04, Thursday 14 May 2026 (90250)
CRS progress for the week

To close out the week, we got stops and shroud mounts installed on the 2 CRS today. This is as far as we can go until we can get flexures or start assembling HOQIs, so probably not much more to report until later next week. We've covered the CRS in foil to protect them, and packed up the left over hardware for these 2 sensors. 

Images attached to this report
LHO General
corey.gray@LIGO.ORG - posted 16:30, Thursday 14 May 2026 (90242)
Thurs DAY Ops Summary

TITLE: 05/14 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

Cement truck convoy day for CEBEX today.  Bigger BeamSplitter "captured" in the suspension assy & FARO-ed in the afternoon.  A couple big middle school tours.  ISS Array alignment continued.
LOG:

H1 SUS
ibrahim.abouelfettouh@LIGO.ORG - posted 15:20, Thursday 14 May 2026 (90249)
BBS01 Installed into BBSS

Ibrahim, Betsy, Oli

Today, we installed BBS01 into the BBSS successfully. 

BBS01 was on a table. BBSS was on the aluma lift. We picked BBS01 using the ERGO arm and slowly came into the optic. In this process, we:

On top of pictures below, 2 videos:

Images attached to this report
H1 CAL
michael.ross@LIGO.ORG - posted 10:58, Thursday 14 May 2026 (90246)
iNCal Low Speed Accelerometer Tests

I spun the iNCal (currently installed version) at a low speeds to see if low speed operation shows the same vibrations that high speed operation does (see 67207). Even rotating at 1 Hz shows a large increase in signal in the accelerometer (H1:PEM-EX_ACC_BSC9_ETMX_Z) around 200 Hz. 7 Hz shows an order of magnitude increase between 100-300 Hz. The 0 Hz spectrum is with the iNCal powered but a set speed of 0 Hz. 

The lesson is that the iNCal will inject broad band noise in the strain readout even at very low speed operation.

Non-image files attached to this report
H1 SUS (SUS)
ryan.crouch@LIGO.ORG - posted 10:42, Thursday 14 May 2026 (90245)
OPLEV charge measurements, ETMX, ETMY

I ran the oplev charge measurements this morning for both of the ETMs, previously checked in alog89906.

ETMY's charge remains largely unchanged, the values across the quadrants remain below 100 on all quadrants/DOF and I don't see any appreciable trends. As a reminder we switched off the HV digitally for EY.

ETMX's charge is decreasing across all quadrants/DOF after the sign flip we inposed back in April. Over the past 4 weeks the average decrease for P was ~ -14 [V], and ~ -18.25 [V] for Y. UL saw the greatest decrease, a drop of over 30 [V] for both P & Y, UR saw the smallest decrease, around ~ 5 [V] for both P & Y. The charge is now at or below 50 [V] on all quadrants/DOF except UR_P and LR_P.

Images attached to this report
LHO General
corey.gray@LIGO.ORG - posted 07:34, Thursday 14 May 2026 (90241)
Thurs DAY Ops Transition

TITLE: 05/14 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: MAINTENANCE
    Wind: 5mph Gusts, 3mph 3min avg
    Primary useism: 0.01 μm/s
    Secondary useism: 0.23 μm/s 
QUICK SUMMARY:

New ISS Array alignment will continue as well as work with the new Bigger BeamSplitter. 

No alarms overnight. Clearer & calmer weather this morning.

With the better weather, perhaps the DGR subcontractors will start pouring concrete for the CEBEX walls today (this will require the main gate to be left open for the cement trucks to roll through.  (WP# 13250)

H1 IOO (INS, IOO, ISC)
keita.kawabe@LIGO.ORG - posted 23:19, Wednesday 13 May 2026 - last comment - 11:50, Thursday 14 May 2026(90237)
Swapped the ISS array. Alignment into the new unit started. (Rahul, Elenna, Keita)

Following yesterday's alog 90219:

At this point I and Rahul checked the beam positions in HAM2. Some things to note:

We proceeded to swap the ISS array unit.

At this point we saw flashes on QPDs as well as array PDs right away. INNER as well as OUTER SUM flashes were both about 0.06 (in the old unit it was 0.03 for OUTER but INNER was much smaller).

We started trying to center the QPD using the first pico mirror. Since pico driver is temporary unavailable (IOT2L is moved away) Rahul turned the pico manually while Elena looked at the laptop screen to monitor flashes in the individual segments. We managed an OK job (arrayqpd_centered.jpg) and checked the beam spots again.

The baffle height might not be the same as the lens height and/or the ISS array input hole height, but otherwise it seems that we're shooting down the beam from the 1" lens to the ISS array. We'll check if the lens, baffle and the array are all at the same height or not, and decide how to proceed.

Images attached to this report
Non-image files attached to this report
Comments related to this report
keita.kawabe@LIGO.ORG - 23:40, Wednesday 13 May 2026 (90239)

1st: Rahul is disconnecting the QPD cable.

2nd, 3rd (photo by Betsy): Rahul in chamber (me outside).

4th: Old unit was extracted. This is S1202971.

5th: New unit (S1202965) to the left, old one to the right.

6th: Rahul after successfully connecting up the new unit in chamber.

7th (photo by Betsy): Elenna (front) is checking the QPD centering, Rahul (a shadow in the back in this photo) is manually moving the pico mirror from -Y door, and I'm somewhere inbetween just observing the two doing a good job.

Images attached to this comment
corey.gray@LIGO.ORG - 08:45, Thursday 14 May 2026 (90243)EPO

epo tagging for photos!

rahul.kumar@LIGO.ORG - 09:39, Thursday 14 May 2026 (90244)

Attaching two pictures in reference to Keita's comment above - "The beam was very high on the left hole of the two-hole baffle (Rahul has a good pic), high on the right hole (right_hole_after_new_array_QPD_centered.mp4)"

Images attached to this comment
keita.kawabe@LIGO.ORG - 11:50, Thursday 14 May 2026 (90248)

We concluded that the height of the baffle and the array unit are both correct, the beam is really too high on the 1" lens and we're shooting down from there to the QPD. (This should have been the case for a long time with the old unit. Right after the new unit was installed the beam was on QPD and the beam stayed on the QPD, the diameter of the QPD is 3mm, i.e. we haven't made any huge change on the height of the beam at the left baffle hole.)

  • Rahul found in solidworks that the design beam height for LHO is 6.132"=155.75mm.
  • Looking at the pictures we took in the chamber, the center height of the two-hole baffle is about 156mm so that's fine.
  • The height of the spacer we have, which is supposed to be D1101074 specifically made for LHO,  has 4.94"~125.5mm nominal height and our measurement shows somewhat larger than 125.5mm, excellent agreement. We didn't measure the thickness of the thin part of the array base plate (https://dcc.ligo.org/LIGO-D1300323, detailed dimensions are only available in solidworks) nor the distance from the bottom to the beam center of the elevator plate D1400140 (again only available in solidoworks) but Rahul's number makes sense, the height of the actual array unit seems to be according to the design.

With this information, what we'll do next is to gradually bring down the height of the beam on the left baffle hole using the first pico mirror, and use the second pico mirror to bring the beam back on the QPD, until the beam line into the array becomes level-ish with the ISI surface. It doesn't have to be perfect but we don't want to be this much tilted.

Images attached to this comment
H1 SEI
jim.warner@LIGO.ORG - posted 18:38, Wednesday 13 May 2026 (90238)
CRS progress today

Shoshana, Michael, Jim

Today we went into the PSL and started putting together the 2 complete CRS assemblies we have cleaned and ready to go. This went pretty smoothly and we now have to mostly done CRS, sans HOQI readout. We don't have flexures we can use, so we can't suspend or do any mechanical tuning, but proof masses are installed in the frames, mass adjustment hardware and picos are mounted. Tomorrow, we will probably look at what prep we can do on the other 2 CRS, but fasteners are still working through c&b for those, so I don't know there is much to do until those come out.

Images attached to this report
H1 SUS (EPO, SUS)
ibrahim.abouelfettouh@LIGO.ORG - posted 16:36, Wednesday 13 May 2026 (90236)
BBSS Taken out of Can and Prepped for Install

Ibrahim, Betsy, Randy

Today, we:

Particle counts were checked periodically and were under 75 consistently during acitvity

See pictures.

Images attached to this report
LHO General
corey.gray@LIGO.ORG - posted 16:30, Wednesday 13 May 2026 (90222)
Wed DAY Ops Summary

TITLE: 05/13 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

ISS PD Array and BBSS work continues.  Had a couple of big school field trip visits.

Odd weather day with fairly high winds and rain for most of the day.
LOG:

H1 COC (EPO)
ibrahim.abouelfettouh@LIGO.ORG - posted 16:29, Wednesday 13 May 2026 (90235)
BBS01: First Contact on HR Side (and flipping BBS post-gluing)

Ibrahim, Betsy, Oli

BBS01 AOSEM flag standoffs were removed, concluding gluing.

BBS01 was flipped to the HR Side via the inspection fixture.

Betsy and I then first contacted the HR Side (S1) and peeled an hour or so later.

We did not see any features or defects as we did with S2.

Images attached to this report
H1 TCS
thomas.shaffer@LIGO.ORG - posted 16:00, Wednesday 13 May 2026 (90234)
TCSY table chiller lines all replaced and tested

Camilla C, Madi S., TJ S

Just as we did with the TCSX table a few weeks ago (alog90078), we swapped all of the flex lines on the table. Most of this was done last week, but today Madi and I fisnished the last two lines today. We then used the same vacuum trick to suck water into the table lines to "test" the lines over lunch, and then plugged the table back into the full system and slowly turned on the chiller. We had one leak at the laser driver, but cutting and reseating the 1/8"OD tube seemed to fix it. 

While trying to removed the old 3/4"OD return tube from the tee, I managed to bump the iris next to the bottom periscope mirror. We'll have to recheck this when we have beam again and can some HWS tests.

The chiller is running, I'll check on things in the morning.

Images attached to this report
H1 SEI
anthony.sanchez@LIGO.ORG - posted 15:51, Wednesday 13 May 2026 (90233)
H1 ISI CPS Noise Spectra Check - Weekly

H1 ISI CPS Sensor Noise Spectra Check - Weekly FAMIS 39336

For some context, most of the Corner station is vented and the BS cartridge is not in the chamber which explains what is shown on the BS plots here..

Non-image files attached to this report
H1 IOO (INS, IOO, ISC)
keita.kawabe@LIGO.ORG - posted 10:07, Wednesday 13 May 2026 - last comment - 13:46, Wednesday 13 May 2026(90226)
ISS work restarts

Restored the alignment sliders for IM2 and IM3 back to Monday values ([IM2P, Y] =[765, -187.7], [IM3P, Y]=[-560.7, 320]).

Measured the flashes. Chose the flash that gave the MC2 trans sum maximum power, which in general agreed with IM4 trans sum max but didn't with ISS QPD nor array PD inner sum nor outer sum. 

Anyway, 

PIT and YAW numbers were after normalization divided by (seg1+2+3+4), not by SUM, so there's a small difference but that doesn't matter at this point.

IM4 TRANS and ISS QPD PIT and YAW are broadly in agreement with Jenne's alog 90206 i.e.

I haven't compared the ISS Outer SUM with March 2026 when IMC was locked with 2W. Somebody check please. We'll go into chamber and start checking the beam path.

Comments related to this report
elenna.capote@LIGO.ORG - 13:46, Wednesday 13 May 2026 (90232)

On March 11 when we locked the IMC at 2 W, the outersum was 0.062. Today, I measured the outersum flashes (relative to the dark noise) to be 0.031, with 0.18 W input. This means our alignment into the ISS has improved relative to March.

LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 08:34, Thursday 07 May 2026 - last comment - 04:03, Thursday 14 May 2026(90152)
CP1 Soft Regeneration Update

(Jordan V., Dave B., Gerardo M.)

The internal pressure to CP1 turned around overnight signaling that the process of emptying the trap is complete, now we'll continue to monitor and pump on the cryotrap volume.until good pressure is achieved.

A side note, I manually turned off the CC for PT114B last night at 9:44 pm (local time) as the pressure was rising a bit high, then turned it back on this morning at 5:33 am local time.

Attached is a snapshot of one day trend data of pressure behavior regarding the soft regeneration for CP1.

Process started here.

Images attached to this report
Non-image files attached to this report
Comments related to this report
gerardo.moreno@LIGO.ORG - 00:44, Wednesday 13 May 2026 (90220)VE

(Jordan, Travis, Gerardo)

CP1 soft regeneration update, CP1 pumpdown continues, system is currently pumped down by the SS500 cart, one turbo pump and one scroll pump.  Yesterday we visited the sensing line and we injected high purity nitrogen gas, we removed the lower sensing line near the Rosemount sensor to be able to inject the nitrogen gas, no issue introducing the gas, lower sensing line appears clear.

To be done, leak check CP1.

Attached is a plot of the pressure internal to CP1, the plot is for the total ongoing soft regeneration.

Images attached to this comment
gerardo.moreno@LIGO.ORG - 04:03, Thursday 14 May 2026 (90240)VE

(Jordan, Gerardo)

We leak checked CP1, specifically the bi-braze joints, we introduced He to both sensing lines (we disconnected the lines before the 3 way valve -X marks the spot - , this is less disruption to the shape of the metal tubing lines), we started with the bottom or low sensing line, we introduced 1 psi of flow into the line for about 35 seconds, no signal was detected by the leak detector attached to the exhaust of the turbo pump.  We did the same test with the high sensing line, no signal was detected.  Since we had the setup on hand we also decided to spray all the bellows, given that now they are free of ice, sprayed helium for about 35+ seconds, no signal was detected by the leak detector at any of the points sprayed.

During all the tests performed the He background at the leak detector was 1.0X10-10 Torr*L/Sec.

Images attached to this comment
Displaying reports 1-20 of 87662.Go to page 1 2 3 4 5 6 7 8 9 10 End