Displaying reports 76321-76340 of 76889.Go to page Start 3813 3814 3815 3816 3817 3818 3819 3820 3821 End
Reports until 16:14, Thursday 03 March 2011
LHO FMCS
john.worden@LIGO.ORG - posted 16:14, Thursday 03 March 2011 (593)
HAM chamber weight
Bubba evened the wager count. HAM11 was weighed today with two 84inch doors and two 68inch temporary covers of 3/16 aluminum. There were no internal components for this measurement. Annulus ion pump and power supply were still mounted. Actual weight was 9200 pounds (winning number was 9210)
LHO FMCS
dani.atkinson@LIGO.ORG - posted 16:17, Wednesday 02 March 2011 (591)
Ops Day Shift Summary
  • H2 input beam tube was removed and placed on the stands on the LVEA floor.
  • Ski and a visiting contractor worked on the air handler systems.
  • Betsy took a SUS delivery at the staging building.
H2 INS
patrick.thomas@LIGO.ORG - posted 10:33, Wednesday 02 March 2011 - last comment - 11:29, Monday 07 March 2011(590)
dust monitors in LVEA
I have changed the holding time to 1 minute and the sampling time to 1 minute for all the dust monitors in the LVEA in an attempt to resolve a problem with them getting stuck on hold.
Comments related to this report
patrick.thomas@LIGO.ORG - 11:29, Monday 07 March 2011 (599)
Seems to be working so far.
H2 INS
patrick.thomas@LIGO.ORG - posted 17:10, Tuesday 01 March 2011 - last comment - 16:20, Thursday 03 March 2011(589)
Ops Day Summary
8:36 Unifirst delivery
~11:09 Praxair filled CP1 and CP2

Richard investigated the tripped breaker for the LDAS chiller
Dave tested the vacuum system email alarms
HAM 11 was picked up and moved next to the Y arm! (pictures attached)
Images attached to this report
Comments related to this report
john.worden@LIGO.ORG - 16:20, Thursday 03 March 2011 (594)
HAM weight is reported in Thursday's alog.
X1 SEI
hugh.radkins@LIGO.ORG - posted 16:37, Tuesday 01 March 2011 (588)
HAM Assembly #3 Vertical Height Measurement
Measured with the Optical Level the vertical distance from the TestStand Stage0 Supports to the top of the Optical Table.  This gives us an idea of how tall the assembly is wrt design.

Using the Wilde Optical Level we averaged the four ends of the HAM Adapter Bars Height.  These sit between the Stage0 bottom and the Test Stand.  This gave us an average height of the bottom of the Stage0 mount.  We then shot the top of the Optical Table at four corners and the middle.

The average height difference was 780.8mm; the design height given by DCoyne PerComm is 780mm.

So not bad.  Attached is the field note.
Non-image files attached to this report
H2 DAQ
david.barker@LIGO.ORG - posted 16:02, Tuesday 01 March 2011 (587)
maintenance summary

All aligo and iligo CDS machines with ports open to GC were patched this morning. If a reboot was required to complete the patch it was done so.

machines patched are: ruby,silverstar,ilog,apache,sugarloaf,strawberry,cdslogin,cdswiki

H2 INS
corey.gray@LIGO.ORG - posted 15:52, Tuesday 01 March 2011 (586)
HEPI "Feet" Set To Nominal Position For One BSC's Worth of HEPI

(Corey, Greg, Hugh)

In preparation for installing the HEPI Assemblies on an upcoming BSC, Greg & I set the HEPI Foot to it's "nominal position" for four of HEPI Assys (to be installed on BSC7).  On the HEPI "Cage", there is a part/serial number marked on the base.  The four we worked on were Serial #'s:  54, 77, 51, & 45.

H2 General
bram.slagmolen@LIGO.ORG - posted 14:29, Tuesday 01 March 2011 (585)
ISC components from LVEA to Optics Lab
I took (3) plastic containers from the ISC Optics cabinet near the H1 PSL into the Optics Lab (container ISC-18 (various optics), ISC-19 (1" and 2" newport mounts) and unlabelled with bases and posts). We will use these parts to set up the Reference cavity for the H2 One Arm Test (H2OAT).

We will keep track on what we took from the containers, to keep the stock list up to date.

Also, I took the 'spare' 21.5 MHz modulator from the cabinet from the cabinet labelled 'Camera', which has a list on the door with 'Who' took 'What' and 'Where' with 'Date'. So I listed the modulator and my name on it as well. I guess I will double check if we can use this modulator.

Still not sure what the beam height on the table should be, as the RF diode is at ~3" height (unless there is a magic spacer). I guess the 'soon to come laser' will probably set the standard.
LHO FMCS
david.barker@LIGO.ORG - posted 17:22, Monday 28 February 2011 (582)
roll out of new alert machine

I have created a new machine which sends EPICS alarms as text messages to cell phones. It is a GC machine which is also on the iLIGO CDS network. Its names are:

sugarloaf.ligo-wa.caltech.edu
cdsalerts

It is running a modified version of the email_alarms.pl script, ported from solaris to linux and using burt in place of caGet. This system can send emails directly, even to Sprint phones. So it is not dependent upon the robinson email proxy which the old system needed.

X1 SUS
jeffrey.bartlett@LIGO.ORG - posted 17:11, Monday 28 February 2011 (581)
Quad 3 Rough Alignment
We completed the Quad 3 rough alignment for both chains. Set up the optical lever and started on the fine alignment. Found the Reaction chain yawed relative to the Main chain and the structure, and adjusted the Top Stage blade angles to remove the yaw. We will work on setting the pitch tomorrow.    

H2 General
jeffrey.garcia@LIGO.ORG - posted 15:58, Monday 28 February 2011 (580)
Ops Day Summary

~9:45 fb0w was re-booted 

10:30 - Rodney to Squeezer area to flush out eyewash station

Hugh and others prepping for HEPI install

11:35 – Dave reports that fb0w is stable and rebooted the machine to begin writing frames again.

12:30 – truck for freight pick-up from Doug
LHO FMCS
mark.lubinski@LIGO.ORG - posted 14:21, Monday 28 February 2011 (579)
Facilities
Flushed all of the eye wash/shower stations in LVEA, LSB Optics lab and Warehouse
H2 General
david.barker@LIGO.ORG - posted 11:57, Monday 28 February 2011 (578)
fb0w not writing frames while LDAS was down

H1 DAQ system.

LDAS were down due to  cooling issue in their server room. While the disk system for fb0w's frames were not available, fb0w was ran in partial mode (real time data only). LDAS have recovered their disk system and fb0w is now writing frame files again.

The data gap on nds0 is

08:50 H-R-982947008-32.gwf
11:37 H-R-982957024-32.gwf

For data in this period, please use nds2.

LHO FMCS
mark.lubinski@LIGO.ORG - posted 10:19, Monday 28 February 2011 (577)
FMCS
RO unit shut down in auto from level control
Logbook Admin General
jonathan.hanks@LIGO.ORG - posted 09:41, Monday 28 February 2011 - last comment - 08:29, Tuesday 01 March 2011(576)
aLOG system maintenance tomorrow (Tues 1 Mar 2011)
The aLOG will be rebooted tomorrow after some routine system maintenance.

The reboot should happen at 10am Pacific time 1 Mar 2011.  Please save any entries you may be working on before that time.  The down time is expected to be a minute or two.
Comments related to this report
jonathan.hanks@LIGO.ORG - 08:29, Tuesday 01 March 2011 (584)
The system maintenance has been completed.
jonathan.hanks@LIGO.ORG - 21:48, Monday 28 February 2011 (583)
There is a fair chance that I will need to be elsewhere at 10 am Pacific.

The aLOG will be rebooted around 8:15 am Pacific on 1 Mar 2011.

Please be sure to save your entry before the reboot.
LHO FMCS
mark.lubinski@LIGO.ORG - posted 07:30, Monday 28 February 2011 (575)
FMCS
Started RO unit this morning at 06:45
LHO FMCS
mark.lubinski@LIGO.ORG - posted 07:28, Monday 28 February 2011 (574)
FMCS
The chiller was running Friday and Saturday morning for the Corner station.  We lost the chiller some time on Saturday, but the CWP remained running at 45 Hertz, but there was no display on the controller panel.  I've turned off that pump, manually restarted CWP2 and Chiller 2 started.  Once temps return to normal we will turn the heat back on.
Displaying reports 76321-76340 of 76889.Go to page Start 3813 3814 3815 3816 3817 3818 3819 3820 3821 End