Displaying reports 69761-69780 of 77084.Go to page Start 3485 3486 3487 3488 3489 3490 3491 3492 3493 End
Reports until 00:26, Wednesday 28 August 2013
H1 ISC
corey.gray@LIGO.ORG - posted 00:26, Wednesday 28 August 2013 - last comment - 07:47, Wednesday 28 August 2013(7558)
TMS Upper Mass Attached to ISI; Telescope/Table Staged For Cleaning

(Andres, Cheryl, Corey, Jeff)

Upper Mass Clamped To ISI

This morning the Upper Mass (already under the ISI on the Genie) was raised up on to the ISI (before that happened, Vibration Absorbers were moved to their correct positions)  This was fairly straightforward.  There were a few issues with a couple of clamps.  Two clamps had to vary from the drawing (D0902163) because the ISI's Stage0 made installing the dog clamp's screws not possible.  Then one of these screws also fell into a hole of Stage0 (think it can be fetched out by removing a dog clamp and using a tool to extract the screw).  So, Upper Mass for all intents and purposes is clamped/torqued on the ISI.

Table/Telescope Staged for Cleaning & Install

Next up is rolling the "lower Assy" (i.e. Table & Telescope) under the Upper Mass and connecting Upper Mass SUS wires to the "lower mass".  Before doing this, some tooling was staged, and then the Lower Assy was set up for inspecting/blowing dust off its optics.  I have the Table/Telescope set up in the TMS Lab in such a way that it is in a dark area of the lab and it is easier to inspect the mirrors with flashlight.  I went through a first round of blowing particles off the Telescope mirrors.  I probably removed 40% of particles.  But the remaining particles were pretty pesky, and I leave that for Cheryl to work on. 

Once the optics are clean, we'll be ready to roll the Lower Assembly into the VEA (probably after lunch on Wed) & attach it to the Upper Mass.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 07:47, Wednesday 28 August 2013 (7560)

[Whoops, made this entry last night (after adding more photos to the H1 EX TMS Resource Space), and this morning noticed Cheryl's entry.  Sorry for reduncancy.  Will keep up since I've updated a few things and posted pics.]

H1 PSL
stefan.ballmer@LIGO.ORG - posted 00:06, Wednesday 28 August 2013 (7557)
New PSL FSS state code running on h1pslfss (not in svn yet)
I installed and ran the new FSS autolocker code. Changes include:

- Ability to engage the autolocker when the FSS is already locked - without killing the lock!
- Three independent delay epics records for states 1, 2 and 3. Their names and for now reasonable operating values are:
    H1:PSL-FSS_AUTOLOCK_DELAY1 = 5 sec
    H1:PSL-FSS_AUTOLOCK_DELAY2 = 1 sec
    H1:PSL-FSS_AUTOLOCK_DELAY3 = 0.1 sec
- On state 4 lock-loss, hold temperature output and try state 2 again (ramping up FSS gain)
- A switching integrator in FM1 of the TEMP_LOOP. I loaded the following filters:
    FM1: p0:z0.05 (pole at 0Hz, zero at 0.05Hz, high frequency gain of 1 - this is the switchable integrator.)
    FM2: p500:g0.01 (pole at 500Hz, low frequency gain of 0.01).
    FM10 (not used) a copy of the old lowpass (the two new filters together are equal to the old lowpass, except that we now have a true integrator instead of a pole at 0.005Hz)
  The FM1 switchable integrator is turned off in state 0 and 1 to clear the integrator history.

I didn't have a mode cleaner tonight, so we will have to check the fast-recovery feature through state 2 tomorrow.
Other than that, the system behaved as advertised.


Related items that will need to be checked in to the svn (I am holding off to test is a bit more before propagating it to LLO without warning.):
/opt/rtcds/userapps/release/psl/common/medm/PSL_FSS.adl
/opt/rtcds/userapps/release/psl/common/models/pslfss.mdl
/opt/rtcds/userapps/release/psl/common/src/fss/FSS_AUTOLOCKV2.c  (new file - already in svn)


PS: On request from Christina I left the FSS and TEMP loop off overnight - the PSL temperature is still recovering form the fan speed change.

H1 PSL
christina.bogan@LIGO.ORG - posted 21:06, Tuesday 27 August 2013 (7556)
PSL to science mode over night
The last measurements have to be done when all the fans inside the PSL are off, so I switched into science mode for the night to do the measurements tomorrow morning. Afterwards I will switch backto commisioning mode to work inside the enclosure again.
H1 PSL
stefan.ballmer@LIGO.ORG - posted 20:40, Tuesday 27 August 2013 (7555)
NPRO characterization paper
For reference, here is NPRO characterization paper from Patrick and Benno.

The laser currently installed in H1 is 1639F, i.e. "F" in the paper. 
Non-image files attached to this report
H1 AOS
cheryl.vorvick@LIGO.ORG - posted 19:24, Tuesday 27 August 2013 (7554)
TMSX upper structure attached to ISI - optics cleaning on ISC table tomorrow.
- Corey, Andres, Jeff, Cheryl

TMS Upper structure was attached to the ISI today.  Cables are routed to head toward their ISI brackets.  Jeff and Andres dressed the cables coming through the upper mass to be not touching the upper mass or rubbing against eachother.  One issue with dog clamps came up - waiting on an answer from SYS for a fix, if any change is necessary.  One wayward bolt may need to be rescued from the top of stage0, with no chance of moving on it's own.

I started cleaning optics on the ISC table, and the lights from the clean room were so strong I could not see the particulate on the optics that I easily observed before.  Possible that Corey's cleaning got a lot, but big particles on two optics that I've been tracking were still there.   Some options are to cover more lights with foil, or move the telescope down to the darker end of the room.  Doesn't look like the clean room is wired so I can turn lights off without turning the fans off, but maybe I missed something.
H1 SEI
hugh.radkins@LIGO.ORG - posted 16:17, Tuesday 27 August 2013 (7553)
WHAM6 HEPI Actuators all Attached
The amount of change sensed by the dial indicators imply that we will pass an IAS scan.  Largest changes are <0.2mm but we'll do the survey anyway.  Hopefully that will conclude tomorrow.  We'll follow that with ISI unlocking and door install.  HEPI electronics (removed for Actuator attachment) will be reinstalled and testing begun.
H1 CDS
david.barker@LIGO.ORG - posted 16:06, Tuesday 27 August 2013 (7552)
Tuesday Maintenance, upgrade front ends to RCG2.7.2

Dave and Jim,

We had compiled all models against RCG 2.7.2 yesterday. This morning we installed and restarted these models using the sequence:

The PSL models were not recompiled nor restarted, that system is in use today by the PSL and AEI teams.

The h1lsc model needed a manual press of the BURT button on the GDS_TP medm screen to get it to start.

The h1isibs and h1isiitmx models showed an INI mismatch with the DAQ. Vincent made some more BSC ISI changes. After he was done, I restarted the DAQ. About half of the front ends went into a 0x2bad DAQ error. I restarted the MX_Streams on those systems which cleared the error.

The frontends which went into the bad state were sus(2a, 34, 56, ex) susaux(b123,h2,h34,h56,ex) sei(b2,b3) lsc0, asc0, iscex (total of 14)

We expect the upgrades to have fixed the erroneous Binary IO initial state readback, and the unresponsive matrices.

The DAQ was upgraded to 2.7.1 some time ago, the front ends went to 2.7.2 today (which has the addition of the matrices fix) to essentially complete the 2.7.1 upgrade.

LHO General
dale.ingram@LIGO.ORG - posted 15:59, Tuesday 27 August 2013 (7551)
Ops Summary, 8/27/13
Vendors on site today:  Sprague (X arm), Unifirst, Basin Disposal to empty cardboard dumpster and bring it back, Mount Lock & Key, Praxair for CP3.

Dave and Jim executed the upgrade and restart of the front ends.  They didn't do the PSL.

Work permits signed by ops today:  4097 (front ends), 4099 (HAM2,5,6 camera cables), 4100 (two clean room cleanings near HAM5; completed), 4101 (SEI model update/recompile), 4102 (autolocker).

Sporadic dust alarms today in the SUS test stand (LVEA) and in the optics lab/bake oven room.

Correct PSL enclosure phone numbers: H1 -- 113 (inside), 226 (outside).  H2 -- 114 (inside), 225 (outside).

Remember that the dust monitor map that used to reside on the CR white board now sits in the wiki at https://lhocds.ligo-wa.caltech.edu/wiki/DustMonitorLocations
H1 AOS
thomas.vo@LIGO.ORG - posted 15:23, Tuesday 27 August 2013 (7549)
H1 ITMY Optica Lever test data
For Optical Lever acceptance review, this data was requested.  This set will also be included in the testing and commissioning document for optical levers, T1300563.

Figure 1 shows the dark noise spectra in Volts/Hz^1/2, this is taken as individual segments at the ADC and then converted from counts to volts in DTT.

Figure 2 shows the transfer function between the OSEMS of the M0 stage and the L2 stage, this is using an excitation on the M0 stage of 200 counts uniformly at broadband frequencies.

Figure 3 shows the ITMY drift for 24 hours in pitch and yaw in units of microradians.  We see that over the course of 24 hours, pitch drifts ~2urad and yaw drifts ~1.5urad
Non-image files attached to this report
H1 INS
jodi.fauver@LIGO.ORG - posted 15:23, Tuesday 27 August 2013 (7550)
Final iLIGO Large Optic suspensions removed from OSB Optics Lab
Mark L., Eddy and I removed four LOS from the Optics Lab today. Three were headed for recycling per Michael Landry and one was packed into a crate for shipping to Steve Penn. We put shipping requests on the iLIGO optics cases headed for CIT: this included the two ETMs destined for KAGRA per Eiichi's request. Mark and Eddy carted everything ready for shipment to the LSB so Terry can work on the logistics. There were two cases full of SOS destined for MIT: these were hauled to X Mid Optics Lab for storage until MIT is ready to receive them. 

Three iLIGO large optics remain on-site: they are stored in cake tins in an Optics Lab cupboard. We will ship these to CIT when we get some cases back.
LHO General
bubba.gateley@LIGO.ORG - posted 15:19, Tuesday 27 August 2013 (7548)
Apollo crew
We assisted Jodi with removal of suspensions from the optics lab, some for shipment and some for recycle. 
Welded the tabs for the bread board on the leaner pier at End Y for Rick S.
Tyler worked in the machine shop on parts for Betsy.
H1 SEI
vincent.lhuillier@LIGO.ORG - posted 12:45, Tuesday 27 August 2013 (7547)
ISI - HEPI models updates on BSC1,2,3

For the ISIs, I updated the common model, edited the .ini list, localy rerouted the STS-2 paths, compiled, installed and restarted the models.
For the HEPIs, I localy rerouted the STS-2 paths, compiled, installed and restarted the models.

LHO General
patrick.thomas@LIGO.ORG - posted 08:50, Tuesday 27 August 2013 (7545)
restarted and burt restored IOC for dust monitor in H1 PSL diode room


			
			
H1 PSL
christina.bogan@LIGO.ORG - posted 19:01, Monday 26 August 2013 (7544)
FSS work
[Peter, Rick, Christina]

To have a look at the AOM double pass efficiency, we checked the RF power send to the AOM. It was 1.46W, which is too high. So we changed the attenution in front of the VCO from 9dB to 10dB (using an 8dB and a 2dB attenuator). That gave us 1.2W. 

Afterwards we optimized the alignment of the AOM and got a double pass efficiency of 72% (69.5mW to AOM, 59.5mW in single pass, 50.4mW after the EOM).

Because of realigning the AOM we had to optimize the alignment of the reference cavity and got 30mW transmitting with 50mW send into the cavity.
H1 ISC
kiwamu.izumi@LIGO.ORG - posted 17:39, Monday 26 August 2013 (7543)
HIFO Y noise model moved to a new place

As a part of the HIFO wrap up, I moved all the matlab scripts and associated files for the HIFO Y noise budget from

 /opt/rtcds/userapps/release/als/h1/scripts/

to

 /ligo/svncommon/40mSVN/NB/aLIGO/HIFO/H1

They are now under the subversion control of 40m SVN and not the CDS user_apps.

H1 AOS
thomas.vo@LIGO.ORG - posted 17:23, Monday 26 August 2013 - last comment - 14:33, Tuesday 27 August 2013(7542)
TCS RH ITMX Install
GregG ThomasV BetsyW

Installed the TCS RHs onto the suspension cage, the cables are routed up the side.  Will put the final touches on the cable routing and do a continuity/resistance check tomorrow.
Images attached to this report
Comments related to this report
greg.grabeel@LIGO.ORG - 14:33, Tuesday 27 August 2013 (7546)
Thomas Vo, Greg Grabeel

We finished installing the ring heaters for ITMx with only a couple of issues. The first problem is the temperature sensor broke off at the leads. The electrical leads had epoxy encapsulating them but that epoxy broke along with the leads. Thomas and I wrapped the temperature sensor up and zip tied it to the structure.

The second issue was the nut plate designed to hold the cable bracket to the top of the quad structure was too wide and two silver plated nuts were used instead. The nut plate was running into the edge of the structure.

The resistance for the upper and lower ring heater were both 43 ohms at the J9 cable connection.
Images attached to this comment
H1 SEI
hugh.radkins@LIGO.ORG - posted 16:33, Monday 26 August 2013 (7541)
WHAM6 HEPI Actuator attachment progress
Last two Vertical Actuators attached.  Four Horizontals to go.
H1 ISC
corey.gray@LIGO.ORG - posted 16:02, Monday 26 August 2013 (7540)
H1 TMS Upper Mass Staged Under BSC9 Cartdidge

(Andres, Apollo crew, Cheryl, Corey, Jeff)

Upper Mass Rolled Out To Cartridge

Most of the day was prepping and actually moving this Assembly.  Because of the orientation and spacing out at the Test Stand, the plan is to roll the Genie with the Upper Mass back-end-first under the Cartridge.  To orient the Upper Mass on the Genie, the Upper Mass was rotated via lifting hardware at the Bosch Frame.  Then this afternoon, the Upper Mass was rolled under the Cartridge while keeping it under a clean room (this is from the TMS Lab, through receiving, cleaning room, and into the VEA under the Test Stand. 

Upper Mass Cleaned Before Roll Out

Before the big move, we performed a cleaning of the Assy.  We vacuumed & wiped with pre-soaked Alpha Wipes.

Vibration Absorber Interference

Time was running late, so we didn't attempt to clamp the Upper Mass to the ISI, but one thing we did notice was the NW Vibration Absorber on the Upper Mass Cage will interfere with the ISI's Stage-0.  We're going to talk about this with the SUS crew and see if this can be moved.

Cookie Cutter/Alignment Template (D1101050)

Not really sure where the error is on this, but to use this tool, we had to install it in a way where we did not utilize the counterbored holes (so perhaps the counterbores were cut on wrong side.  It still works, but it's just sad that there are un-used counterbores on this guy.

Images attached to this report
Displaying reports 69761-69780 of 77084.Go to page Start 3485 3486 3487 3488 3489 3490 3491 3492 3493 End