Displaying reports 76181-76200 of 76892.Go to page Start 3806 3807 3808 3809 3810 3811 3812 3813 3814 End
Reports until 23:20, Tuesday 19 April 2011
X1 SEI
corey.gray@LIGO.ORG - posted 23:20, Tuesday 19 April 2011 - last comment - 08:44, Wednesday 20 April 2011(741)
BSC ISI Assembly Status

[Corey, Hugh, Jim, Stephany]

BSC#1 Assembly Work

More helicoils were installed on the Optics Table (until we discovered we were almost out of helicoils).  The Stage0 Base was lifted off the tested so it could be weighed (this was done with a load cell via the forklift).

BSC Work Area Clean Up (aka HAMISI#3 Work)

Made first attempt at installing the Vertical GS13's & two thirds of their Outer Walls, and then discovered the feed-thrus did not line up with the hole in the Stage-1 floor!  Basically, procedure (E0900216-v5) uses a drawing to show how to orient/install the vertical GS-13, and this drawing is 120 degrees off.  Looking from the top, the Vert GS13 should actually be 120deg counterclockwise from how it is displayed in the photo (figure is attached).  So most of the day was devoted to installing the GS13/Walls, uninstalling, and then re-installing.  In all the hub bub, I failed to note the Serial Numbers for the now-covered GS13's.  I did get one of them though.  V2 is S/N 163.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 08:44, Wednesday 20 April 2011 (743)

One More HAMISI Procedure (E0900216) Note

For installing the Outer Walls, the procedure does not make mention of torquing the 120deg brackets during installation (this is in Sec. 4.34).  This could be an easy thing to forget during installation with all the bolts to be torqued.

LHO FMCS
kyle.ryan@LIGO.ORG - posted 21:03, Tuesday 19 April 2011 (740)
Apparent leak in Y-1 module
I noticed that the Y-1 module pressure was in the upper 10-7 torr (Y-mid end) range as I was preparing to leave tonight!!!!! -> I notified John W. and went to the Y-mid to investigate:  

*GV10 and GV9 annulus pressures ~normal 
*CP3 level normal
*Started QDP80 pump and connected it to the closed purge/vent valve (Y-mid MTP decoupled to premit retraction of spool bellows for BSC6 removal) in preparation to rough-down BSC6 volume (currently vented)
*combined GV10 gate annulus volume to rest of annulus piping (i.e. pumped GV10 gate annulus) 
*Soft-closed GV9 

John, Bubba, Scotty and Robert S. arrive 

*Begin pumping down BSC6 volume with QDP80 
*Tightend many of the suspect-looking "gappy" conflat flanges, tapped joints, wiggled external piping etc.
*Opened GV9 
*Closed Y-mid vent/purge valve but leaving QDP80 running

No conclusion at this time.  

John W. confirms that he is able to view the site from home. John W. and I (maybe Mike L.) will monitor off and on from home during the night.  

PT244 @ 1.08 x 10-6 torr as of 2105 hrs. local
H2 INS
michael.rodruck@LIGO.ORG - posted 18:45, Tuesday 19 April 2011 (739)
H2 PSL installation

Work was started on the interior insulation. Contractors also started work on the floating outer wall but we ran into problems with the drywall screws being too long and touching the inner layer of drywall. They will continue tomorrow with shorter screws.

Dust counts remain normal

H2 General
cyrus.reed@LIGO.ORG - posted 16:40, Tuesday 19 April 2011 (738)
Ops Day Summary
Usual Tuesday deliveries.  Work continues on H2 PSL enclosure and chamber cleaning tests.  Dust monitor trends attached for 0730-0430 local time, same locations as previous entries.
Images attached to this report
X1 SUS
betsy.weaver@LIGO.ORG - posted 15:20, Tuesday 19 April 2011 (737)
One Arm ITM (ETM02)
Marielle and Margot are visiting this week to bond the first test mass, the one arm ITM.  Pictures are of the the optic with First Contact applied to the HR surface (by Margot yesterday), and of Marielle and Gerardo using the Romer CMM Arm to measure the thickness of the optic in a few places (verifying wedge, etc, in prep for locating the ears for bonding).
Images attached to this report
LHO FMCS
mark.lubinski@LIGO.ORG - posted 11:20, Tuesday 19 April 2011 (736)
Well Pump
Ran well ump to fill well tank.
X1 SEI
corey.gray@LIGO.ORG - posted 21:05, Monday 18 April 2011 (735)
BSC ISI Assembly Status

[Corey, Jeff, Jim, Stephany]

BSC#1 Assembly Work

Lots of shuffling took place today as plates were moved within the Staging Bldg and from the Vacuum Prep Warehouse.

Helicoiling and dowel pins were finished off on the Stage0 Top Plate.  The Top Plate was then installed & torqued onto the Bottom Plate.

The Optics Table was brought onto the Granite Table and now helicoiling begins!

BSC Work Area Space Creation

This section covers work to reassemble HAMISI#3 (i.e. clearing shelf space for upcoming BSC work). 

All of the Sensor Assemblies were installed.  It was determined earlier that two of the Sensors for #3 were bad, so new ones were swapped in for #3.  The new Sensors are S/N# 12029--->H3 & S/N# 12040--->V3.

During disassembly it was noticed that the small screws in the cable plugs which connect to the GS13 looked pretty damaged (their threads were really eaten up during assembly).  It was decided we don't want to use these screws, and want to just plug in the connectors.  But to do this, the damaged screws have to be pulled out because they don't allow the plugs to be connected.  This was done for all (6) plugs.

All of the Horizontal GS13's were installed. 

Note On Broken Tangs:

A few times during the reassembly of #3, rogue broken tangs have been found on several occasions (i.e. when you're installing a part, one finds that a bolt won't screw in---usually damaging the bolt).  This has happened while installing an Actuator and while installing a GS13.  So, eventhough we may be thorough, not all broken tangs are being accounted for.

Images attached to this report
H2 INS
michael.rodruck@LIGO.ORG - posted 17:03, Monday 18 April 2011 (734)
H2 PSL installation

Today the contractors installed insulation on the roof, later covering this with another layer of sheetrock. Aluminum standoffs were also installed on the 4 sides of the building - the floating exterior wall will attach to these.

As Dani mentioned, dust levels remain normal. One week trend is attached.

Images attached to this report
LHO FMCS
dani.atkinson@LIGO.ORG - posted 16:01, Monday 18 April 2011 (733)
Ops Day Shift Summary
  • Cleaning preparation work was done on aHAM12 (iHAM11).
  • Construction continued on the H2PSL enclosure with laying of drywall.
  • I tracked dust monitors during this activity to see if dust from drywall laying was potentially getting into open HAM. Attached is a chart showing today's dust monitor trends, the only significant spike inside the clean room was when the forklift was maneuvering through the doors. Other than that activity was really low (<500) and drywall work doesn't seem to have interfered.
Non-image files attached to this report
X1 SUS
betsy.weaver@LIGO.ORG - posted 14:11, Monday 18 April 2011 - last comment - 14:15, Monday 18 April 2011(727)
Particulate Blow off
A MicroVac Portable ULPA Cleanroom Vacuum/Blower was purchased from Terra Universal.  After Class B'ing a TFE hose, we confirmed that particle counts coming out of the exhaust and through the TFE hose were near zero (after making sure that surrounding dust wasn't being picked up and slewing the counts).  Friday, we attempted to take some video/pictures of the blower hose blowing off particulate collected on a tabled QUAD UIM subassembly (see attached pictures). The field of view of the surface in the video is on the order of a few square inches.
Images attached to this report
Non-image files attached to this report
Comments related to this report
betsy.weaver@LIGO.ORG - 14:13, Monday 18 April 2011 (731)
A different round of blowing in a different location of a UIM.
Images attached to this comment
betsy.weaver@LIGO.ORG - 14:15, Monday 18 April 2011 (732)
It's a bit difficult to quantify how much particulate is being removed, but it is clear from the photos/video that a significant portion of the macroscopic stuff is being removed.
H2 General
robert.schofield@LIGO.ORG - posted 12:52, Monday 18 April 2011 (730)
Building slab follows ground below a few Hz
On several occasions I have set up seismometers on a building slab and on the ground near the slab and found that the slab follows the ground below a few Hz. However, I don’t think that I have previously put these results in the log. 

Recently Jan Harms and I were making Newtonian-noise related measurements and set up seismometers at the locations indicated on the attached plan of the corner station. The top plots in the figures X,Y and Z show calibrated velocity spectra for the X, Y and Z axes (directions indicated on the plan) for seismometers at locations indicated by arrows on the plan in colors matching the spectrum trace colors. The lower plots in each figure show coherence between the seismometer on the slab edge and the one 3.5 meters away, off of the slab in the gravel (RED). For comparison, the figures also show (BLACK) coherence with the seismometer that is 3.5 m in the opposite direction on the slab. Because we used only 2 seismometers, the black traces were taken at a different time. Coherence between the slab-edge seismometer and the off-slab seismometer drops faster with frequency than for the slab-edge and the other seismometer on the slab. 

The frequency at which coherence drops off between the slab-edge and the other on-slab seismometer at a distance of 3.5m away, is typical for 3.5m spacing, even at the center of the slab, and does not result from one of the seismometers being at the edge of the slab. The drops in coherence in the 1 Hz region, where the velocity is lowest, are also present in spectra from the huddled seismometers, indicating that a significant fraction of the signals in these regions are due to electronic noise. The black traces were made at lower resolution than the other traces and so do not extend down to the lower frequencies.

The on-slab and off-slab spectra are very similar and the coherence is high below about 3 Hz in X, 5 hz in Y, and 8 Hz in Z. For fundamental Rayleigh waves, the wavelengths at these cutoff frequencies are thought to be of order 100 meters, based on propagation velocity measurements.

Robert S., Jan H.
Images attached to this report
Non-image files attached to this report
H2 INS
robert.schofield@LIGO.ORG - posted 11:34, Monday 18 April 2011 (729)
H2 PSL table installation successful
Last week we mounted the H2 iLIGO PSL table on a new leg system for aLIGO, discussed here.

Our design philosophy was to minimize RMS motion in the aLIGO band by raising the table sway resonances from iLIGO’s 20 Hz to about 100 Hz, and the vertical bounce on the legs from the 40-60 Hz region to about 200 Hz. We did not want to raise the resonances much higher, because they would overlap with the periscope resonance. We chose not to float the table because the system we have experience with only controls 3 degrees of freedom and it increases low frequency motion in the 1 Hz region and below.

Figures 1 and 2 show displacement spectra and RMS from accelerometers mounted on the H1 (iLIGO) table (red), and the H2 aLIGO table (blue) for comparable locations near the periscope position, taken at the same time, and a spectrum from the floor near the H2 table, taken at a slightly different time (black). Clean rooms were off for these spectra. The lowest of the sway resonances of the new table is at about 95 Hz, not quite 100 Hz, but acceptable, and the bounce mode is at about 200 Hz. 

The RMS motion of the new H2 aLIGO table above 10 Hz is about 20% greater than the rms for the black floor trace, while the RMS motion of the iLIGO H1 table is 730% greater. 

These results were comparable with those from the first installation, made at LLO, discussed here.

Robert Schofield, Rick Savage, Michael Rodruck, Mark Dodson



Non-image files attached to this report
Logbook Admin Bug
michael.rodruck@LIGO.ORG - posted 10:23, Monday 18 April 2011 - last comment - 17:08, Thursday 15 September 2011(728)
Search bug

If you type an entry into the "Quick search" box and hit enter, the page refreshes instead of executing a search. You have to click the search button to actually do a search.

Comments related to this report
jonathan.hanks@LIGO.ORG - 17:08, Thursday 15 September 2011 (1411)
Fixed as of Sept 2011.
LHO FMCS
kyle.ryan@LIGO.ORG - posted 16:48, Friday 15 April 2011 (726)
Prepped HAM12 south door for removal on Monday


			
			
H2 INS
michael.rodruck@LIGO.ORG - posted 16:27, Friday 15 April 2011 (723)
H2 PSL installation

Work was finished on the first layer of exterior sheetrock, as well as the interior ceiling sheetrock. More sheetrock work to be done on Monday.

Dust levels are normal. Plot shows one week of data.

Images attached to this report
H2 General
jonathan.berliner@LIGO.ORG - posted 16:24, Friday 15 April 2011 (725)
Friday Ops Log
- H2 PSL: Work was finished on the first layer of exterior sheetrock, as well as the interior ceiling sheetrock. (MichaelR)
- Group from WSU touring site, including LVEA.
- Terry Santini at EY to fix water pump.
- Electronics delivery expected for Richard hasn't arrived yet (or at least when I was here).
X1 SUS
betsy.weaver@LIGO.ORG - posted 16:03, Friday 15 April 2011 (724)
QUAD work - Q3 status
After running the balance of the test procedure on Q3 on Thur, we dropped the ECD blocks onto both chains.  New TFs revealed than something was then touching.  After another few hours of BOSEM/ECD plate alignment (which basically pushed us back through a portion of the test procedure), we finally found the slight interference.  Rob is back to running the TF gamut.  Of the 12 he had to re-take, he has 3 left for Monday.  
X1 SUS
mark.barton@LIGO.ORG - posted 10:44, Wednesday 15 December 2010 - last comment - 13:27, Friday 15 April 2011(414)
Quad test stand pitch/yaw range
Betsy, Jeff and I did a measurement of the maximum obtainable pitch and yaw range on the rebuilt Quad #2 using an optical lever. According to Norna's write up, T1000268-v1 ( https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=11868 ) we should be able to get 1.4 mrad in each direction at the optic. At the DOF Test screen we applied successively offsets of +2556 and -2556 in pitch and +7863 and -7863 in yaw, which with the usual output matrix maxes out (32K) at least one of the OSEMs. The resulting deflections of the optical lever spot were +9.5 and -11.5 cm in vertical (+=down) and +5.5 and -6.5 cm in yaw (+=left). The optical lever baseline was 4.98 m. 

This implies a total range of 1 mrad in pitch and 0.5 mrad in yaw, which is rather less than expected. A big chunk of this is that the actual UK driver boxes for the test stand were not built to the 200 mA max output assumed in T1000268. To check this, the voltage across the face1 coil was measured at the simulated vacuum flange, with 32K-1 of offset applied at the Output Filters screen. The resistance (including that of the cables) was 39.9 ohms and the voltage was 3.69 V implying a maximum current of 92.5 mA.

The fact that the pitch range is larger than the yaw is probably connected with the fact that the fundamental pitch mode frequency is rather lower than in the model, i.e., there is more pitch compliance than expected.
Comments related to this report
mark.barton@LIGO.ORG - 13:24, Friday 15 April 2011 (721)
Further investigation revealed that the driver boxers are not the problem. The LHO ones have all been tested to 200 mA for 20 V input - see S0900011, S0900012, S0900013. The early low-capacity drivers that Norna recalled were apparently sent to LASTI - according to Brett Shapiro those were 75 mA units.
mark.barton@LIGO.ORG - 13:27, Friday 15 April 2011 (722)
Correction: test reports S0900011, S0900012, S0900013 were for LLO. Test reports S0900050, S0900051 and S1000001 are for LHO. In any case all top drivers for both sites have been tested to 200 mA.
Displaying reports 76181-76200 of 76892.Go to page Start 3806 3807 3808 3809 3810 3811 3812 3813 3814 End