A trial transfer function measurement on the H2 FMY M1 today resulted in a stalled Matlab script when attempting to retrieve data. The issue was tracked down to a modified "H2SUSFMY.ini" file that had all but two channels in the "acquire=0" state. This is possibly due to the new FMY model installed last week with the RCG auto-generating a new .ini file. The .ini file was edited to acquire the needed channels, and the trial measurement ran smoothly thereafter.
Today, after rechecking the lock-down of all of the masses, and checking over the fiber guard once more, Travis and I moved the ITMy Main Chain (monolithic) into the split tooling cradle where the lower chains were to be mated back up. In order to do this we had to remove the First Contact (FC) from the CP HR and ITMy AR surfaces. We blew the surfaces with the deionizing gun (N2) as per the removal procedure. I wiped the CP outer edges of the gold coating in a few spots where it didn't look like the FC was fully removed. The ITM AR surface looked good, with the exception of the outer edge 1 cm in from the bevel where the FC was not covering for the last few months. There was some minor particulate there, it would not blow away with the gun, and I did not want to do more FC application/removal that close to the edge, so we opted to leave it. When we attempted to marry the chains, we discovered that the fiber guard blocks access fro the 2" screws which bolt the chains together. So, we stopped will bring shorter screws in tomorrow to see if they work.
Over the last day or two we have continued to add SUS payload to the BSC8 ISI: Cabling - We have spent a bit more time than I anticipated routing the 27 SUS cable strands up (and down) the ITMy and FMy suspensions, and the 7 SEI/SUS handoff cables across the optical table and out to the ISI stacks. Cable brackets CB1, 2, 3, and 4 are mounted along with a handful of PEEK D1000600 cable clamps. (4) Vibration Absorbers and (6) Sheer Plate Dampers were attached to the FMy. Stays - After getting them hot out of the oven today, we made an attempt to attach them to the FMy. Unfortunately, the overall length of the stay is too long to mate up to the suspension structure properly. Fortunately, Kurt will be on site tomorrow and can help us sort out exactly what part has the problem and work out triage for the stays needed on this suspension now.
Attached are plots of dust counts > .5 microns.
For whatever reason (likely due to a change in the wiring, or just to the trickyness of the wiring to the front end) there were a couple of wiring mistakes in the h2susauxb478 model. I consulted H2 aLIGO BS, ITM and FM Suspensions Controls Wiring (D1001725) and was able to clean it up as best as I could. The model was then recompiled, installed, and restarted on h2susauxb478.
So it turns out that the wiring change was due to a reconfiguration of the cable layout to the QUAD M0 and R0 stages, as specified in #1508 and #1513. The wiring diagram in v7 of D1001725-v7 reflects the proper changes, and this is what the SUSAUX models were brought into line with, so all is good.
Model and corresponding screens for h2susauxb6 are now in place. These include SUS_AUX channels for ETMY and TMSY. The model is:
/opt/rtcds/lho/h2/userapps/release/sus/h2/models/h2susauxb6.mdl
and is based on the H2 aLIGO SUS ETMX Controls Wiring (D1002741). The model is now running on the h2susauxb6 front-end machine.
The corresponding overview screen (linked from the EY/SUS menu in the sitemap) is:
/opt/rtcds/lho/h2/userapps/release/sus/common/medm/SUS_AUX_EY_OVERVIEW.adl
which includes links to the following:
/opt/rtcds/lho/h2/userapps/release/sus/common/medm/quad/SUS_AUX_QUAD_OVERVIEW.adl
/opt/rtcds/lho/h2/userapps/release/sus/common/medm/tmts/SUS_AUX_TMTS_OVERVIEW.adl
SUS_AUX_TMTS_OVERVIEW is also a new screen for the TMTS sus aux channels. These all use the appropriate macro expansions.
These new parts replace the deprecated QUAD_AUX_OSEM_*_MONITOR parts, which have now been removed from the userapps repo.
ICC in HAM-10 is complete. Wipe down, second vacuum, inspection, and sampling were all finished before lunch. The tube blank and the door were replaced after lunch. FTIRs will be sent off tomorrow. Work permits were pulled, signed, and filed for ICC at HAM-9/BSC-4. We'll start staging there tomorrow.
BSC 6 cabling is now ready for the new trilliums to be installed. Corners 1-3 have also gone through their preliminary cable routing. Corner 1 S/N Trillium S1105196 L4C S1104253 GS-13 S1104118 Course Vertical Actuator S1104612 Course Horizontal Actuator S1104614 Fine Vertical Actuator S1104089 Fine Horizontal Actuator S1104088 Corner 2 S/N Trillium S1105197 L4C S1104254 GS-13 S1104117 Course Vertical Actuator S1104613 Course Horizontal Actuator S1105183 Fine Vertical Actuator S1104090 Fine Horizontal Actuator S1104091 Corner 3 S/N Trillium S1105195 L4C S1104255 GS-13 S1104199 Course Vertical Actuator S1105184 Course Horizontal Actuator S1105185 Fine Vertical Actuator S1104093 Fine Horizontal Actuator S1104092
(Corey, Jim, Vincent)
V3 CPS Swap
At Corner3, we had a broken Coarse (Stage0-1) Vertical (V3) CPS; the serial numbers for the bad CPS/board are: 12865 & 12337. The Sensor was removed from the ISI, and its board was pulled out of its mini-rack.
The new Sensor was installed/aligned, its new board was installed in the rack, and then the gap was set for this Sensor. Here are the serial numbers for our new V3 CPS:
S/N: 12898(probe) & 12416(guage/board)
PS: Vincent's informed me, may have yet another bad CPS, and yes, it's at Corner3 again (more to come later).
No 808nm light yet, we plan on doing that today (Tuesday)
Attached are plots of dust counts > .5 microns during October 7, 2011.
Attached are plots of dust counts > .5 microns. H0:PEM-LVEA_DST12_5: > .5 micron counts in the new H2 diode room H0:PEM-LVEA_DST13_5: > .5 micron counts in the new H2 laser room enclosure
Brushing of the floor was completed this morning. On a positive note, only two drills were required to clean the chamber! First vacuum was finished and wipe down is about 80% done. Some black "crusty" stuff was found on portions of the downstream beamtube nozzle. It required scraping with a razor blade to release from the surface which appeared "pitted" in the areas where "crusties" were found. After I inspected a sample and observed the scraping in action, I consulted with Michael L. We agreed that all areas that had "crusties" should have a post-work FTIR taken.
For the last month or so, the SEI assembly crew has been trying to figure out the source of a lateral "twist" in our third BSC assembly. When we initially loaded and released the ISI (~ 1 month ago) initially we found an approximately .060" rotation in Stage 1 relative to our nominal position. After replacing the flexures and springs,as well as measuring the Stage 0-1 spring posts for machining errors, we adjusted the springs on their mounts (using available dowel pin slop to rotate the springs to counter the ISI's rotation), we floated the ISI a second time and found a .040" rotation. This is close to what we found on the second assembly (BSC6), but this rotation was enough that we could not connect horizontal actuators. For our 3rd round of releasing the springs, we replaced the flexure brackets and gussets. Measurements of old and new brackets/gussets showed no differences, no off angles on either set. This time when installing flexures, though, we pushed sideways (in the plane of the ISI rotation) on the bottom of the flexure, hoping to offset more of the rotation. It seems to have worked, as we now find ~.007" rotation.
(Corey, Filiberto, Hugh, Jim, Mitch, Vincent)
**** This covers Testing & Installation of Cables for BSC8 which covered much of this week. ****
Swapping Cables & Laying Them Out For Final Configuration
Other than the Capacitive Position Sensors, cabling for the BSC8-ISI had been Class-B. This week we swapped out these cables for Class-A cables, and positioned them on the ISI in a "final configuration". Photographed cable layouts, and posted in ResourceSpace, here. Below are the serial numbers and locations for all of the cables we installed this week.
Cable Serial Numbers
Drawing # (D11001__) | S/N (S110____) | LOCATION |
_48 | _4051 | Corner1_Stage1_Horiz Actuator Extension |
_48 | _4050 | Corner1_Stage1_Vert Actuator Extension |
_48 | _4057 | Corner1_Stage2_Horiz Actuator Extension |
_48 | _4058 | Corner1_Stage2_Vert Actuator Extension |
_50 | _5188 | Corner1_Stage1_Horiz Actuator |
_50 | _5187 | Corner1_Stage1_Vert Actuator |
_51 | _4085 | Corner1_Stage2_Horiz Actuator |
_51 | _4084 | Corner1_Stage2_Vert Actuator |
_52 | _5193 | Corner1_Trillium |
_53 | _4556 | Corner1_GS13 Extension |
_53 | _4557 | Corner1_L4C Extension |
_54 | _4256 | Corner1_L4C |
_55 | _4120 | Corner1_GS13 |
_48 | _4056 | Corner2_Stage1_Horiz Actuator Extension |
_48 | _4049 | Corner2_Stage1_Vert Actuator Extension |
_48 | _4047 | Corner2_Stage2_Horiz Actuator Extension |
_48 | _4048 | Corner2_Stage2_Vert Actuator Extension |
_50 | _5189 | Corner2_Stage1_Horiz Actuator |
_50 | _5186 | Corner2_Stage1_Vert Actuator |
_51 | _4086 | Corner2_Stage2_Horiz Actuator |
_51 | _4094 | Corner2_Stage2_Vert Actuator |
_52 | _5192 | Corner2_Trillium |
_53 | _4560 | Corner2_GS13 Extension |
_53 | _4561 | Corner2_L4C Extension |
_54 | _4257 | Corner2_L4C |
_55 | _4122 | Corner2_GS13 |
_48 | _4055 | Corner3_Stage1_Horiz Actuator Extension |
_48 | _4054 | Corner3_Stage1_Vert Actuator Extension |
_48 | _4053 | Corner3_Stage2_Horiz Actuator Extension |
_48 | _4052 | Corner3_Stage2_Vert Actuator Extension |
_50 | _5191 | Corner3_Stage1_Horiz Actuator |
_50 | _5190 | Corner3_Stage1_Vert Actuator |
_51 | _4082 | Corner3_Stage2_Horiz Actuator |
_51 | _4083 | Corner3_Stage2_Vert Actuator |
_52 | _5194 | Corner3_Trillium |
_53 | _4558 | Corner3_GS13 Extension |
_53 | _4559 | Corner3_L4C Extension |
_54 | _4258 | Corner3_L4C |
_55 | _4121 | Corner3_GS13 |
SUS Viton Cable Clamps Installed
Swapped out Peek cable clamps with newer Viton Cabl Clamps for the SUS cabling strung on the side (at Corner3) of the ISI (we did NOT address any clamps on the Optical Table. (photo of Jim installing a clamp is attached)
Testing Seismometer Cables
Before connecting cables to the Interface Feedthrus and Powering ON the seismometers, we used our Emulator box to test out the cables for the L4C's and GS13's. (We were not able to test out the Trillium Cables; we tried the STS2 Emulator, but this did not work for us.)
Balancing Stage 2 & Capacitive Position Sensor (CPS) Issues
On Wed night we made an attempt at checking/balancing the ISI because the SUS group wanted to run measurements on a floating ISI. We were surprised at how much Stage2 was off. It took a while, but we were able to get all the Vert CPS under 0.5V.
After this, we locked up Stage2, and unlocked Stage1 to begin balancing, but then we noticed we had a railed (+13V) V3 CPS. In all liklihood, we are going to have to swap this CPS and board out (we checked it and its cabling several times to no avail).
Change to Cabling Table Above
After routing cables last week, we tested Actuator cables and it was noticed (2) Actuators were wired up wrong (Corner3's Horiz & Vert Fine Actuators were basically switched). The cables were then switched.
On Friday afternoon, I did one more check of all of our cables to confirm everything matched the documentation, and sure enough I saw that the (2) actuators we switched were physically cabled to the wrong actuators!
This morning, we checked the cabling here, and the problem was traced to the Position Sensors (what we use to look at what the Actuators do). The Horiz & Vert Fine Capacitive Position Sensors (CPS's) were the culprits (a Horiz cable was connected to a Vertical Sensor, and vice versa). These CPS's were switched to a correct configuration, and the Actuators were also switched.....all this switching occurred at the Interface Feedthru.
So, to be thorough, here is the correct cabling layout for the Fine Actuators at Corner 3 (:
Drawing # (D11001__) | S/N (S110____) | LOCATION |
_48 | _4052 | Corner3_Stage2_Horiz Actuator Extension |
_48 | _4053 | Corner3_Stage2_Vert Actuator Extension |
_51 | _4083 | Corner3_Stage2_Horiz Actuator Extension |
_51 | _4082 | Corner3_Stage2_Vert Actuator Extension |