(All time in UTC)
15:28 Kiwamu asked the intent bit to be set to comissioning. Calibration works begin.
15:30 Fil to both end stations EER (end station electronics room).
15:31 IFO lock broke. ETMX switched to high voltage
15:52 Locked at NOMINAL_LOW_NOISE. Kiwamu driving ETMX.
16:09 Fil back. Going to CER.
16:12 Fil done
16:51 EX Dust alarm went off. I checked EX dust monitor but not sure what happened to its medm screen.
17:00 Rich Abbot to LVEA. Field RF measurement.
17:13 Daniel to joined Rich.
17:40 Small re-locking issue. I didn't aware of the new method of locking PRMI so I didn't . The SRM offset was high and eventually ISI tripped. Jeff Kissel took care of the ISI.
17:51 Lockloss at SWITCH_TO_QPD see alog 20988
18:05 Locked again at NOMINAL_LOW_NOISE
18:11 Rich back for now
18:15 Rich back out
18:42 Richard to MidY
19:00 Richard back
19:07 Greg updating DMT code. This requires DMT computer restart but shouldn't affect anything in the control room.
19:15 Rich out
19:20 Nutsinee begins testing ITMX L2 DAMP MODE9 and 10 violin mode damping filters
20:00 Violin mode filtes testing stopped
20:23 Richard's intern to the roof to checck on camera
20:51 Rich back to the CER
21:00 Calibration crews took down the ifo.
23:00 Handling the ifo to Travis.
While I was out on vacation, Chris and Joe cut 3 of the 25# rolls of aluminum into 10' lengths and completed installation of those to the Mid station on the upper section of the enclosure. Additionally they have cleaned and installed strips on 240 meters of enclosure north of the Mid station to date.
Today I replaced one of the condenser fan motors on the staging building chiller. As I was removing the motor and support/guard, the last of the spot welds broke. Had this happened during operation the fan would likely have fallen into the chiller causing a considerable amount of damage. I took the support to the weld shop, cleaned and re-welded it. While I had the unit disassembled, I also cleaned the coils which I would estimate were 40% blocked with debris.
WP 5466 Jonathan, Jim A script has been added to gather up medm screens and put them in a tar file for exporting. This is to support offsite viewing of medm screens for the detector. The script runs as the controls user on script0 at 1:00 AM local time each day. The frequency of this may be reduced to once per week when we enter O1.
Attached are ASD and Coherence betwix the three corner station STS2s taken at 3am local Wednesday Thursday and Friday. These three days look very similar. I installed STS2-A aka HAM2 on Tuesday. Recap:
STS2-C (HAM5) has been in place for long time. STS2-B (ITMY) is the unit returned from Stanford replacing PEM STS2 which we were using to replace our original STS2-B which is still at Quanterra for repairs. STS2-A returned from Quanterra after a couple months in their vault where they say there was no problem. The A unit spent time in the BeirGarten near the ITMy unit undergoing cable and chassis swaps, see 18354 for recap but nothing was consistent.
To me, STS2-A still looks like this unit has a problem. When I look at plots from back in May, 18354, it looks even worse now. There was better coherence in Z and X with the other units and Y was equally poor.
RobertS--do you have an opinion?
Ignore the Title stating Huddle and cables switched. Units are in home position on nominal cables.
Travis S, Darkhan
Yesterday, Aug 27, 2015, we took Pcal end-station calibration measurements at both end-stations. The measurement procedure is described in T1500063 (-v5).
The following steps from the procedure have been completed at both end-stations:
Rough numbers from MEDM screen logged into the record sheet (provided in appendix A of T1500063) suggest that RxPD and TxPD calibrations as well as optical efficiencies of Pcal beams at LHO EY did not change significantly compared to numbers from calibration on 2015-05-22, however we saw ~1 - 2 % drop in the optical efficiency of Pcal beams at LHO EX compared to measurement taken on 2015-05-20.
Calibration results will be reported after completing the last part of the calibration procedure, running Matlab scripts that acquire data and calculate responses of TxPD and RxPD:
Record sheet papershots are attached to this alog.
Jenne, Nutsinee
There was a suspecious lockloss at SWITCH_TO_QPD at 17:50 UTC. We went through lockloss plots and found ASC-MICH was unstable right before the lockloss.
J. Kissel, D. Barker Dave found that H1SUSETMY L3 LOCK L FM 2 (which has and remains OFF all throughout lock acquisition and lownoise) had been changed by Evan from compensating for the ESD driver's low pass filter (which is now done in the H1 SUS ETMY L3 ESDOUT $(QUADRANT) FM2/FM7 banks) to some other filter, and sadly did not name it so it shows up (appropriately) as "Unknown." I;m not sure what his intent was with this filter, but because is OFF all the time, I loaded the coefficients so that the model doesn't have a "modified filter coefficients" message which sets off all sorts of SysAdmin alarms. I'll find out from Evan what his intent, and probably clean it up later.
the attached files show the current status of the front end code.
ER8 Day 11. No restarts reported
(All times UTC)
Summery:
Evan and Stefan were working on recentering the AS WFS when I arrived. When they were done, Evan cleared out his changes in the SDF aside from some ASC diff that occurred from dark offset scripts. I accepted the ODC Master changes from alog 20915.
Guardian brought the IFO into a full lock really quick, Evan added some DCPD Whitening, and it has stayed in lock since.
Locking:
Itbit set at 10:48 UTC with long lock hopes.
HWS SLED IX is ON
Having the HWS SLED on should not effect the interferometer, I added this into the guardian because we don't want the SLED running indefinately, but it is easy to turn it on and forget. If the warning message is confusing we could remove it, or move it to a less obtrusive place.
Presumably this check is coming from the DIAG_MAIN node. I think the important principle for that node should be that all the diagnostic checks should be actionable, in other words someone should get out of their chair and deal with whatever the notification is to make the notification stop. If the plan is to leave the HWS SLED on, or it's not critical to shut it off, then it should be removed from DIAG_MAIN.
Maybe we can add a second DIAG node for not immediately actionalbe diagnostics, but my guess it that it will just be ignored, since by definition nothing there will be critical.
New EXCITATION_OVERVIEW screen has been created:
$USERAPPS/sys/common/medm/EXCITATION_OVERVIEW.adl
Hopefully this can help in tracking down excitations that could be preventing the system from entering READY:

The two columns show the front-end excitation monitors (FEC, left) and the ODC monitors (ODC, right).
NOTE: ONLY ODC monitors count towards OBSERVATION READY at the moment.
The FEC monitors are there for reference, and for completeness.
The EXCITATIONS box in the OBSERVATION_OVERVIEW screen now contains a link to this screen.
I updated this screen to remove the PEM_M* and ODC_MASTER checks, and added the missing CAL_EY.
Evan, Sheila
While the IFO was down for some calibration measurements, we made another attempt at phasing AS36.
We first redid the dark offsets, this was an important step. Then we locked the bright michelson with 22 Watts of input power.
We steered the beam onto each quadrant of AS_A by maximizing the DC counts, then phased 36 to minimize Q. There were several things that made this seem much more promising than any of our previous attempts to phase these WFS:
Both of these things are firsts for these WFS as far as I'm aware, so this seemed like real progress.
We started to do the same procedure for AS_B 36, but after we phased the first quadrant the phase jumped. Kiwamu was in the rack working on the calibration measurements of the DC PDs at this time and reported that he had plugged a signal into the patch panel. After this I looked at the A signals again, and they did not make sense any more. I tried repeating the procedure above for A, and found that the phases needed to minimize Q with the light maximized on each quadrant had changed by -15, -10, 0, and -20 degrees for quadrants 1,2,3,4.
It seems like we need to make a thorough check of the HAM6 racks before we continue trying to make sense of AS WFS.
Just for the record the momentarily sane phasings were:
| segment | phase (degrees) |
| 1 | -155 |
| 2 | -175 |
| 3 | -165 |
| 4 | -158 |
Stefan and I did a wiggling test of the cables in the HAM6 rack while the interferometer was locked.
We watched AS90I, AS45Q, and all the quadrants of the AS WFS (36 and 45 MHz). The only thing we saw was a 5% fluctuation in AS90I in response to the 90 MHz LO cable being wiggled. [Although once the beam diverter is closed and the AS90 signal is attenuated, the response to wiggling is much stronger—something like 20% to 40% fluctuation.]
Evan Stefan Daniel
The second EOM driver was installed in the CER using the 9MHz control and readback channels. The first attached plot shows the DAQ readback signals. Both drivers show the similar noise levels for the in-loop and out-of-loop sensors. They are also coherent with each other as well as ASC-AS_C! The in-loop noise is clearly below which would indicate that the signal is suppressed to the sensor noise. The measured out-of-loop noise level is also a factor of 4 higher than the setup in the shop.
The second plot shows the same traces but this time the ifr is feeding the EOM driver in the CER. As expected its out-of-loop noise level is now consistent with measurements in the shop and no longer coherent with the unit in the PSL.
We were starting to suspect that we are looking at down-converted out-of-band noise...
Using a network analyzer, we took the following measurements:
The first four of these are shown in the attached plot [the OCXO has been multiplied by 5 in frequency for the sake of comparison]. The message is that the 45.5 MHz in the IFO distribution system has huge, broad wings out to 2 MHz away from the carrier. These are not seen on the IFR, the harmonic generator on the bench, or the 9.1 MHz in the distribution system.
Although the EOM driver still works to suppress some of the RFAM below 50 kHz, the broad wings still contribute significantly to the rms; most of it is accumulated above 200 kHz offset from the carrier. This is shown in the second attachment.
I looked again at some rf spectra in the CER.
These peaks appear on every output of the harmonic generator, even when it is not driving any distribution amplifiers (just a network analyzer).
These peaks also appear even when the harmonic generator is driven by +12 dBm of 9.1 MHz from an IFR (not from the OCXO + distribution amplifier).
This suggests we should focus on the harmonic generator or its power supply.
This entry is meant to survey the sensing noises of the OMC DCPDs before the EOM driver swap. However, other than the 45 MHz RFAM coupling, we have no reason to expect the couplings to change dramatically after the swap.
The DCPD sum and null data (and ISS intensity noise data) were collected from an undisturbed lock stretch on 2015-07-31.
Noise terms as follows:
The downward slope in the null at high frequencies is almost certainly some imperfect inversion of the AA filter, the uncompensated premap poles, or the downsampling filter.
* What is the reasoning behind the updated suspension thermal noise plot?
* Its weird that cHard doesn't show up. At LLO, cHard is the dominant noise from 10-15 Hz. Its coupling is 10x less than dHard, but its sensing noise is a lot worse.
I remade this plot for a more recent spectrum. This includes the new EOM driver, a second stage of whitening, and dc-lowpassing on the ISS outer loop PDs.
This time I also included some displacement noises; namely, the couplings from the PRCL, MICH, and SRCL controls. Somewhat surprising is that the PRCL control noise seems to be close to the total DCPD noise from 10 to 20 Hz. [I vaguely recall that the Wipfian noise budget predicted an unexpectedly high PRCL coupling at one point, but I cannot find an alog entry supporting this.]
Here is the above plot referred to test mass displacement, along with some of our usual anticipated displacement noises. Evidently the budgeting doesn't really add up below 100 Hz, but there are still some more displacement noises that need to be added (ASC, gas, BS DAC, etc.).
Since we weren't actually in the lowest-noise quad PUM state for this measurement, the DAC noise from the PUM is higher than what is shown in the plot above.
If the updated buget (attached) is right, this means that actually there are low-frequency gains to be had from 20 to 70 Hz. There is still evidently some excess from 50 to 200 Hz.
Here is a budget for a more recent lock, with the PUM drivers in the low-noise state. The control noise couplings (PRCL, MICH, SRCL, dHard) were all remeasured for this lock configuration.
As for other ASC loops, there is some contribution from the BS loops around 30 Hz (not included in this budget). I have also looked at cHard, but I have to drive more than 100 times above the quiescient control noise in order to even begin to see anything in the DARM spectrum, so these loops do not seem to contribute in a significant way.
Also included is a plot of sensing noises (and some displacement noises from LSC) in the OMC DCPDs, along with the sum/null residual. At high frequencies, the residual seems to approach the projected 45 MHz oscillator noise (except for the high-frequency excess, which we've seen before seems to be coherent with REFL9).
Evidently there is a bit of explaining to do in the bucket...
Some corrections/modifications/additions to the above:
Of course, the budgeted noises don't at all add up from 20 Hz to 200 Hz, so we are missing something big. Next we want to look at upconversion and jitter noises, as well as control noise from other ASC loops.