After discussing the issue of an interfering table mass last week we elected to move the mass 2" in -Y to allow the PR2 scraper baffle to be installed in the correct location using the cookie cutter. There were no further issues encountered and the work is now complete. I placed the old baffle Z plate on a shelf in the clean room outside HAM2 that will need to be sent back to UF for modification.
I've run the latest security updates on the two CDS nameservers, and rebooted them this morning.
[Sheila and Kiwamu]
The FSS wasn't locking this morning, interrupting PMC's lock. Lowering PSL-FSS_RESONANT_THRES from 0.9 to 0.5 fixed the issue. The alignment on the FSS reflection camera looked bad. It has been unclear why the FSS alignment kept drifting in pitch.
It appears to have crashed over the weekend.
There was an earthquake close by this morning at 06:47. SUS IOP watchdogs did not trip, looks like it was all over in less than a minute.
The plot is 10 minutes of second trends, starting at 06:40.
Changed the /opt/rtcds/userapps/etc/userapps-user-env.sh file to a new copy checked out from the userapps repository. The new configuration includes paths added to support the userapps repository changes made Nov. 15.
Changed the /opt/rtcds/userapps/etc/userapps-user-env.sh file to a new copy checked out from the userapps repository. The new configuration includes paths added to support the userapps repository changes made Nov. 15.
[Jeff B, Jeff L, Rich A, Koji A]
On Friday, we looked at OMCS for the preparation of the installtion after the TF approval in the late afternoon.
- Dog clamps, 12pt screws, the cookie cutter, and its screws were prepared.
- The genie lift was moved near HAM6
- We looked at the cable routing. The quadrapus cables are too long & we have three unused connectors.
They will be tacked on the OMCS structure.
- The isolation between the cable shields and the suspension structure was checked. We found that the
shield of the OMC ISC cables are shorted to the suspension structure. The DCPD preamp housings
(made of AL) are directly attached on the structure. (The situation is the same for the LLO OMC too.)
We can't isolate the preamp right now unless we have some special PEEK components
such as PEEK 1/4-20 screws or PEEK shoulder washers for 1/4-20. We have CLASS A, C&Bed Kapton
sheets, which may be useful.
On Monday morning, we continue to work on the cable routing while the remedy for the preamp isolation will also be explored.
With help from CherylV, JoeG, VolkerQ, OlliP, PeterK et al., we completed the installation of the H1 PSL ISS 2nd loop PD array in HAM2 yesterday afternoon. This array was fabricated and aligned by OlliP, PeterK, RichA, and CalumT at CIT, then shipped to LHO and set up in the H2 laser area enclosure for further testing of sensitivity to pointing fluctuations and final alignment. An updated method for quantifying the pointing sensitivity and executing the final alignment was developed and is documented in T1300925 which will be posted to the DCC shortly. Also, the performance of this array is captured in the test report, E1300863, which should also be posted to the DCC shortly. The installation went relatively smoothly after recovering from compiling issues after the update of the RCG code on Tuesday (thanks to Arnaud and Jeff for help with the suspensions). The DC voltage levels seem to indicate that the PD positioning was somewhat compromised compared with what was achieved in the H2 Laser Area Enclosure before transporting, installing and connecting cables. I suspect that the forces involved in connecting the cables and the weight of the cables is responsible for movement of some of the PDs. All eight array PDs and the QPD checked out electrically and with laser or flashlight light. The measured DC levels after installation and alignment (viewed from the back - terminal side of PDs) were: Upper Left: 415 mV Upper Middle Left: 475 mV Upper Middle Right: 470 mV Upper Right: 365 mV Lower Left: 395 mV Lower Middle Left: 67 mV Lower Middle Right: 565 mV Lower Right: 554 mV Pre-installation measurements are summarized in the attached plots.
Alexa, Rich Detectors ASC_AS-A and ASC_AS-B have been installed and roughly placed on the optical table in HAM6. A quick RF checkout has confirmed that they are both working as expected. Here are the details for each: ASC_AS-A Detector Serial Number:S1300634 Quadrants 2 and 3 are served by a 106 inch in-vacuum 5-way coaxial cable serial number S1301449, which connects to vacuum flange D5, subflange 2D1. This connects to air side cable 28 Quadrants 1 and 4 are served by a 106 inch in-vacuum 5-way coaxial cable serial number S1301453, which connects to vacuum flange D5, subflange 2D2. This connects to air side cable 29 The DC power is supplied to this head by a 180 inch, 25 pin D-sub cable serial number S1106833 ASC_AS-B Detector Serial Number:S1300635 Quadrants 2 and 3 are served by a 106 inch in-vacuum 5-way coaxial cable serial number S1301448, which connects to vacuum flange D5, subflange 1D1. This connects to air side cable 26 Quadrants 1 and 4 are served by a 106 inch in-vacuum 5-way coaxial cable serial number S1301451, which connects to vacuum flange D5, subflange 1D2. This connects to air side cable 27 The DC power is supplied to this head by a 180 inch, 25 pin D-sub cable serial number S1106835 Further data will be taken on the transfer functions and specifics
Daniel S., Patrick T. Daniel found the Beckhoff chassis in the CER for the IOO rotation stage switched off. We also found the cabling from it disconnected from the rotation stage interface box at our test set-up by the H1 PSL electronics racks. It looked like the cables were moved into the H1 PSL enclosure. We disconnected these cables from the chassis in the CER (to be safe, because we don't know the state of them at the other end) and switched the chassis back on. As we left it, the Beckhoff chassis is on with the IOO rotation stage cables disconnected from it.
J. Kissel, F. Clara, R. McCarthy, R. Abbott, S. Aston After discovering (last night) that the H1 OMCS transfer functions revealed an excess DC gain of 5.5, Stuart, Richard, and Filiberto identified that an incorrect breed of TOP driver for the OMCS, which was a result of an incorrect wiring diagram. Fil has now swapped in the correct driver, and I've taken transfer functions. I've finished taking all Phase 2b measurements, but not yet processed them all (aLOG to come); I post the raw transfer function data here which has the comparison to the previous measurement (and shows the coherence), just to prove the point and demonstrate victory. Of interesting note -- the OMCS TOP Driver (D1100304) has a lower transconductance, 2.026 [mA/V], that a Triple Top Driver (D1001242), 11.919 [mA/V]. Therefore, the "incorrect", Triple Top set of transfer functions have better SNR / coherence than the "correct" OMC TOP transfer functions. Who thought hard enough about the OMCS that they calculated the DAC / coil driver noise, which then convinced them to create a whole new, annoyingly different, driver type? I certainly have not seen any such design discussion. R Abbott hasn't either. This applies for the TMTS as well, which also has its own TOP driver. Hurumph.
[ChrisW, Zach]
The OMC model has been genericized and exported to LHO from LLO. Here is a summary of what was done:
All the above is committed to the SVN and has been checked out at LHO.
As I understand, there is an RCG build directory issue that is currently preventing installation, but that should be cleared up shortly.
HugoP ,GregG, JimW
Following the rebalance of HAM3 this afternoon, TFs are now running on HAM3 and ITMX ISIs. Should be done early tomorrow.
The X arm cryo pump spool was installed at GV 7. Before installation we discovered an I LIGO conical baffle in the spool which we removed. We also reconnected the annulus piping at GV 7.
Tested photodiodes in ITMX. Testing was done on feedthru E4-6-1, air side. PD forward voltage: Pin1&2: 0.409V Pin4&5: 0.422V Pin7&8: 0.423V Pin10&11: 0.423V Filiberto Clara
Crane work at End Y – Apollo Soft Cycle GV17 at End Y – Kyle ZV-800 viewport installation (HAM3) – Apollo Iluminator and camera installation (HAM3) – Jeff L./Travis Running TF on ITMx - Betsy Running TF on MC1/MC2/MC3/PRM – Betsy GV-8 soft close - Kyle Cryo Pump reinstall on X arm in LVEA – Apollo HAM3 ISI rebalance – Jim/Greg
Replaced Top Coil Drivers in SUS-C7 (U37, and U36) with OMC Coil Drivers. Wire Diagram D1002740 calls out for top coil drivers. New units were placed as follows in SUS-C7 Rack: OMC Coil Driver D1100304 - S1102659 was placed in U37 OMC Coil Driver D1100304 - S1102660 was placed in U36 Filiberto Clara
Alastair H. Greg G. Robert S. Thomas V. We were able to complete the alignment of this set of mirrors tonight. One of the 10-24 vented SHCS on the back of the SM2 mirror in BSC2 got bound up and broke at the head but we decided to move forward with the installation and were able to get the mirror secured. Although all the bolts are tightened down to their capacity on both mirrors, the alignment is still vulnerable to being bumped.
The location of the broken and the loose bolts are identified in the attached sheet (2) of the assembly drawing