Displaying reports 67761-67780 of 77136.Go to page Start 3385 3386 3387 3388 3389 3390 3391 3392 3393 End
Reports until 13:46, Thursday 30 January 2014
LHO General
patrick.thomas@LIGO.ORG - posted 13:46, Thursday 30 January 2014 - last comment - 14:03, Thursday 30 January 2014(9667)
Apollo flying crane over X arm in LVEA


			
			
Comments related to this report
patrick.thomas@LIGO.ORG - 14:03, Thursday 30 January 2014 (9668)
Done
H1 SEI
patrick.thomas@LIGO.ORG - posted 13:42, Thursday 30 January 2014 (9666)
Richard and Filiberto working near LVEA BSC chambers (WP 4417)


			
			
LHO General
patrick.thomas@LIGO.ORG - posted 13:39, Thursday 30 January 2014 (9665)
Fire Systems Maintenance to look at fire hydrant leak


			
			
LHO General
patrick.thomas@LIGO.ORG - posted 13:38, Thursday 30 January 2014 - last comment - 14:24, Thursday 30 January 2014(9664)
Jeff and Andres working near HAM4


			
			
Comments related to this report
patrick.thomas@LIGO.ORG - 14:24, Thursday 30 January 2014 (9670)
Done
LHO General
patrick.thomas@LIGO.ORG - posted 13:31, Thursday 30 January 2014 (9663)
Betsy getting box of parts from LVEA


			
			
H1 TCS
patrick.thomas@LIGO.ORG - posted 13:20, Thursday 30 January 2014 - last comment - 14:04, Thursday 30 January 2014(9662)
Aidan working on TCS in HAM4


			
			
Comments related to this report
patrick.thomas@LIGO.ORG - 14:04, Thursday 30 January 2014 (9669)
Starting work.
H1 SUS (SUS)
betsy.weaver@LIGO.ORG - posted 13:10, Thursday 30 January 2014 (9661)
SUS and more TMS Ground Checks on ETMy cartridge

This morning Filiberto, Travis and I made grounding checks of the SUS cables on the ISI.  We also check a few of the TMS cables that were easy to access near our bundle.  Coery checked some prior as well.  Long story short, we only found 1 cable route that has a ground issue and it is on a TMS segment that runs to BOSEMs.  It is the connection with the D100225-S1104782 cable in it.  This cable has been through testing, so likely we can find and remedy this ground.  Coery said he'll add it to the TMS hit-list.

H1 SUS
betsy.weaver@LIGO.ORG - posted 12:01, Thursday 30 January 2014 - last comment - 14:07, Friday 31 January 2014(9658)
Ring Heater in line of fire during welding

We've observed some burn marks on the shielding of the ETMy ring heater cables which occured sometime during the 3 prior weld sessions (May 2012, Dec 2013, Jan 2014).  The burns are on the lowest ring heater cable that laces around the test mass and makes a connection between the test mass and the PUM.  There is a burn on the right segment and the left segment.  I dug up a picture that shows that the burn on the "right" segment (as viewed from the back of the suspension) was there just after the May 2012 weld session, so that one is not new.  However the "left" cable burn is new from the Dec or Jan welding.  We did not see when this actually occured.

Filiberto tested the ring heater cable and found that all pins are operating as per spec, although he thinks pin 1 is shorting.  We are tracking down what this means (did we test it correctly, when was it last tested, is it possible that the burn is contributing to the short, even though it does not look like it is, etc.).

Comments related to this report
betsy.weaver@LIGO.ORG - 12:03, Thursday 30 January 2014 (9659)

This is the picture of the RH "right" cable taken in May 2012.

Images attached to this comment
betsy.weaver@LIGO.ORG - 12:11, Thursday 30 January 2014 (9660)

And here is the "left" RH segment burn which happened in the Dec or Jan weld.

Images attached to this comment
filiberto.clara@LIGO.ORG - 14:07, Friday 31 January 2014 (9723)
For the ring heater cable, the following pins were tested.

Pins 2,3,4, and 5 are tied together.
Pins 14,15,16, and 17 are tied together.
The resistance between these two sets is 47.5 ohms.

Pins 8,9,10, and 11 are tied together.
Pins 20, 21, 22, and 23 are tied together.
The resistance between these two sets is 45.9 ohms.

Pin 1 is tied to shield and shorted to ground.

Filiberto Clara 
H1 CDS
patrick.thomas@LIGO.ORG - posted 10:56, Thursday 30 January 2014 (9655)
h1asc model restarted


			
			
H1 IOO
paul.fulda@LIGO.ORG - posted 10:43, Thursday 30 January 2014 - last comment - 11:24, Thursday 30 January 2014(9652)
Making REFL beam size measurements on ISCT1

I'm making a measurement of the ITMX direct reflected beam size on ISCT1. PRM is misaligned, sending the beam to the parking dump for this mesurement. Please do not align PRM as this will make the REFL beam too powerful for the beam analyzer and may fry it.

Comments related to this report
paul.fulda@LIGO.ORG - 11:24, Thursday 30 January 2014 (9657)

I'm done for now making measurements with PRM misaligned. I'll realign PRM now and measure the PRM direct reflected beam

H1 CDS
patrick.thomas@LIGO.ORG - posted 10:24, Thursday 30 January 2014 (9651)
DAQ restart for h1asc model change


			
			
H1 CDS
patrick.thomas@LIGO.ORG - posted 10:23, Thursday 30 January 2014 (9650)
h1asc model restarted (WP 4415)


			
			
LHO General
patrick.thomas@LIGO.ORG - posted 10:01, Thursday 30 January 2014 (9649)
King Soft Water taking water samples


			
			
H1 PSL (PSL)
patrick.thomas@LIGO.ORG - posted 08:44, Thursday 30 January 2014 (9648)
PSL check
Output power is 29.3 W (should be around 30 W)
FRONTEND WATCH is green
HPO WATCH is red
SysStat is good

PMC has been locked 1 day, 16 hr (should be days/weeks)
Reflected power is 10.9% of transmitted power (should be <= 10%)

FSS has been locked for 10 min (should be days/weeks)
Resonant threshold is .5V (should be .9V)

ISS diffracted power is around 8.8% (should be 10%)
Last saturation event was 16 min ago (should be days/weeks)
LHO General
patrick.thomas@LIGO.ORG - posted 08:30, Thursday 30 January 2014 (9647)
Hugh, Apollo working on HAM4


			
			
H1 ISC
kiwamu.izumi@LIGO.ORG - posted 02:06, Thursday 30 January 2014 - last comment - 02:12, Thursday 30 January 2014(9644)
Infrared laser locked to X arm for studying the green beat noise

Stefan, Kiwamu

As a part of the beat noise study, we locked the main infrared laser to the X arm cavity by feeding the reflection signal back to the MC length.

Although we succeeded in locking the IR,  the beatnote tonight was not great at all. It was roughly 500 Hz / sqrtHz in a band from 1 to 900 Hz when the infrared was locked. Plus, the mode hopping was so frequent that I was not able to integrate the spectrum lower than 1 Hz.


IR locking to the X arm:

Because the green light tonight was not stable enough for us to do the CARM hand off, we instead started locking the IR to the X arm. This is the first time for us to directly lock the infrared main laser to an arm cavity without an aid of the ALS technique. We started this from estimating the PDH optical gain of REFLAIR_RF9 by simply looking at the free swinging wave form. According to Alxea's math (alog 7054), we got ~ 1.21 counts/Hz for the optical gain. Also the MC2 M3 stage was approximated to be 18.2 / f^2  Hz / counts. Using these two information, we set the LSC gain to be 0.46 as an initial guess. Note that we cranked up the whitening gain of REFLAIR9 to its maximum. The demod phase was also adjusted to maximized the PDH signal in in-phase. We then fed it back to MC2.

A good servo gain was then empirically found to be about -0.2. Even though we didn't have a transmitted DC or reflected DC signal, we could tell if we grabbed a sideband resonance or carrier resonance by looking at the size of the Q-signal. This allowed us to detemie the right control sign.

The locking procedure is as follows:

  1. Lock IMC
  2. Remove all the notches and aggressive filters in MC2 M3 ISCINF_L.
  3. Turn on only FM3 and FM6 in MC2 M3 LOCK_L to have a large phase margin from 40  to 500 Hz.
  4. Run the beatnote tracking servo using ezcaservo (see Daniel's instruction in alog 9559).
  5. Decouple the MCL at DC by enabling FM1 of LSC_MC
  6. Make sure that the input matrix is set right so that REFLAIR_RF9_I will be used.
  7. Engage the reflection PDH servo which is currently in LSC-SRCL filter. Use  FM2 FM3 and FM4 with a gain of -0.2.
  8. Once the PDH signal becomes quitter, stop the ecaservo and also cut the LSC-MC path by enabling FM7.

One major difficulty we had during the IR lock was that a mechanical resonant mode at 41 Hz (bounce? roll? of MC2) rang up so much that we could not keep locking the IR. We often let the IMC alone to allow it to settle down for a while and this helped a lot. Also Stefan could introduce the additive offset path on top of the MC length control. He had to crank up the input gain of both common mode board and IMC board to the maximum of 31 dB. It seems that we could still go higher although we didn't quantitatively evaluate it yet. This additive offset technique should serve as a good mitigation for this 41 Hz mode issue while maintaining a high control bandwidth.

The attached is a screen shot of the IR locking configuration.

 

Noise of the green beatnote was far from good:

The noise performance of the green beatnote was not great. Something must be wrong. The smallest noise floor I could get was approximately 500 Hz/sqrtHz in a band from 1 Hz to 900 Hz.  I tried not include a mode hop during the spectrum integration. Even so, as you can see in the attached spectrum, it was suspiciously  flat. I used H1:ALS-C_COMM_PLL_CTRL for measuring the beat noise. The calibration was done by injecting a known RF frequency into the PLL and measuring the ADC counts. It was measured to be 7.916 Hz/counts. Also I added a z40/p1.6 filter to cancel the VCO response.

Images attached to this report
Comments related to this report
kiwamu.izumi@LIGO.ORG - 02:12, Thursday 30 January 2014 (9645)

Additional Note:

PRM is currently in its parking position to avoid a power-recycling fringe at the reflection port.

H1 General
andres.ramirez@LIGO.ORG - posted 16:00, Wednesday 29 January 2014 - last comment - 07:52, Thursday 30 January 2014(9636)
Ops Shift Summary
8:30–9:00 Going into the LVEA to work on dust monitor – Patrick
9:01      PSL Check List done (noticed the ISS Diffracted Power was                     
          Close to 24% - It should be 5-15%)
9:00–10:30 Water Ground staff on site for water sampling – Hanford
9:27–10:03 Back in the LVEA to swap dust monitor power supply–Patrick                      
9:36-      Starting Initial Alignment of Ham 4 optical table- Hugh
9:41       PSL Check List done (noticed the ISS Diffracted Power was                       
           close to 24% - It should be 5-15%)
9:49–12:06  Working on ACB in LVEA West Bay – Mitchell/Scott
13:05-13:59 Back to work on ACB in LVEA West Bay – Mitchell/Scott
13:10-15:14 Periscope assembly on H2 PSL – Joe
13:46-14:48 Installing Tablecloth bracket on SR2 (LVEA) – Jeff B.
13:50-15:14 Joining Joe for periscope assembly on H2 PSL – Craig/Sam
15:00       Safety Meeting 
Comments related to this report
hugh.radkins@LIGO.ORG - 07:52, Thursday 30 January 2014 (9646)

Left LVEA ~1745

Displaying reports 67761-67780 of 77136.Go to page Start 3385 3386 3387 3388 3389 3390 3391 3392 3393 End