Displaying reports 75421-75440 of 76933.Go to page Start 3768 3769 3770 3771 3772 3773 3774 3775 3776 End
Reports until 16:18, Friday 14 October 2011
H2 SUS
jameson.rollins@LIGO.ORG - posted 16:18, Friday 14 October 2011 (1569)
dac missing from h2susb6 IO chassis

The h2susb6 IO chassis seems to be missing a dac (dac_4).  lspci is listing 4 dacs, but 5 are needed for controls of ETMY and TMSY.  See the SUS ETM controls wiring diagram (D1002741).  h2susetmy uses dac0, dac1, and half of dac2 for OSEM coil drive signals, h2sustmsy uses half or dac2 for it's OSEM coil drive signals, and h2susetmy uses dac4 for it's ESD drive signals.

H2 CDS
david.barker@LIGO.ORG - posted 15:55, Friday 14 October 2011 - last comment - 16:13, Friday 14 October 2011(1567)
new epics gateways installed, loop backs eliminated
The new epics gateways installed to support CA connections between CDS, H2FE and H2PSL LANs enabled an EPICS "loop back" whereby on any LAN both the local IOC and the gateway responded to connection requests. Using the "signore" server ignore argument, these loop backs should now be eliminated.
Comments related to this report
jameson.rollins@LIGO.ORG - 16:13, Friday 14 October 2011 (1568)

This solved the problem I was seeing in #1562.  Both the h2susitmy and h2susetmy models have been restarted and are running fine.

H2 SUS
betsy.weaver@LIGO.ORG - posted 21:57, Thursday 13 October 2011 - last comment - 22:07, Thursday 13 October 2011(1564)
Monolithic ITMy Installed on BSC8 ISI
(Sadecki, Bland, Buckland, Garcia)

Today we:
Attached the 4 Stay assemblies to the FMy (modification and recleaning complete), dog clamped them down and torqued the bolts to spec.
Verified magnet polarities of all magnets on ITMy.
Sorted, checked function on medm, and connected the 12 ITMy Top BOSEMs (model/code fixed).
Finished the ITMy cable routing.
Added ITMy Top Stage split lock collars.

And FINALLY,
Mated the ITMy Monolithic lower suspension to it's upper structure under the BSC8 ISI!

Attached the sleeve (with only a few bolts, because we only want the payload right now and will maybe remove it again).
Attached the LS cross braces.
Attached Vibration Absorbers (with only a few bolts as these will be removed and replaced again).

Again, the FMP tooling helped to ease the process.  The mating screws for the Lower to Upper structures  and the Sleeve are difficult to attach so we're considering looking into opening up some holes on the future units.

Full picture collection from today is on ResourceSpace:

https://ligoimages.mit.edu/?c=770

Tomorrow, the SEI crew will add ballast mass and rebalance the table.  We will then work on lacing the cables up the suspension, reconnecting the wire segment between the UIM and top mass, and freeing the masses into suspension.  Then we'll need to attach and align the BOSEMs before we can take transfer functions.  A tall order for the last day of the week.
Images attached to this report
Comments related to this report
betsy.weaver@LIGO.ORG - 22:07, Thursday 13 October 2011 (1565)
SUS-SEI cable connections at the cable brackets (ref D1101477):

D1000225 - 180" cables:

S1104876 cb3 floor2 connects to D100234 s/n  915
S1104877 cb3 floor3 connects to D100234 s/n  920
S1104875 cb3 floor4 connects to D100234 s/n 908
S1104871 cb2 floor2 connects to D1002522 s/n 912/d1002523 s/n 906
S1104874 cb2 floor3 connects to D1002522 s/n 933/d1002524 s/n 906
S1104872 cb2 floor 1 connects to D1001518 TCS Ring Heater - no serialization

ESD Cables:
D1001617-s1104939 cb4 connects to d1001472 s/n 004 
H2 FMP
jodi.fauver@LIGO.ORG - posted 20:51, Thursday 13 October 2011 (1563)
BSC-4/HAM-9 ICC
Terry and Christina got second cleaning taken care of this morning. The ICC crew removed bolts from the dome and the appropriate doors, moved the purge air from HAM-9's west door and attached it to the BSC, and started removing feedthroughs and viewports. Mark asked John to have a look at a couple of viewports that had "discoloration" on them: one turned out to be something on the glass surface that was readily removed and the other one seemed to be a spot where a laser had gone astray.

On another note, Rai and I spent some time in the optics lab looking at a couple of possible methods for documenting/quantifying particulate depletion on chamber surfaces.
H2 SUS
jameson.rollins@LIGO.ORG - posted 18:11, Thursday 13 October 2011 (1562)
h2susitmy model restarted; CA exceptions encountered

I made a couple of minor tweaks to the h2susitmy model. Most of them were entirely cosmetic, but I did change a couple of the goto/from names to be a little more generic, mostly just to make things easier when porting the model to other quad suspensions (etmy, itmx, etc.). I recompiled the model to confirm that everything was kosher, and restarted it on h2susb478. The seemed to come back up fine after the restart...

However, during the restart I received a flood of the following messages:

CA.Client.Exception...............................................
    Warning: "Identical process variable names on multiple servers"
    Context: "Channel: "H2:SUS-ITMY_R0_COILOUTF_F2_SW1R", Connecting to: 10.201.0.28:56833, Ignored: 10.201.0.180:5064errlog = 31 messages were discarded
Channel: "H2:SUS-ITMY_R0_COILOUTF_F2_Name03", Connecting to: h2susb478:56833, Ignored: 10.201.0.180:5064"
    Source File: ../cac.cpp line 1209
    Current Time: Thu Oct 13 2011 17:33:47.977845564

I'm not sure what's causing this issue, although I note that Cyrus and Jim were working on EPICS gateway stuff earlier today....  Still investigating the issue...

H2 SEI
corey.gray@LIGO.ORG - posted 16:31, Thursday 13 October 2011 (1561)
Peek Connectors Plugged In At Feedthru

Previously, we had no guidelines on how to connect our 25-pin cables (they are used for the Trilliums [D1100152] and as Extensions for the GS13s/L4Cs [D1100153]).  These cables have Peek connectors on both ends, but one end is nickel plated; we weren't aware of an orientation for these cables, so we randomly had Peek/nickel plated connectors connected at the feedthru. 

We were notified that the Peek connector must be connected at the feed-thru.  This morning (4) of our cables were flipped around for the BSC8-ISI.  BSC6-ISI is also connected correctly as well.  Attached are photos of the wrong connectors plugged in at the feed-thru and the right ones plugged in.

Images attached to this report
H2 SUS
jameson.rollins@LIGO.ORG - posted 16:09, Thursday 13 October 2011 (1560)
ETMY SUS model (h2susetmy) updated

The ETMY SUS model (h2susetmy) has been updated and brought into sync with the ITMY SUS model (h2susitmy).

This was done by taking the itmy model, modifying the cdsParameters and subsystem names appropriately, and fixing the IO wiring to match that of the SUS ETM controls wiring diagram D1002741-v3.

NOTE: the DIO stuff was not changed.  As far as I can tell from the wiring diagram the BIO wiring for ETMY is the same as that for ITMY.  However, I'm not entirely clear how the BIO interface works, so I may be misunderstanding the mapping.  I'll try to confirm and post a follow up to this log.

NOTE: the model was compiled and installed but is not currently running.

H2 SEI
corey.gray@LIGO.ORG - posted 16:08, Thursday 13 October 2011 (1558)
BSC6-ISI Cabling and Balancing

(Hugh, Jim)

Balancing The System

After the Trillium Installation, the system was balanced today, with the hopes for Vincent to have an assembly to run tests on.

More Cabling Notes

Following up on Greg's cable work, today Hugh & Jim installed the Extensions for the Actuators, GS13, and L4Cs.  From Greg's documentation, we can add these cable serial numbers:

Drawing # (D11001__) S/N (S110____) LOCATION
BSC6-ISI Extension Cable Serial Numbers
_48 4040 Corner1_Stage1_Horiz Actuator Extension
_48 4041 Corner1_Stage1_Vert Actuator Extension
_48 4040 Corner1_Stage2_Horiz Actuator Extension
_48 4039 Corner1_Stage2_Vert Actuator Extension
_53 5200 Corner1_GS13_Extension
_53 5203 Corner1_L4C_Extension
_48 4037 Corner2_Stage1_Horiz Actuator Extension
_48 4038 Corner2_Stage1_Vert Actuator Extension
_48 4034 Corner2_Stage2_Horiz Actuator Extension
_48 4036 Corner2_Stage2_Vert Actuator Extension
_53 5201 Corner2_GS13_Extension
_53 5204 Corner2_L4C_Extension
_48 4046 Corner3_Stage1_Horiz Actuator Extension
_48 4045 Corner3_Stage1_Vert Actuator Extension
_48 4043 Corner3_Stage2_Horiz Actuator Extension
_48 4044 Corner3_Stage2_Vert Actuator Extension
_53 4565 Corner3_GS13_Extension
_53 4563 Corner3_L4C_Extension

 

 

H2 SEI
corey.gray@LIGO.ORG - posted 11:53, Thursday 13 October 2011 (1550)
BSC6-ISI Trilliums Installed

(Corey, Jim, Mitch, Vincent)

Installing/Testing Trilliums

We received a crate of (4) Trilliums this morning, and we immediately installed them into the BSC6-ISI (aka Unit#2).

One of our Trilliums we ended up pulling out (s/n 03).  After it was tested, we were getting ready to bolt it to the Stage1 Floor, but the 1/4-20 bolt had issue dropping through the base flange of the Pod.  We pulled out the pod and visually observed the base flange was slightly rotated wrt the pod.  Enough so, that it was not easy to pass a 1/4" bolt through the hole.  This is when we decided to install #31 here.

All of the Trilliums were passed tests for functionality (Vincent ran 5-10min power spectra), and the pressure sensors were also looked good on all four.

H2 SUS
jeffrey.garcia@LIGO.ORG - posted 10:45, Thursday 13 October 2011 (1557)
New H2SUSITMY code running
J. Batch, J. Garcia

The new "h2susitmy" code was compiled and installed via the standard "make" and "make-install" commands on the "h2build" machine.  The FrontEnd code was then begun on the "h2susb478" machine via the 'starth2susitmy' command.  The new "h2susitmy" code corrects a Simulink diagram mislabelling.  
H2 CDS
james.batch@LIGO.ORG - posted 10:17, Thursday 13 October 2011 (1556)
Epics Gateways started
Two additional EPICS gateways were started this morning to support the PSL network:

server   client
================
 cds      h2psl
h2fe      h2psl

This adds to the existing gateways

server   client
===============
 cds      h2fe
h2psl     h2fe  (started Oct. 11)

Linux and Mac workstations have had their login scripts changed to set the EPICS_CA_ADDR_LIST environment variable dynamically according to which network the workstation is connected.
H2 SUS
jameson.rollins@LIGO.ORG - posted 00:04, Thursday 13 October 2011 - last comment - 09:05, Thursday 13 October 2011(1554)
ITMY SUS ADC0 -> R0 wiring fixed (hopefully) in h2susitmy

I found what appeared to be some miswiring of a couple of channels from ADC0 to the R0 OSEM inputs to the ITMY QUAD_MASTER block in the h2susitmy model.  I found:

ADC0_18 -> R0_OSEM_F1
ADC0_19 -> R0_OSEM_F2
ADC0_20 -> R0_OSEM_F3
ADC0_22 -> R0_OSEM_LF
ADC0_23 -> R0_OSEM_RT
ADC0_21 -> R0_OSEM_SD

However, according to D1001725-v7 the wiring should be:

ADC0_20 -> R0_OSEM_F1
ADC0_21 -> R0_OSEM_F2
ADC0_22 -> R0_OSEM_F3
ADC0_18 -> R0_OSEM_LF
ADC0_19 -> R0_OSEM_RT
ADC0_23 -> R0_OSEM_SD

I didn't find anything in the aLOG or svn log to indicate that the wiring should be any different than what's in the wiring document linked above, so I went ahead and fixed the model and committed the change (r1230).

NOTE: I DID NOT REBUILD/INSTALL/RESTART THE MODEL.

Comments related to this report
jeffrey.garcia@LIGO.ORG - 09:05, Thursday 13 October 2011 (1555)
I had made some reordering changes to the "h2susitmy.mdl" to fix the older (committed) version according to the new D1001725-v7 document.  The changes I made were the same as mentioned above, but I did not commit the changes to the SVN because the Simulink diagram added a vertical line across the wiring coming from the ADC selector to the ADC inputs after I made the changes.  I wanted to confirm changes and resolve this issue before compiling/rebuilding/reinstalling.  A back-up of the earlier model before I made changes is in: '/ligo/svncommon/SusSVN/sus/trunk/QUAD/H2/ITMY/h2susitmy_111012_before_jeffg_changes.mdl'
H2 FMP
jodi.fauver@LIGO.ORG - posted 18:22, Wednesday 12 October 2011 (1553)
BSC-4/HAM-9 ICC
Cleanrooms were moved into place today: 1 over the BSC, 1 over the HAM, 1 for the dome, 1 for garbing/staging, and 1 for wrap-bag-tag of viewports and feedthroughs. (So, this time around we'll be a FIVE-RING circus!) Many other items were staged in preparation for door/dome and table removal on Friday. First cleaning was done this afternoon.
H2 SUS
betsy.weaver@LIGO.ORG - posted 17:39, Wednesday 12 October 2011 (1552)
ITMy monolithic work
The Main and Reaction Lower suspensions were married up and placed on the FMP lifting equipment today in prep for the move back to the QUAD Upper Structure on the ISI.  We stalled on this a bit because the original marriage bolts didn't work with the newly fit Fiber Guards.  Will need to update this in the QUAD model!

We also started to map out the QUAD Top BOSEMs since we were hoping to get those roughly in place prior to reattaching the monolithic underneath.  However, the cable signals were not mapping to what we expected (see Garcia's alog coming...), so we aborted to go sort out code/model issues.
H2 SUS
betsy.weaver@LIGO.ORG - posted 17:28, Wednesday 12 October 2011 (1551)
BSC8 FMy Structure Stay Issue Resolved
Yesterday, we ran into issues with 2 of the 4 FMy Structure Stays for BSC8, namely that they were too long and could not mate correctly.  With a Worden-waiver we cut down the tips of the D090002 pins by 1/4".  They were wrapped in foil and ameristat with only the tip exposed during the modification, then they were recleaned and are in an airbake oven for 24 hours.  The other 2 Stays were fit checked and mate properly.  Kurt from CIT is visiting and found the problem in the SW model, so is updating drawings for the future units not yet procured.
H2 SUS
jameson.rollins@LIGO.ORG - posted 18:19, Tuesday 11 October 2011 - last comment - 13:06, Wednesday 12 October 2011(1541)
Wiring fixed in h2susauxb478 model.

For whatever reason (likely due to a change in the wiring, or just to the trickyness of the wiring to the front end) there were a couple of wiring mistakes in the h2susauxb478 model.  I consulted H2 aLIGO BS, ITM and FM Suspensions Controls Wiring (D1001725) and was able to clean it up as best as I could.  The model was then recompiled, installed, and restarted on h2susauxb478.

Comments related to this report
jameson.rollins@LIGO.ORG - 13:06, Wednesday 12 October 2011 (1549)

So it turns out that the wiring change was due to a reconfiguration of the cable layout to the QUAD M0 and R0 stages, as specified in #1508 and #1513.  The wiring diagram in v7 of D1001725-v7 reflects the proper changes, and this is what the SUSAUX models were brought into line with, so all is good.

H2 SUS
robert.lane@LIGO.ORG - posted 16:19, Thursday 23 June 2011 - last comment - 12:26, Thursday 13 October 2011(972)
ITMY OSEM Coil Resistances, LED Voltages, PD Voltages
R. Lane, A. Ramirez

Testing ITMY (QUAD 2)
Took the Top Mass OSEM Coil Resistances, Photo Diode Voltages, and LED Voltages today. Took measurements at the connection between the octopus cables (D1000234) and the top mass extension cable. The OSEMS meet the requirements.*

Coil Resistances: 39±1Ω
PD Voltages: 1.01±0.05V
LED Voltages: 0.53±0.05V

	Main Chain
OSEM	S/N	Cable	Coil(Ω)	LED(V)	PD(V)
Face 1	481	695	36.3    1.017	0.554
Face 2	638	695	36.0    1.018	0.551
Face 3	501	695	36.4    1.018	0.558
Left	496	695	36.0    1.017	0.551
Right	499	698	36.5    1.018	0.558
Side	445	698	36.7    1.017	0.558

Reaction Chain
OSEM	S/N	Cable	Coil(Ω)	LED(V)	PD(V)
Face 1  471	698	35.9	1.018	0.553
Face 2  484	698	36.4	1.018	0.554
Face 3  472	707	36.9	1.016	0.554
Left    630	707	36.8	1.017	0.562
Right   466	707	36.7	1.019	0.558
Side    415	707	36.0	1.018	0.559

*The requirement for the coil resistance to be 39±1Ω was defined at LLO using "extra long" non final cables. This requirement is not sufficient to determine if the resistance is within standard. I will inquire with the correct authorities to determine what the new value should be for the in-vacuum final cables. However, they do meet the tolerance of ±1Ω. We took the measurement at the octopus cable, not at the vacuum feed through simulator as specified. We did not have the cables available. Although this should not add more than a few tenths of an ohm to the final resistance and would not make up the difference. 
Comments related to this report
betsy.weaver@LIGO.ORG - 12:26, Thursday 13 October 2011 (1559)
The "M0 F2" OSEM now has a S/N 261.  This is the current list on the H2 ITMY QUAD in the LVEA.
Displaying reports 75421-75440 of 76933.Go to page Start 3768 3769 3770 3771 3772 3773 3774 3775 3776 End