Displaying reports 69901-69920 of 77084.Go to page Start 3492 3493 3494 3495 3496 3497 3498 3499 3500 End
Reports until 15:44, Monday 12 August 2013
H1 SEI
hugh.radkins@LIGO.ORG - posted 15:44, Monday 12 August 2013 (7417)
WHAM6 SEI HEPI is now Unlocked and Floating
Nothing really sensitive on this platform at the moment but the system is floating; please be mindful of the blue crossbeams.  We'll do Optical Table positioning tomorrow if IAS is available.
LHO General
bubba.gateley@LIGO.ORG - posted 15:41, Monday 12 August 2013 (7416)
Apollo crew
Today we relocated the E-module and the newly assembled clean room skeleton, as well as other extraneous "stuff" @ end y to allow for vinyl flooring installation to proceed tomorrow. We also started removal of FFU's and lights from the clean room located at ham 4 which is approximately 50% complete. Machined some vacuum accessories for Cheryl V. 
H1 SEI
hugo.paris@LIGO.ORG - posted 10:52, Monday 12 August 2013 (7413)
HAM - IMC chambers controls turned back on

Transfer functions were runnning over the weekend on HAM2 and HAM3 ISIs (tilt decoupling frequency meausrement).

Measurements are complete. Isolation loops, and HEPI alignment offsets were turned back on.

H1 CDS
james.batch@LIGO.ORG - posted 10:04, Monday 12 August 2013 (7412)
Access to lhocds has been restored.
Found computer completely unresponsive, rebooted.  Had to manually mount /ligo file system.
H1 SEI
hugo.paris@LIGO.ORG - posted 09:43, Monday 12 August 2013 (7411)
HAM6-ISI - HEPI can be unlocked

The transfer functions measured recently on HAM6-ISI featured a discrepancy between what was seen by GS13-V2 (purple curve), and what GS13-v1 (cyan) and GS13-V3 (yellow) would see. 

Thinking GS13-V2 could be saturating, we tried taking a new set of measurements over the weekend, with lower actuation. Reducing the actuation did not change the shape of HAM6-ISI TF, as seen on the latest results.

The transfer function measured with the CPSs show a good match between the corners, and confirm the good functioning of the platform, themselves, and the actuators.
 
I extracted the GS13 responses out of the TF measured on HAM6-ISI over the weekend. GS13-V2 has its resonance pretty low (~15%, blue curve) compared to what we usually see (red curve). This is what caused the discrepancy we saw.
 
Nothing alarming though. The sensor works fine, even in the worse configuration (see spectra with ISI tilted).
 
Moreover, the symmetrization filters we apply into the readout chain are maid to account for mismatch in GS13 resonance frequency. I made a quick set of symmetrization filters. Once symmetrized the TF feature a good match between the corners (see HAM6-ISI Symmetrized TF).
 
HAM6-HEPI can be unlocked.
Images attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 12:13, Sunday 11 August 2013 (7410)
Can't access lhocds remotely today to view VE overview screen
I am on site (briefly) to verify vacuum system is Ok - it is - leaving now (1215 hrs.)
H1 AOS
cheryl.vorvick@LIGO.ORG - posted 00:01, Saturday 10 August 2013 (7409)
TMSX cable clamp removed - cables threaded through the top mass
I removed the screws and washers from the peek clamp bracket.  Washers were not reachable, but I was able to push them to a place where they dropped into a temporary foil shield I installed under the top mass.

Keita and I then removed the peek clamp and bracket by lifting it from the bottom and hooking it from the top with a dental pick.

Cable connectors were threaded from the top down, past the blade spring on the -Y side, with the orientation defined in D0901880-v5, while cables were held out of the way on the other side of the "H" slot in D1200469-v1.

Pictures:

P1030993 - peek clamp and bracket
P1030995 - bracket screw removed - loose washer remains
P1030997 - fishing for the peek bracket
P1030999 - bracket caught
P1050005 - "H" slot as seen from below before threading cables
P1050006 - "H" slot as seen from above before threading cables
P1050009 - "H" slot as seen from below after threading cables
P1050011 - "H" slot as seen from below after threading cables
P1050020 - cable connector seen from the side, as it just fits through 
                      the "H" slot around the blade spring (-Y side, left in this picture)
Images attached to this report
H1 ISC
alexan.staley@LIGO.ORG - posted 17:52, Friday 09 August 2013 (7408)
More on Noise Budgeting

(Alexa, Kiwamu)

 

I have attached the following graphs:

 

1) The most recent noise budget produced by the ALS HIFOY model

2) Plot of all the contributing sensor noise to the IR noise before applying the CARM control  (which is why we do not see a knee at high frequency when comparing to the noise budget graph)

3) Infrared Noise assuming:

S_IR  = S_sensornoise                                      for f < UGF of CARM feedback

S_IR = UGF/f * S_sensornoise                          for f>UGF of CARM feedback

Thus, we are assuming a 1/f behavior above the UGF, which should overestimate the RMS. This graph includes the current acoustic noise and that with the acoustic noise lowered by a factor of 10 predicted by Robert for the science run.

4) Plot of RMS vs UGF of CARM feedback. This graph indicates if the acousitc noise is lowered by a factor of 10 the UGF of the CARM feedback can be increased while reaminig under the noise limit of 8Hz.

Non-image files attached to this report
H1 SUS
arnaud.pele@LIGO.ORG - posted 16:58, Friday 09 August 2013 (7407)
ETMX transfer functions

Starting a new round of transfer functions on ETMX over the week end. GPS starting time = 1060127914

LHO VE
kyle.ryan@LIGO.ORG - posted 16:28, Friday 09 August 2013 (7405)
Manual CP1 level control passed to CDS PID @ 1230 hrs. local
Kyle 

Had valved-out inst. air to LLCV this morning while manually filling CP1 -> Hand over to PID control re-exposed known quirk with CP1's pneumatic actuator control box, that being a gas-column oscillation -> I adjusted (cw) the damping jet until the oscillations stopped -> Control behavior may be different as a result 

I will monitor from home
H1 General
andres.ramirez@LIGO.ORG - posted 16:00, Friday 09 August 2013 (7404)
Ops shift Summary
Work at LVEA – Richard

375 ml of distilled water added to the crystal chiller – Justin

Testing ITMx ( Spectra Test ) - Arnaud
H1 SEI
hugh.radkins@LIGO.ORG - posted 15:42, Friday 09 August 2013 (7403)
WBSC1 (ITMY) SEI HEPI Vertical L4-Cs swapped on Corners 2 & 4
We had tried some whack the Crossbeam repairs but this did not improve the response so we've exchanged:

                 C2      C4
Pulled  L41343  L41439
Install  L41451  L41333

from BSC1.
H1 SUS
arnaud.pele@LIGO.ORG - posted 12:24, Friday 09 August 2013 (7400)
ETMX Spectra

After the alignment of the ETMX, a quick spectra has been ran, to check for rubbing.

The attached pdf shows a comparison between monday's (2013-08-05, in blue) and today's (2013-08-09, in green) undamped spectra, for the main and reaction chain top mass 6 degrees of fredom. Main resonnances haven't moved since then, and thus, the quad looks to be freely suspended, without any major rubbing. 

Last nights transfer functions didn't succeed, because of a bug in the automated script. It has been fixed, and the tf will be reran over the week end.

Non-image files attached to this report
H1 CDS
cyrus.reed@LIGO.ORG - posted 12:18, Friday 09 August 2013 (7401)
Vacuum Workstation Updates
A short list of updates for the vacuum workstations:

- I have corrected the issue with some paths embedded in the local VE MEDM files that prevented some displays from working when /ligo was not mounted.  All local MEDM files should now not depend on any servers being mounted.

- DNS servers were modified to point to ns0 and ns1, which did not exist when the workstations were installed.

- I have removed hanford2 from the fstab.  It's filesystem is now sufficiently trashed enough to not be useful.  /ligo is still mounted read-only, to allow the use of Data Viewer.

- The latest OS updates were applied, and the workstations rebooted.


In addition, the control room Centos vacuum workstation has been upgraded to look like the rest of the workstations installed in the outbuildings, since the Centos box depends heavily on hanford2 and was thus not very useful anymore either.
H1 SEI
hugo.paris@LIGO.ORG - posted 10:35, Friday 09 August 2013 (7399)
HAM-ISI transition script work under Guardian Interpreter

Jamie, Hugo,

Tested the following HAM-ISI transition scripts, under the guardian interpreter:
READY      -> DAMPED
DAMPED   -> ISOLATED
ISOLATED -> DAMPED
DAMPED   -> READY

Minor adjustments appart, It was a very straightforward process, thanks to Sebastian and Charles help. 
 

HAM-ISI transition script are ready, and work under Jamie's new Guardian Interpreter yes

 

Next steps for SEI guardian:

LHO VE
richard.mccarthy@LIGO.ORG - posted 09:50, Friday 09 August 2013 - last comment - 15:19, Friday 09 August 2013(7396)
Vacuum Crate LY Fail
The VME crate for the LVEA Y arm vacuum controls failed last night.  From initial investigation it looks like the power supply died.  I have swapped out the crate with a different one and re-installed all of the cards and cables.  Cyrus assisted in getting it back up and running. See his report.
Comments related to this report
john.worden@LIGO.ORG - 09:53, Friday 09 August 2013 (7397)

Richard,

Can we get a time of the failure? That will give us a good number on the LN2 boiloff rate.

 

thanks

cyrus.reed@LIGO.ORG - 10:10, Friday 09 August 2013 (7398)
Taking advantage of the unplanned downtime, the boot parameters on this crate have been changed to boot from the new vxworks boot server, vxboot.  It booted successfully with no visible errors, so the boot server has passed another test assuming the crate continues to run with no errors.  We will start to reconfigure the remaining vacuum crates to boot from the server as time and circumstances allow.
david.barker@LIGO.ORG - 15:19, Friday 09 August 2013 (7402)

h0vely failed at 01:26 UTC Friday, 18:26 Thursday local time. I'm investigating why no emails were sent to cell phones.

The DAQ EDCU did not reconnect to this IOC, I restarted the DAQ at 11:59 this morning to force a reconnection.

LHO VE
kyle.ryan@LIGO.ORG - posted 09:03, Friday 09 August 2013 - last comment - 16:29, Friday 09 August 2013(7394)
CP1 level low after loss of CDS computer
Found CP1 level @ 23" WC = 55% full at 0830 -> Determined CP1 LLCV fully closed via removing inst. air and observing no stroke -> Begin manual filling of CP1
Comments related to this report
kyle.ryan@LIGO.ORG - 09:09, Friday 09 August 2013 (7395)
28" WC = 68% full @ 0910 
john.worden@LIGO.ORG - 16:29, Friday 09 August 2013 (7406)

Kyle reports that the boiloff rate overnight averaged ~2.8%/hour   --  40% in 14 hours.  

The liquid reservoir is not purely cylindrical so this will likely be a non linear rate.

Displaying reports 69901-69920 of 77084.Go to page Start 3492 3493 3494 3495 3496 3497 3498 3499 3500 End