Displaying reports 76021-76040 of 76907.Go to page Start 3798 3799 3800 3801 3802 3803 3804 3805 3806 End
Reports until 18:41, Tuesday 14 June 2011
H2 General
matthew.evans@LIGO.ORG - posted 18:41, Tuesday 14 June 2011 - last comment - 09:10, Wednesday 15 June 2011(921)
Biquad Filter Test

Matt, Rolf, Dave, Alex (remote)

We got the Biquad filter module working in the new CDS system and made a few simple tests.  For these test I created a few somewhat complex filters:

The first test was to check the transfer function.  The biquad filter matched the the standard filter (direct form 2) with various combinations of the above filters.  No problems were observed.

The noise test was designed to match the test performed at the 40m lab in March 2008. With all of the above filters engaged, a 1 Hz sine wave with amplitude 1 was injected into the input of the biquad filter and a standard filter module. In the frequency region where the noise is amplified by the HP filter, the biquad filter produced a numerical noise floor 8 orders of magnitude lower than that of the standard filter. Furthermore, the harmonic distortion seen in the standard filter was absent in the biquad.

Non-image files attached to this report
Comments related to this report
matthew.evans@LIGO.ORG - 09:10, Wednesday 15 June 2011 (922)

A little more information... the trouble with DF2 is that it essentially applies the poles first, and then the zeros.  This is a problem only when there are low-frequency poles and zeros, since the input is attenuated by the poles (into the numerical noise generated by the filter), and then amplified by the zeros (along with the noise).  The "Not 1Hz" filter is designed to demonstrate this by placing poles and zeros at the same frequency, both for the notch at 1Hz, and the pole/zero pair at 10mHz which accetuates the effect.  The input 1Hz sine wave is also attenuated by this filter, so that the noise generated in the filters is easier to measure.  The noise is then amplified by the "HP 1k" filter which follows the "Not 1Hz" filter to prevent masking by numerical noise added later in the data recording and processing.  (The "Pass 1Hz" input filter is present only to reduce the on and off glitches produced when starting and stopping the excitation.)  See also G0900928.

H2 General
kyle.ryan@LIGO.ORG - posted 17:10, Tuesday 14 June 2011 (920)
Valved-in ion pump, valved-out turbo on HAM6


			
			
H2 General
jonathan.berliner@LIGO.ORG - posted 16:14, Tuesday 14 June 2011 (919)
Tuesday Ops Log
- Laser Safe today.
- RichardM, CyrusR and FilibertoC out to work by SUS stand by HAM12
- TerryS and crew mopping in the LVEA by BSC7 and BSC10
- MichaelR installing acoustic enclosures by H2 PSL, drilling into studs.
- RichardM works on TCSX access controls
- DaniA works on TCSY dark study
- Ski and Control Solutions technician out to MY to work on HVAC control system
- Paradise Water arrives in the morning
- Apollo crew working at EY
- DI water overflowed in LSB Fiber Lab at ~15:50. Clean-up is ongoing, LisaB supervising.
- Clean room craned to HAM12
- Sock placed on top of BSC7's dome
- GregM gave seminar on Fourier Transformations
- DaniA gave laser safety orientation to SURFs
- Particle counts high in OSB Bake Oven Lab (see Kyle's entry), HAM12 (mopping), H2 PSL (mopping).
LHO FMCS
kyle.ryan@LIGO.ORG - posted 14:46, Tuesday 14 June 2011 (918)
High particle counts in room 169 (bake oven room)
Over the past several weeks I have been notified by Patrick and Jonathan of intermittent high particle counts being recorded in the bake oven room (room 169).  These high counts don't necessarily correspond to times when people are present in the room -> 

Initial investigation shows that the dedicated exhaust fan (added to exhaust any "smells" that could eminate from the hot ovens to the building exterior and which is separate from the HVAC) has 0.6" H2O accross its iris damper while nominal has traditionally been 0.5" H2O.  The variable speed adjust is set to minimum speed which is normal and should result in 0.5" H2O drop when all other air supplies/returns are nominal.  Ski confirms nothing has changed recently in the HVAC system supplying this and adjacent rooms. Also, the fume hood switch is in the on position as is nominal.  

I noticed that the ceiling tile located directly above the particle counter shows evidence of having been removed recently (caulking seam separated with visible gaps around tile periphery).  I will see to it that this tile gets caulked and attempt to verify the the fume hood fan is actually working.  Also, its time for a general clean-up in this room.
LHO FMCS
kyle.ryan@LIGO.ORG - posted 18:29, Monday 13 June 2011 (917)
Vertex opened to X-end + YBM
Opened Vertex to the YBM and X-end for a couple of hours for the squeezer folks.  Vertex and X-end pressures too high to leave opened to BT for any extended period.

Need to review user settings for Corner Station large ion pumps -> seems like maximum power setting is set too low and/or current limiting "I-protect" option not as expected.  
H2 INS
patrick.thomas@LIGO.ORG - posted 16:23, Monday 13 June 2011 (915)
Ops Shift Summary
Apollo clening in new transmon lab at end Y
Cleaning at BSC7 in preparation for in chamber cleaning
Assembly of clean room for mechanical test stand
Drilling for floor bolts for squeezer table stand
Gate valves opened for locking H1 X arm
CDS work on electronics racks in LVEA for H2 ITM cartridge install
Cardboard recycling pickup
H2 INS
patrick.thomas@LIGO.ORG - posted 15:50, Monday 13 June 2011 (916)
dust monitor 4
The dust monitor at location 4 was pulled outside of the clean room at ~22:00 UTC.
H2 INS
david.barker@LIGO.ORG - posted 12:35, Saturday 11 June 2011 (914)
summary CDS computing install in LVEA

Summary of work performed 6-11th June. Rolf, Dave, Richard, Cyrus. Computing and Networking

We have installed five front end computers in the LVEA on the outside of the Y arm, next the the TCS systems. Four of these computers have IO Chassis attached and are

h2susb478 sus ITMY
h2susb78 sus FMY
h2seib8 seismic BSC8
h2susauxb478 sus aux ITMY/FMY

The fith machine is h2tcsl0 which is waiting on its Chassis.

All four machines are running IOP models and user models. All were built against RTS branch-2.3.

Networking was installed in the LVEA to support these systems. A Workstation was installed (on the CDS LAN) next to the racks. More workstations will be moved into the inside of the arm when needed.

LHO FMCS
kyle.ryan@LIGO.ORG - posted 20:03, Friday 10 June 2011 (913)
X-end on turbo

Note:  The measured dewpoint of the blow down air, i.e. the air comming out of the +1 psig VE, was -6C while the air sourced from the purge air header measured the normal <-54C.  Prior to valving-in the pumps to a vented volume I typically close the vent valve to the VE and measure the air sourced from the purge air header then close-off the header air and open and measure the air blowing out of the slightly pressurized VE.  Normally the two measure the same as you would expect and are "off scale" dry.  In this case, the two were much different.  I repeated this measurement a few times and the values were exactly repeatable.  I conferred with John W. and decided to begin pumping the "wet" VE anyway.  

The ambient humidity is high today.  I intend to investigate with the people involved with today's unlocking if they had closed-off the purge air during the in-chamber activity for some reason or if they had blocked off 1/2 of the door opening as is the norm.  Not doing so would negate the effectiveness of the purge air's ability at keeping wet room air from mixing with the chamber interior air and might explain this observation. 

I opened GV7 too.  

The mid stations don't have their pressure gauges cabled and CDS indicated values are bogus.  Y-mid seems slow to change and is still indicating ~8 x 10-8 torr at the turbo inlet.  
H2 INS
patrick.thomas@LIGO.ORG - posted 18:33, Friday 10 June 2011 (912)
Ops Shift Summary
H1 ETMX was unlocked
HEPI welding continues
HAM 7 HEPI install work
assembly of test stand cleanroom
CDS work on electronics racks in LVEA for H2 ITM cartridge install
X1 SUS
mark.barton@LIGO.ORG - posted 17:21, Friday 10 June 2011 (911)
Problem with test stand M0 and R0 SD OSEM sensor channels
Since the test stand upgrade, the side OSEM sensor channels (X1:SUS-QUAD_M0_OSEMINF_SD_IN1 and X1:SUS-QUAD_R0_OSEMINF_SD_IN1) have been very noisy, to the point where enabling the SD DOF control loops would trip the watchdog because of HF signals amplified by the upward slope in the software output filter.

The noise looked vaguely digital in dataviewer but it was hard to tell due to the poor time resolution, and until today we hadn't probed in more detail. However doing a triggered time response measurement in DTT revealed that an otherwise plausible looking signal is being chopped by a rectangular window at 16 Hz with a 1/8 duty cycle (i.e., 1/128 s on out of 1/16 s). See the attached plot, which shows X1:SUS-QUAD_R0_OSEMINF_SD_IN1 (which exhibits the problem) against X1:SUS-QUAD_R0_OSEMINF_F1_IN1 (which doesn't).
Non-image files attached to this report
H2 INS
greg.grabeel@LIGO.ORG - posted 16:52, Friday 10 June 2011 (910)
HAM 7 HEPI Install

The North end of HAM 7 has had the weldments and crossbeam attached. It was a very tight fit to move the crossbeam between the two chambers. Some creativity was called for, but installing the crossbeam for HAM 8 may require even more. The next steps will be to finish the clamp on the crossbeam and torque the bolts all of the bolts.

Images attached to this report
H2 INS
hugh.radkins@LIGO.ORG - posted 15:40, Friday 10 June 2011 (909)
HEPI Phase2 Welding In Progress
The HEPI Plumbing is now in the LVEA.

Image1 is the turns up on the Mezzinine.  #2 is below the mezzinine heading into the LVEA.  #3 is in the LVEA at the piping bridge.
Images attached to this report
X1 SEI
fabrice.matichard@LIGO.ORG - posted 18:03, Thursday 09 June 2011 (907)
Two Stages Floating - Testing Starts
The two stages of the first BSC-ISI have been released and balanced. 

Stage 2 total mass is 235 lb under the 6240 lb nominal. So we'll use 550 lb of mass on the keel mass instead of 785 lb. I am going to communicate the number to SYS so they can adjust their models and balancing.

Stage 1 is 135 lb under nominal (out of 8250 lb total on the large blades), about -45lbs/corner, which is very good.

Thanks to all the team for all the efforts to make it possible to float the platform only 5 weeks after we started the assembly.

We now start the testing of Unit #1, and keep working on the assembly of Unit #2. 
Images attached to this report
LHO FMCS
dani.atkinson@LIGO.ORG - posted 16:09, Thursday 09 June 2011 (906)
Ops Day Shift Summary
  • EX (BSC9) was prepared for door removal and unlocking of the ETM tomorrow morning.
  • Work at EY to prepare for receipt of BSC6.
  • Vacuum prep room of OSB is getting some ridiculously high dust counts. Kyle speculates that it could be air flow issues, and notes potential changes to the exhaust fan in that room.
  • Construction of a tall clean room in the LVEA got as far as an unadorned structure today, waiting for a ceiling, electrical appliances, curtains, etc.
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:42, Thursday 09 June 2011 (905)
Closed GV10, Vented X-end


			
			
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:41, Thursday 09 June 2011 (904)
X-mid on IP10 (10-8 torr from turbo)
Burped GV15 gate annulus into aux. cart, cracked GV15 to pump X2 hydrogen while X-end isolated.
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:38, Thursday 09 June 2011 (903)
Vertex & HAM6 pumping


			
			
X1 SUS
robert.lane@LIGO.ORG - posted 11:00, Thursday 09 June 2011 (902)
LHO SUS Test Stand
Power Spectrum of LHO SUS Test Stand without any OSEMs. Disconnect at the point where octopus cables would attach. 

Interesting harmonic of interest at 16 Hz in side channel.

AC power harmonic in all channels (60 Hz)
Non-image files attached to this report
H2 INS
benjamin.abbott@LIGO.ORG - posted 10:03, Thursday 09 June 2011 (901)
Single Arm ISI Install
Sam and I, with much help from Richard, Filiberto, and Carl, have populated the two racks for the Single Arm Installation.  For the corner, the chassis are in, and the internal wiring is all hooked up.  At the end, most of the chassis are in, but Rolf is using the IO Chassis, and two binary chassis for some testing in the computer room, so those parts are not yet installed.  All of the cables are, at least, attached at one end, waiting for the IO chassis, or Binary chassis.  We just finished making the field cables that we need to test, and we will start testing this morning.
-Ben   
Displaying reports 76021-76040 of 76907.Go to page Start 3798 3799 3800 3801 3802 3803 3804 3805 3806 End