Volker, Matt H, Corey, Rick S, Guido, Rodica (remote), Rich A (remote)
Quick summary of work on the ISS array this week (I will write a more detailed alog later with details on cabling, mode matching, lens/mirror/ISS array positions, what optics used, photos, etc)
The beamsplitter mount ROM RH4 on HAM2 was swapped out for one that was controllable with pico motors. The in-air cabling was hooked up to a feedthrough port and tested with a temporary setup controlling it on the in-air side. All degrees of freedom work.
Lots of work was spent getting the lenses in the correct spot so that the beam waist and position was in the correct spot, no clipping, etc. The mirror in AROM RH2 was swapped for a flat mirror and the beam is now directed onto the entrance aperture of the ISS array. The lenses were tilted off axis a little bit to make sure no back reflected beam went directly back into the system and black glass beam dumps were installed to try to catch these back reflected beams (positions guessed as we cant see the back reflected beams).
We had to move a couple dumps/baffles into slightly different positions to make things fixed and we had to alter the in-air cable dressing that was done previously as it went right where we wanted to put stuff. All cables have been redressed up to the feedthrough but NO ground loop hunting done on cables yet. SEI personnel might want to check my cable routing from feedthrough to stage zero to stage 1 on the ISI, but I am pretty confident its okay.
Next week.....trying to get the quadrant detector and photodiodes aligned
Betsy, Travis, Jason
The reaction chain TFs for ITMx failed last night. Upon running them with DTT this morning, we saw some very subtle cross coupling in the L and Yaw TFs. We went into the chamber and tightened up the mounting of the reaction chain BOSEMs which seemed a little rattly. We also attempted to relieve some of the stiffness of the reaction chain cabling which runs between the UIM and PenRe mass of the suspension. The softening of the cables seemed to improve one of the subtleties, but not the other. This is still being worked on via cable checks at the OSEMs. TBC...
Meanwhile, we installed ACB target and Jason looked at the ACB alignment. Unfortunately he found that it is ~8mm off in the lateral (!) direction. This is completely baffling (!) to us since this baffle has been mounted since the arm was used in HIFOx. Indeed, when you eye-ball the baffle to the optics it does look offset. So, I guess it is assumed we will fix this on Monday via shoving the whole baffle over (somehow while it is mounted behind the support tube).
[Sheila, Kiwamu]
This morning, we switched the simulated laser from the 532nm to 1064 nm one to make the alignment work more reliable. After that, we managed to finish all the necessary work for installing the 90/10 BS in POP. We are done.
Some pictures are available in Resourcespace (https://ligoimages.mit.edu/?c=1483).
(Installation of a 1064 nm laser)
The difficulties we had yesterday were due to the use of a green laser (see alog 12507) although green light is usually more convenient than IR since it is visible and therefore easy to handle. In addition to it, a concern we had is that insertion of the 90/10 BS in the path may further reduce the power of the green light and consequently may make it difficult for us to find the HR reflected light which had been an issue yesterday and in the past. To asses this power reduction issue, we temporarily inserted the BS to see how dim the beam would become. The BS reflected seemingly more than 50 % of the green light and therefore it was far from transparent. We decided to switch the laser to a 1064 nm one.
(Alignment work)
We changed the injection path such that the IR laser bypasses PR2 as PR2 has an extremely low transmissivity for 1064 nm. We placed the fiber launcher at the east side on the table and placed a temporary steering mirror in front of the 1st picomotorized mirror (M1). In this way, the simulated beam skipped PR2 and the 3" mirror behind PR2 and joined the real path before M1. This worked really well. We could obtain decent alignment after approximately half an hour of alignment work on the fiber launcher and temporary steering mirror. We checked the centering on the QPDs by looking at MEDM screens and confirmed that both QPD A and B were well centered.
(Insertion of BS and more alignment)
We placed the BS and its associated V-black glasses according to the drawing (D0901094). Then the misalignment caused by the insertion of the BS was compensated by steering the two picomotorized mirrors (i.e. M1 and M2) by hand. This also went very smooth. We could get back to the good alignment within half an hour or so. We checked the alignment once again with the MEDM screen and confirmed that both QPDs are well centered. To wrap up the mission, we then took out the temporary steering mirror and fiber launcher out of the HAM3 chamber. We are done.
Morning Shift 0800-1200 (Corey covering afternoon)
838 – HAM2 setup (Corey and Matt H)
849 – Thomas, Vern, Eric Gustafson doing OpLev survey in corner
station, following by end stations
902 – Aaron to EX for cable pull (with Manny)
903 – Arnaud beginning measurements at ITMX…should take half
hour
905 – Matt Heintze and Janeen walkabout in LVEA
930 – Jeff/Andres/Calum/Kate to EX for surveys in preparation
for EX vent
1035 – Thomas transitioning End-X to laser HAZARD
1038 – Jeff + Andres foiling and modifying airflows around
IMC chambers in LVEA
1051 – Jason investigating a rubbing issue on ITMX
model restarts logged for Thu 26/Jun/2014
2014_06_26 10:34 h1iopsusey
2014_06_26 10:39 h1iopseiey
2014_06_26 11:17 h1hpietmy
2014_06_26 11:17 h1isietmy
2014_06_26 11:17 h1susetmy
2014_06_26 11:17 h1sustmsy
2014_06_26 11:33 h1iopsusex
2014_06_26 11:35 h1iopseiex
2014_06_26 11:39 h1hpietmx
2014_06_26 11:39 h1isietmx
2014_06_26 11:39 h1sustmsx
2014_06_26 11:41 h1susetmx
2014_06_26 13:18 h1broadcast0
2014_06_26 13:18 h1dc0
2014_06_26 13:18 h1fw0
2014_06_26 13:18 h1fw1
2014_06_26 13:18 h1nds0
2014_06_26 13:18 h1nds1
no unexpected restarts. SWWD install at end stations with related DAQ restart.
J. Kissel, for D. Barker Here is be the timing sequence (assuming the excitation of the suspension is continuous) implemented on H1 SUS/SEI ETMY IOP Software Watchdog (SWWD) and Hardware Watchdog (HWWD): 1. T=0, SUS detects an excitation of the suspension, starts its IOP SWWD WD countdown timer. HWWD also starts its countdown. 2. T=5 mins, the SUS WD countdown expires. The IPC to the SEI IOP SWWD goes to zero. 2.1 the SEI SWWD WD countdown timer starts 2.2 the SUS SWWD DK countdown timer starts 3.0 T=9mins, the ISI and HEPI models see only one minute left on the SEI IOP WD countdown, nicely zero out the DAC drives in preparation for DACKILL 4.0 T=10mins, the SEI IOP SWWD times out and DAC KILLS the ISI and HEPI DACS 5.0 T=20mins, the SUS IOP SWWD times out and DAC KILLS the SUS DACS. Also the HWWD powers down the ISI coil driver chassis and HEPI valve driver chassis 6.0 T=40mins the HWWD opens the relay contacts disabling the SUS coil drive signals.
Yesterday, with Mark's help I took videos of a walk round at EndX and EndY at LHO. The purpose was to record where various pumps, instruments etc are located to aid Systems in updating drawings. In particular we noted the positions of the trillium seismometers, taking measurements from fixed references. Videos, stills etc are saved on the DCC at T1400438.
Summary of the problem:
We have been struggling for several months with what we believe are direct (magnetic) couplings between the BSC-ISI actuators and seismometers . We have tried to measure and subtract the main coupling (Z to RZ). We have obtained substantial improvement in the T240 response, but no improvement in the optics low frequency motion as seen by the optical levers. Our conclusion at his point are, that we need to identify and subtract the couplings in other directions and/or there is noise injection somewhere between Stage 1 and the bottom mass of the quad.
Low frequency couplings analysis:
The two BSC-ISI units locked at LHO (ITMX, ITMY) give us a great opportunity to study the low frequency direct coupling from the actuators to the sensors. This document compares transfer functions of the BSC-ISI when the two stages are floating (unlocked/free) and when the two stages are locked. We use two series of measurements performed on ITMY. The goal is to figure out whether the low frequency features in the inertial sensors response are due to motion (translation or tilt coupling) or due to direct pickup (magnetic fields).
Comments are embedded in the document.
The last slide carries the most important information.
Following up on this open issue, here is a comparison of ITMX and ITMY. Both units were locked during these measurements to identify direct couplings. The first page shows the CPS transfer functions, from the V1 actuators to all local CPS. We can see some differences between ITMX and ITMY cross couplings. The second page shows the T240 response. The results of the two units are very similar.
No change anticipated to corner station laser hazard configuration today.
Matt H/Corey - Continuing ISS prep work
HAM3 - ongoing work with 532 nm fiber-coupled laser (Kiwamu/Sheila)
ITMX - alignment looks ok...need to check Arnaud's TFs from last night
Jason may need to review ITMX alignment
EX - TCS will transition to laser hazard, finish populating the HWS section of ISCTEX and do some alignment work with the ALS laser
Richard M investigating heat concerns with racks at end stations
Follow up on note with some additional information than that posted by Justin Bergman re: talk by Calum on Contamination Control on Friday 27th June at LHO.
1) LIGO-T1400024: Airborne Particle Counters (Handheld) - General Instructions and LIGO use
Jeff has now got 3 to 4 hand-held particle counters avaailble for sign out at the contamination area (on our right as you walk down Dycem flooring towards LVEA from cleaning area). An additional 4 unit are on order (2x for hand-held use and 2x to replace broken plumbed in units.) Convert and report all numbers collected in particles per cubic foot (#/ft3), or particles per cubic meter (#/m3) of air sampled. Jeff has the hand-held particles counters set to display particles per cubic foot (#/ft3) i.e. the paticle counter is taking care of the conversion etc ... Just to be sure please include a picture (when you can) of the particle counter screen.
2) LIGO-E1400029: LIGO, Contamination Control Training Material
Level 1 and level 2 are required reading. Most if not all of you have read these at some point. While this will be compulsory for all new staff and a refresher course will be offered soon if you feel you are in need of some additional guidance now please read and review the following: -
LEVEL I General Entry Cert to access any clean room space- All workers
LIGO-E0900047: LIGO Contamination Control Plan (PAGES 1 THROUGH 27 ONLY.)
LEVEL II Chamber Entry - in chamber workers
All documents in section I above plus
LIGO-E1201035: aLIGO Chamber Entry & Exit Procedures &
LIGO-T1400024: Particle Counters - Technical Note on How to use in the field
If you wanted to check agasint what you have just read you could also have a go at our quiz, see: -
LIGO-T1400177: aLIGO Contamination Control Quiz
[Sheila, Kiwamu]
We spent some time trying to align the simulated beam to the POP QPD sled today in HAM3. Since we got confused by ghost beams for a while, we were not able to finish aligning the beam.
We are aiming to get this whole mission done by the end of tomorrow.
We have set up a fiber-coupled green laser to simulate the red POP path. The output coupler of the fiber is set up on the in-chamber table with a clean base plate underneath it to prevent from contamination. The laser is collimated with a small collimator directly attached on the coupler. The laser beam is then steered by a temporary mirror such that we can perform a fine alignment by touching this mirror. We let the beam go through the scraper baffle and PR2 and all the way to the POP sled. However, in the course of the alignment, we think we got confused by a combination of a ghost beam and extremely dim main beam reflected by a BS in front of QPD_A. This actually had been known to be an issue (see alog 5774 and alog 5924), but we simply forgot this issue and went ahead without paying much attention. We then noticed, at some point, that we had screwed up the alignment by ourself. Sad.
In the tomorrow morning, we will resume the alignment work. Once it is done, we are going to move on to installation of the 90/10 BS and subsequent alignment recovery.
I just noticed (or just realized) that the Laser Room lights were on with the Laser Area Enclosure in "Science Mode," i.e. HEPA fans off and HVAC units switched OFF. Although the lights in the room are LEDs, this is way too much heat load for the room when the HVAC units are off. In the future, we should always check the video displays in the control room to ensure that the lights are off when we are in "Science Mode" for the Laser Area Enclosure.
Particle counts taken in HAM 2 during the day
Start of the morning work day reading taken in cleanroom:
0.3um........90 counts
0.5um.....40 counts
0.7um...20 counts
1.0 um....10 counts
Remainder...zero
Start of morning work day reading taken in chamber
0.3um.....20 counts
Remainder...zero
End of morning session reading taken in chamber
0.3um...180 counts
0.5um.....100 counts
0.7um....70 counts
1.0um....40 counts
2.0um.....40 counts
5.0 um...20 counts
Start of afternoon session, readings taken in cleanroom
Everything....zero counts
Start of afternoon session reading taken in chamber
0.3um....50 counts
0.5um....10 counts
End of afternoon session, reading taken in chamber
0.3um...70 counts
0.5um....50 counts
0.7um.....30 counts
1.0um...20 counts
Remainder.....zero
J. Kissel, D. Barker In the spirit of LHO aLOG 9204, we've shaken H1 SUS ETMY using H1 HPI ETMY in order to test the sanity of thresholds set for both the IOP Software WD (IOP SWWD) and the newly implemented Hardware Watchdog (HWWD). These values are currently set at 110 [mV] output of the RMS circuit (which is identical both in the HWWD and IOP SWWD), which via this test, is determined to be roughly 10 +/- 5 [um] or [urad] peak-to-peak (as reported by ISI ST1 CPS, SUS M0 OSEMs, and SUS L3 OPLEVs). See attached overall time-series of the entire test, whose timeline is below. This mount of motion has been blessed by my spider sense of "Wow, that's a *lot* of motion; it's giving me the willies. We should cut off SEI excitation after 10-20 minutes of this." Note that, gauging by the motion of speed-dials, this amount of motion is still *less* than what occurs if, say, Betsy and Travis are mechanically aligning the suspension, so it's still a conservative threshold (because, of course, when at vacuum, and the chamber is fully isolated no such motion should ever occur). Things we've learned: - The IOP SWWD and HWWD now have their threshold set to 110 [mV], equivalent to ~10 [um] or ~10 [urad] of motion, pk to pk. - The RMS output of both the IOP SWWD and HWWD track each other quite well -- as long as the signal is above ~30 [mV] or ~3 [um] or [urad] -- only the IOP SWWD readout is more the accurate below these amplitudes. - Driving a 0.1-to-10-[Hz]-band-limited, white noise excitation at he maximum amplitude of HEPI's DACs does not trip the IOP or HW WDs. One must focus the power at a given frequency to really ring up the RMS. - The calibration from counts to mV for the HWWD RMS OUT channel -- for now, randomly stuck in H1:IOP-ISC_EY_MADC0_EPICS_CH30 -- is roughly 0.1 [mV/ct]. Why the HWWD user interface is icky, but it'll still work: - (As mentioned above) the RMS output of the HWWD does not report any change unless there is a significant amount of motion already present. - The RMS output of the HWWD is choppy -- performing a sample and hold on the RMS value, and jumps around by 10s of [ct], or a few [mV] under constant excitations. - The three HWWD analog trip flag channels -- for now, stuck in H1:IOP-ISC_EY_MADC0_EPICS_CH27 through 29 -- are railed when not tripped, and low when tripped. - The after entering value in the requested RMS voltage trip point, H1:SUS-ETMY_HWWD_RMS_REQ, the readback, H1:SUS-ETMY_HWWD_RMS_RD only returns a value *close* to what's been requested. Similarly the two readbacks, H1:SUS-ETMY_HWWD_TIME_RD and H1:SUS-ETMY_HWWD_TTF_SEI for the time until trip report values only *close* to the requested value, H1:SUS-ETMY_HWWD_TIME_REQ. There's still a significant amount of hardware that needs installing / replacing before we can hook the HWWD up to actually kill ISI coil drivers and HEPI valve drivers, but we will now propogate these thresholds and this infrastructure to the remaining QUAD suspensions over the next week or so. We will also perform a similar test on HAM chambers once they become available, to set those SUS' IOP SWWD thresholds (or at least confirm that they should be the same.) Detailed Time Line GPS Time Amplitude Notes 1087849965 100000 WN; Y, RX, RZ 1087850060 200000 WN; Y, RX, RZ 1087850199 250000 WN; Y, RX, RZ 1087850287 400000 WN; Y, RX, RZ 1087850326 HPI USER WD Trip 1087850348 start over 1087850484 300000 WN; Y, RX, RZ 1087850742 300000 WN RZ RX; 100000 ct 0.5 [Hz] Sine Y 1087850995 done 1087854054 Full bandwidth HEPI TF where WN = white noise excitation, between 0.1 and 10 [Hz], and 0.5 [Hz] Sine = single frequency sine wave at 0.5 [Hz]. As in the original test, I turned OFF all control on the ISI and SUS, and turned OFF isolation control on HEPI. When ramping up the test, I began driving HEPI without turning off the ISI -- the ISI isolation loops survived through 20000 [ct] of HEPI excitation.
Following the DACKILL naming decision yesterday, I installed the latest SWWD version of the IOP models at both end stations. The new models are: h1iopsusex, h1iopsusey, h1iopseiex and h1iopseiey. All user models were restarted as part of this install. The h1iopsusey model has test oscillators which sum with the SIDE OSEM signal. I was able to use the oscillator to test the SUS-to-SEI trip and verify SEI DACs are killed after 10 minute have elapsed. At EY I tested the system by PANIC crashing SUS which started the SEI countdown.
To support the HWWD and SWWD install/tests the DAQ was restarted. Note, the corner station IOP models were make/make-installed but not restarted today, which is why their DAQ status is now 0x2000. This will be remedied when these models are restarted at a later date.
J. Oberling, A. Pele, myself
Alignment of both M0 and R0 of ITMx have been completed, at least until someone tells us otherwise. Pitch adjusters have been locked down and all levels of OSEMs tuned to medium-fine. Stay tuned for alignment values and TF results.
Rolf, Jeff, Jim, Dave
This afternoon we tested the HWWD and new SWWD side-by-side at EY.
HWWD: the HWWD unit is connected in monitor only mode. Its front two monitor ports are cabled to the main-top OSEM satellite amps for ETMY. Its binary in and out cables are connected to ports 24-31 on the binary input and binary output chassis for ETMY. 3 of the 4 front panel BNC ports are connected to spare BNC ports on h1iscey's PEM AA chassis. The back RMS monitor BNC port is also connected to a spare BNC port on the h1iscey PEM AA chassis. We configured the system with a trip point of 110mV and a trip time of 2.0minutes.
SWWD: the h1iopsusey model was built this morning with the latest SWWD parts using RCG2.8.4. The hard-coded RMS trip point is 110mV.
h1susey: the h1susey model was modified to include a HWWD part to communicate with the unit via binary in/out. This required h1susetmy to be compiled against RCG-branch-2.8 to use the new part.
Jeff excited BSC10 at EY using the HEPI actuators. He will post the details in a separate entry. We were able to transition both the HWWD and SWWD to their count-down-to-trip state within the same second. In the attached dataviewer plot. Top Left: the analog voltage from the HWWD back RMS port (being read by h1iscey). Lower Left: is the EPICS channel from the HWWD part in the h1susey model. Top Right: F1 RMS EPICS channel from the SWWD model. Lower Right: output of the SWWD RMS port.
Within the same second, the HWWD turned on its PD front panel led and the SWWD transistioned its output from 1 (good) to 0 (bad). The HWWD RMS value was about 95 at the transition (950 on the plot but the h1iscey PEM AA chassis has an internal gain of x10).
undamped main and reaction chain measurement started at 23:40:59 UTC.
- Betsy and Travis out to LVEA for pit adjustment on ITMX
- Jeff Bartlett around HAMS 23, BSC3, Optics lab working on dust monitors
- Rick to EY for
- Jonathon and Larry to LVEA to work on GC wireless
- Kyle removing CFF blank from OMC tube
- DAQ/Framebuilder restart,
- Jeff shaking ETMY
- Rick turned off the lights and fans in the anteroom of the PSL at 4:00
- Norna, Eric, and Mark B. went to both end stations to take pictures
Joe and Andres finished adjusting QUAD08 so I started a round of TFs on both chains at 12:52. Order is undamped M0, R0, then damped M0 and R0.
First set of measurement failed. Started them again at 23:52:23 UTC.
Transfer functions ran yesterday in the staging building are showing clear sources of rubbing especially in the pitch/length/yaw degrees of freedom for the reaction chain. Main chain has large unexpected cross couplings in pitch.
Andres and Jeff realized the cover was on during that measurement, which is why results were bad. We started them again Friday overnight.
For the latest round of ISS array improvements, pico motors were added to the beamsplitter AROM4 (Fig 7 in T13000327), however it seemed to have slipped through the net which feedthrough the additional in-vacuum cables need to be attached to.
Consulting with Eddie, S at CIT he gave this initial recommendation based on what knowledge he had about available feedthroughs on the HAM2 chamber: this leave us with D1-3C2 and D3-F10 as the only viable options. We'll need 156" or a 180" cable to get from CB-6 to either D1 or D3,
With regards to the new Picomotor being installed in HAM2, the cabling is the following:
picomotor--->D1101515 (quad mighty mouse)--->CB6?--->D1101659 (seis resp cable)
However the D1101659's are only 108", and it didnt appear we had a longer cable on hand.
Thus I did a survey of the feedthroughs on HAM2 and I have marked up where there are unused ports in the attached pdf (hopefully you can understand my chicken scratch). I have not labeled which is D1, D2, etc.
There are a number of spare ones that it appears we could use, the most convenient (for a number of reasons) is the feedthrough in what I believe is the SW corner which has 2 unused ones. These are actually allocated for IO for the adaptive optics.
I requested to use the bottom one of these two unused ports (marked with a star). I have checked verbally with Guido and he was happy for us to use it, as is Hugh and Calum.
It was also suggested initially to swap out the CB6 "L" cable bracket from a 2-tier to a 3-tier. I however recommended adding an additional single cable high "L" cable bracket near the edge of the table on the western side near IM1. It is out of the way of any beams (and would be below beams anyway). This will help us use the short (108") cable we have available to go from feedthrough to this cable bracket and also trying to swap out CB6 with a 3 high cable bracket….though possible has the potential for me to bang/hit/damage something. My suggestion seems a simple and safe solution. Calum and I checked with Hugh about rebalancing and he doesn't see it as a big issue. Volker and I don't think it will be in the way of anything.
After the lenses were put into position and the AROM2 mirror placed back in position I completed the in-vacuum cabling from the feedthrough, to stage zero of the ISI, from stage zero to stage 1, to the new "L" cable bracket. Corey had already connected up the picomotor to the D1101515 cable (he told me he used the longest of the 4 cables which would be the 60" long one cable, "cable #4", connector "J5").
With the 3 spare unused cables I dressed them near the edge of the table so that the connectors were floating in free space. The location of the added "L" cable bracket and the routing/dressing of the in-vacuum cables can be seen in the photos
Now that we have the additional pico motor in chamber we now also need to think about how to hook it up/control it from the in-air side. I posed this Q to Rich A and here was his initial suggestion.
1. We can (if we are careful) use 28 AWG wire inside the vacuum system, which will free us up as far as finding the correct length (156 inches)
2. The only way we can use 28 AWG wire inside the vacuum system will be if we use less than ~50 feet of 22 AWG wire outside the vacuum system.
3. Assuming we use the one spare axis available on top of IOT2L (as provided by Picomotor Driver #3), we can stay within the 50 foot limit
4. A special cable will have to be made that goes between the RJ-9 style connector (see connector.jpg) on the one available output of the Picomotor driver and the 25 pin vacuum feedthrough.
5. The Picomotor driver front panel looks like this: (see picomotor.png)
As you can see, there are two 25 pin connectors that are normally used to drive each picomotor. In parallel with these 25 pin connectors are the individual motor connectors shown in a phone jack style connector. This is how we will pick up the one unused axis for HAM2 ISS steering.
6. The interface between the phone jack and a D-sub can be done by making a short transition cable to D-9
7. Now we just make a 9 pin to 25 pin cable. Easy.
What Rich will need is:
1. The length for the in-air cable from Picomotor controller number 3 to the proposed vacuum feedthrough
2. Account number
3. Permission and agreement from Systems and PSL
I have forwarded this request onto SYS and PSL representativies
Apologies in advance. This will contain quite a lot of detail and be quite verbose but want to get everything down whilst still fresh in my mind
We were tasked with installing new picomotors in the setup for the ISS array and also getting the mode matching correct for the ISS array.
Moving ISS Array
We were informed that the ISS array was initially installed in the incorrect location as the cookie cutter was used upside down. Thus the first thing we did was to put the cookie cutter back on (correct way up) and move the ISS array into what should be a more correct position. This moved the ISS array more towards the center of the table.
PicoMotor on mounts Swap
All that had to occur here was to swap out the fixed mount ROM RH4 (see Figure 7 of T13000327) that the beamsplitter optic site in for one that is controllable by picomotors (note AROM RH2..the last mirror before the ISS array) is already controlled by picomotors.
Before anything was swapped out, AROM RH2 was removed and the beam direction off of ROM RH4 was marked with irises (this is so that we could get the same alignment as currently there back. The base was kept in the same position and the current fixed mirror mount swapped out with one that is pico controlled. The same beam splitter optic was used. The mount was adjusted until the beam went back on the same alignment as before the swap. (One thing to note....and should be able to see on one of the pics in this log, is that the beamsplitter isnt located exactly as per its supposed location in D0901083 v12. Its about 1/2" further from ROM RH3 than design. This is no big deal other than when trying to pre plan on where clamps, etc can go). We tested that the beam from the beamsplitter heading past the ISS array has no clipping by the lid on the ISS array, and its not close to clipping.
See above in the comment section about the in-vacuum cabling of the picomotors. With the in-vacuum cable connected to the feedthrough, a temporary in-air setup was used to test that the picomotors worked. They did successfully.
Note: The Kapton "washers" have not been put in as we have only just got the Kapton sheet into clean and bake
ISS array mode matching
T1400176 gave various recommendations on how the mode matching to the ISS array could be performed. The decision made by SYS, et. al. was to use the two telescope lens solution. In particular Case 1 in Table 3, which is for the first lens after the beamsplitter to be a 2" lens of FL 343.6mm and the second lens to be a 1" lens of FL -171.9mm.
The initial position of where these lenses should go is indicated in D0901083 v12 Sheet 2. However with AROM RH2 still out (from above work) and before we put the lenses in, an iris was positioned in the beam path, and a beam scan on a rail (wiped down and wrapped in foil where appropriate) was bolted to the table (see pic beamscan) in an orientation so that the beam was centered on the beamscan as slid the beamscan back and forth along the rail. These will also act as our targets to check that we have the lenses positioned so that the beam goes through the center of the lenses.
The edge of the rail was positioned roughly in the same location as the optic in AROM RH2. This means that the focus should be roughly 16" (40cm) from the edge of this rail. So where do I get the 16" from. Well it is approximately 10" from AROM RH2 to the entrance of the ISS array, and then Ollie informed Volker that the beam travels 6" inside the ISS array (I dont know where he got the 6" from, but thats what we are going with). Also in Table 3 in T1400176 the waist is called out to be 304um, however Rick S informed Volker and I that we should be shooting for something more like 250um if we can.
The lenses were positioned roughly as per the positions indicated in D0901083 v12 Sheet 2 and it was very quickly seen that the focus position was not even close to the location wanted. After discussion with Guido M. Rodica M, it was decided that we could just slide the lens positions down stream a bit and shouldnt have to much affect. So we moved them both approximately 4" downstream (as indicated by the blue "A"s (seen in New Location for L1L2 pdf). We did notice that the beam onto the beam scan was hitting lower on the beamscan than without the lenses in but we made no attempt to fix that at the moment (more on that later).
Moving the lenses moved the waist position like we expected and so we had an initial go at taking some measurements with the beam scan. Below is the raw data:
Couple other notes:
As Volker and I were dressed up and in chamber, Rick S kindly volunteered to plot the data. The results can be seen in 1st scan horizontal.pdf and 1st scan vertical.pdf
As can be seen in these results, the waist is to small and still not in the correct location. However now that we have some results, using the jamMT program Rick had on the computer, we could use the results we have above and the lens positions to work backwards on what the incoming beam profile is actually like so that we could then alter the lens positions to get the beam size and focal position where we want. The results can be seen in jammt final solution.pdf (note the origin in the horizontal axis is where the edge of the rail is (ie the position roughly of the AROM RH2 mirror)).
The lenses were positioned in the positions as indicated by the jamMT solution and we did another beam scan measurement. Below is the results:
Couple other notes:
Again because Volker and I were in chamber, Rick S again plotted the results for us. These can be seen in 2nd scan horizontal.pdf and 2nd scan vertical.pdf
The results are pretty much bang on what we wanted. Great.
Now that the lenses positions are known we wanted to look at the beam being directed down vertically some (1-2mm) with the lenses in compared to not being in. This means that the beam is not going through the center of the lenses. However with the spacers we had available, we could not find a nice solution, short of kludging together something with washers. However Rick S suggested (and also wanted us to look at anyway) just how sensitive the telescope was if alter the picos on the beamsplitter ie do we need to tilt the mount a lot to get any change). Turns out we dont and its very sensitive so only a small amount of movement of the mirror mounts vertical position moved the beam back to the position we needed (sure this still means that the beam isnt going through the center of the lenses, but we now have the beam height as we want it). Again not a perfect solution but works with what have on hand.
We aso put in the back glass beam dumps. We had to position these by eye/guesstimation as we couldnt see the back reflected light. But we did our best to make sure they clip no beams on the table
Directing beam onto ISS array
Now that the mode matching is right, we can now direct it onto the ISS array. First off we need to swap out the curved optic that was initially in AROM RH2 for a flat mirror. The details of the mirror swapped in can be seen in optic used in AROM2 pic.
This optic had first contact painted on both sides of the mirror, but it also unfortunately in marker had the details of the optic written on the barrel (see pic writing on optic). Decided to try cleaning it off with fresh acetone and the swabs (see pic cleaning optic). The marker came off after a few swabs, and then we used 3-4 swabs on the barrel after we were confident it was clean just to be sure.
Before putting the optic into the mount the back first contact was removed (not using top gun (decision made in consultation with Calum)) and then the optic placed in the mount (see pic optic with first contact). Once mirror installed in position indicated in D0901083 v12 sheet 2 we removed the other layer of first contact.
Rick S gave us circular inserts that go into the aperture of the ISS array (I dont have a pic or a DCC number sorry) and by putting the mid size one into the aperture we were able to direct the beam (using AROM2 to adjust the beam direction and a handheld IR viewer to see whats going on) until it was centered on the hole in the insert. This should have the beam initially aligned to the ISS array as was our task :-)
We then put the SiCarbide baffle which goes in front of the ISS array (with the two holes) back into position. To enable the beam to go through the two holes we had to move the Brewster angled beam dump that is near the side of the ISS array and dumps a beam from HAM1 (I dont know its designation), closer to the edge of the table to allow the baffle we are trying to put in, in.
Everything was then dog clamped down and in-vacuum cables dressed
Pics:
Pic 7-13...are pics of the various components altered/installed so as the as built drawings can be updated
Pic 14 shows the one tiny bit of free space that is still on the table
Pic 15 shows roughly the "beams" view as going from IM1 to IM2 showing should be no clipping of this beam by black glass installed
For bookkeeping's sake, will go with the following labeling/naming of new/changed optics: