Displaying reports 80041-80060 of 85743.Go to page Start 3999 4000 4001 4002 4003 4004 4005 4006 4007 End
Reports until 14:53, Monday 25 March 2013
H2 General
jodi.fauver@LIGO.ORG - posted 14:53, Monday 25 March 2013 (5878)
3IFO NSF Storage Review Prep
The NSF Storage Review will occur here on 09 April 2013. Prep work is going ahead on several fronts: LVEA-West Bay, Y Mid, and X Mid.

-In the West Bay, one section of the western-most pallet rack has been cleared of everything but 3IFO-related items. Items in this rack are currently labelled either for India or 3IFO. (2 pix below) As soon as possible, we will install a gate on this section to create a controlled inventory area. Three Triple Suspensions are stored in the Meat Locker (barrels ratchet strapped to pallets, ratchet handles zip-tied with tamper-evident serial numbered tags). (2 pix below)

-At Y Mid, a series of activities is in progress. TCS Optical Tables were stacked and rotated to create a forklift path through the outer receiving bay. This path will be continue through the middle bay to the VEA. A crane set-down/forklift turn-around area will be marked out in the yellow and black hazard tape: please DO NOT store anything in this stay-clear area. Sixteen(4 chambers-worth) iLIGO external SEI isolation units have been stored in the middle bay and VEA: they are being migrated out to the LVEA where they will be stored until they are installed on H2 HAMs. The OpLev first article test set-up is being removed and the grout pads cleared. Several 3IFO PSL crates have been identified and will be sealed ASAP: several additional PSL-related crates need to be identified. One PSL Chiller crate has been sealed with tamper-evident tape for testing purposes. Two TMS Upper Structure crates have been identified and labeled. One TMS US crate has been sealed with silver serial-numbered tamper-evident tags for testing purposes. Three unidentified crates are in the middle bay along with an electrical rack. The electrical rack needs to be de-populated and Richard will take care of that when convenient. The tentative long-term storage plan calls for all 3IFO storage at Y Mid to be in the VEA and the VEA locks will be changed to provide controlled access.

-At X Mid, a few activities will be under way this week. A forklift path will be cleared from the outer roll-up door through the middle bay to the VEA. A crane set-down/forklift turn-around area will be marked out between the inner roll-up door and the beamtube. The forlift path and the crane set-down area will be marked out in the yellow and black hazard tape: please DO NOT store anything in these stay-clear area. OpLev piers (some coming from other out buildings)will be concentrated to the VEA. Giraffe crates (already in place) and shortie crates will be sealed. The tentative long-term storage plan calls for 3IFO storage to occupy most of X Mid and outer man-door locks will be changed to provide controlled access.

The Apollo crew and I will continue to work on 3IFO LTS issues through 08 April as the opportunity arises.
Images attached to this report
H1 SEI
hugh.radkins@LIGO.ORG - posted 13:17, Monday 25 March 2013 - last comment - 13:20, Tuesday 26 March 2013(5877)
WBSC2 SEI Status--All sensors live, HEPI Floating

Jim, Mitchell & Hugh

Jim went in chamber to assist Betsy with Baffle hanging while Mitchell & I did the final dressing of the sensor cables.  We followed protocol (T1200193) to insure consistent grounding of the GS13 seismometers.  The sensor cables where then checked with the emulator to confirm good & right cables.  All checked out and then were plugged in.  All sensors now functional.

Next we checked the zeros on the HEPI Load Cells, all below 20lbs.  Continued then with HEPI loading after the horizontal locks were pulled back.  All corners now floating.  We are ready to level and elevate the ISI Optical Table in prep for IAS.

Comments related to this report
hugh.radkins@LIGO.ORG - 13:20, Tuesday 26 March 2013 (5890)

Here is an image showing the GS-13 cable attached to the Cable Bracket; it is the bottom gold one.  We remove the peek bushing that would normally isolate the cable backshell & shield.  This grounds the GS-13 in-vac shield insuring the potentially intermittent in pod ground doesn't cause problems.

Images attached to this comment
H1 SUS
betsy.weaver@LIGO.ORG - posted 11:50, Monday 25 March 2013 - last comment - 15:11, Monday 25 March 2013(5875)
BS plugged in and looks ~logical, Elliptical Baffles hung - BSC2

This morning, I hopping into the chamber and plugged in our 3 SUS 25 pin feedthru connections.  Richard turned power on to enable sus controls.  Arnaud fixed some model errors.  The BS is not suspended yet as some coarse SEI balancing and alignment is up next.

Then, Jim and I hung the 2 Elliptical Baffles from the suspension downtubes mounted on Stage 0.  The cartridge is fully payloaded now.

Comments related to this report
mark.barton@LIGO.ORG - 15:11, Monday 25 March 2013 (5879)
The model error that Betsy alludes to was spotted by Dave Barker in the course of debugging a timing error.

The M2 OSEM inputs on the BS block had been wired to  through  in the BSTST model, and when I adapted it for BS I changed them to  through  rather than the correct  through . Thus M2UL and M2LL had been doubling M1RT and M1 SD, and M2UR and M2LR had been picking up the DuoTone signal. 

The corrected model was built, installed, and committed to the SVN.
X1 SUS
jeffrey.bartlett@LIGO.ORG - posted 09:40, Monday 25 March 2013 (5874)
Second TFs of I1-MC3
   After updating incorrect matrix values in MEDM, we reran the TFs on I1-MC3. The results look much better. There are several small non-modeled peeks near or below 0Hz in the L, R, and Y DoFs and some noise in T just below 0Hz in the undamped plots. These are mostly removed from the damped plots. The comparison plots show all these non-modeled peeks are in line with similar non-modeled peek present in other suspensions. Waiting for Testing Group to review data before making any changed to I1-MC3.   
Non-image files attached to this report
H1 ISC
christopher.wipf@LIGO.ORG - posted 00:32, Monday 25 March 2013 (5873)
End Y slow controls signals jumbled
(Sheila, Max, Chris)

On Friday we uncovered a snafu with the slow controls cabling at the Y end.  The connector labels engraved on the rear panel of the "End 2" EtherCAT chassis (Exhibit A) do not agree with the chassis wiring plan (Exhibit B).  Upon opening the chassis it appeared that the internal wiring to the Beckhoff modules was done according to (B), whereas the external cable runs had been connected relying on (A).  Here's a table showing the correspondences:
PortWiring planRear panel description
6AuxiliaryDC Photodiodes
7PZT Mirrors/PDs/Laser TempAuxiliary
8TCSPZT Mirrors/PDs/Laser Temp
9RF AmplifiersTCS
10DC PhotodiodesRF Amplifiers
11LSC DemodulatorsLSC Demodulators
12Laser DiagnosticsLaser Diagnostics
This problem came to our attention after we noticed that the fiber PLL slow path (laser temperature) control output was broken. Actually it was just routed onto the wrong cable. Attached images show the interior and rear panel of the End 2 chassis at the Y end.
Images attached to this report
LHO General
patrick.thomas@LIGO.ORG - posted 19:46, Friday 22 March 2013 (5872)
plots of dust counts
Attached are plots of dust counts > .3 microns and > .5 microns in particles per cubic foot requested from 5 PM March 20 to 5 PM March 21. Also attached are plots of the modes to show when they were running/acquiring data.

Data was taken from h1nds1.
T0=13-03-21-00-00-00; Length=86400 (s)
1440.0 minutes of trend displayed
Non-image files attached to this report
LHO General
patrick.thomas@LIGO.ORG - posted 19:30, Friday 22 March 2013 (5871)
plots of dust counts
Attached are plots of dust counts > .3 microns and > .5 microns in particles per cubic foot requested from 5 PM March 21 to 5 PM March 22. Also attached are plots of the modes to show when they were running/acquiring data.

Data was taken from h1nds1.
T0=13-03-22-00-00-00; Length=86400 (s)
1440.0 minutes of trend displayed
Non-image files attached to this report
H1 SEI
hugh.radkins@LIGO.ORG - posted 17:06, Friday 22 March 2013 (5870)
WBSC2 ISI Cabling Status

All the ISI cabling has been dressed and run to the feed-thrus.  They are connected to the feedthrus; some but not all are disconnected from the sensors.  The racks are currently off.  We will perform emulation check outs before the sensors are wired and powered.  This should go quickly.  The baffles are not hung but can be now.

Please do not power on the BSC2 ISI seismometer racks.  The CPS are on but all others are off and should remain so.  A few images below for the ages.

Images attached to this report
LHO General
corey.gray@LIGO.ORG - posted 16:03, Friday 22 March 2013 (5863)
Ops DAY Summary

Day's Activities:

Baffle crew finished up their week's work in their cleanroom

Betsy heading into BSC2

PCal peeps working in H2PSL Anteroom in afternoon (Pablo, Gregario, & Craig)

Arnaud running quick measurement on ETMy at ~11:00am

rebooting model for SUS BS (Barton)

HAM2 work in afternoon (Betsy)

EY ISC work (Sheila)

SEI crew is working in and around BSC2 (Hugh, Jim, Mitch)

Alarms:

RO Alarm this morning ('Ski notified)

DUST: 

H1 PEM
corey.gray@LIGO.ORG - posted 15:51, Friday 22 March 2013 (5869)
Dust Monitor 8 MAJOR Alarm Setting Adjusted

Dust Monitor #8 = HAM2 Cleanroom (as of 3/18/13)

During my two shifts this week, I noticed this dust alarm having MAJOR alarms throughout the day, and most of the time, I'd check and see no one inside or near the cleanroom.   Generally the alarm would only last one cycle (~1min) & then clear.

The MAJOR setting was set at 200counts for 0.3um & 0.5um.  I increased it to 300counts & we'll see how it goes.  (this was done by changing values on the Alarm Settings medm window for Dust Alarm #8)

(at the moment, we have Travis & Betsy in the cleanroom working inside of HAM2 and the counts are 0.)

H1 SUS
arnaud.pele@LIGO.ORG - posted 14:57, Friday 22 March 2013 (5866)
Alignment offsets sliders range HSTS/HLTS

Mark B. Arnaud P

After Betsy realized the range of the ALIGNMENT OFFSET slider was much greater than the real actuation range (see alog entry 5852), we decided to change the max and min values of the slider for all the suspensions. For now only HSTS and HLTS medm screens have been modified. BSFM and ETM/ITM will be done after verification of the actual range.
The actuation range is limited by the DAC ouptut (2^18/2=131072), which can be transposed in urad for Pitch and Yaw. The chosen numbers can be found in the following documents (HLTS and HSTS), in the spreadsheet page 3.

https://dcc.ligo.org/DocDB/0100/T1300083/001/T1300083-v1.pdf
https://dcc.ligo.org/DocDB/0100/T1300079/001/T1300079-v1.pdf

Now the sliders go from +/- 4195 for HSTS Pitch, +/- 7828 for HSTS Yaw, +/-4409 for HLTS Pitch, and +/- 1708  for HLTS Yaw (see pictures attached)

Technical details

In order to do that :

Created two adl files in /opt/rtcds/userapps/release/sus/common/medm/hxts
SUS_CUST_HSTS_M1_OPTICALIGN.adl
SUS_CUST_HLTS_M1_OPTICALIGN.adl
copied from
SUS_CUST_HXTS_M1_OPTICALIGN.adl

opened
SUS_CUST_${HLTS/HSTS}_OVERVIEW.adl in edit mode with medm
changed the name of the argument calling the adl file from SUS_CUST_HXTS_M1_OPTICALIGN.adl to SUS_CUST_${HLTS/HSTS}_M1_OPTICALIGN.adl

opened
SUS_CUST_${HLTS/HSTS}_M1_OPTICALIGN.adl with medm

changed the range
for HLTS  
from +/-12300 urads to +/-4409 urads for PITCH
from +/-12300 urads to +/-1708 urads for YAW   

for HSTS
from +/-12300 urads to +/-4195 urads for PITCH
from +/-12300 urads to +/-7828 urads for YAW  

Modified the label above the gain from :
[DAC Counts (in EULER Basis)] into [Counts (in EULER Basis)]

svn added and commited the new and modified files in the following folder : /opt/rtcds/userapps/release/sus/common/medm/hxts

Images attached to this report
X1 SUS
andres.ramirez@LIGO.ORG - posted 13:33, Friday 22 March 2013 - last comment - 14:51, Friday 22 March 2013(5865)
Phase1b I1-MC3 TFs Results
Here are the Tfs and Spectra Test results for I1-MC3.

Non-image files attached to this report
Comments related to this report
jeffrey.bartlett@LIGO.ORG - 14:08, Friday 22 March 2013 (5867)
These plots were made using incorrect Burt settings in MEDM. We will load the correct Burt file and rerun the transfer functions. 
mark.barton@LIGO.ORG - 14:51, Friday 22 March 2013 (5868)
Further to previous, the problem was that HLTS settings had been loaded instead of HSTS ones. Thus the R, P and Y curves are shifted vertically by the square of the ratio of the respective lever arms (mostly noticeable in R and P). Allowing for that, the curves look very good, and we simply need to retake the data.
H1 SUS
mark.barton@LIGO.ORG - posted 12:50, Friday 22 March 2013 (5864)
BS safe.snap link
Betsy noticed that the BS screen was in a bad state, with gains and offsets and matrix values not filled in, despite the fact that I'd done setup on it back on 2/18 (alog 5440). It turns out it was because although I'd created 

/opt/rtcds/userapps/release/sus/h1/burtfiles/h1susbs_safe.snap

there was no symbolic link

/opt/rtcds/lho/h1/target/h1susbs/h1susbsepics/burt/safe.snap 

pointing to it. So after the various restarts between now and then it was not getting correctly restored. I created the link and checked that the correct settings were loaded when I restarted the model.
H1 AOS
gerardo.moreno@LIGO.ORG - posted 09:02, Friday 22 March 2013 (5862)
H1-ITM Elliptical Baffles

Michael V., Nichole W., Scott S., Gerardo M., Jodi F., Jim W.

Both suspensions for the ITM Elliptical baffles were installed succesfully.  Both baffle "boxes" are not installed, but they are being stored insided the beam tube for now, they can be installed at a later time.  We still need to remove a couple of loose pieces of equipment from inside chamber, such as a "table" and a "lifting" jig, they will be removed some time today.

Big thanks to the Apollo crew for their help (Scott, Chris, and Mark).

Images attached to this report
H1 ISC
sheila.dwyer@LIGO.ORG - posted 21:11, Thursday 21 March 2013 (5861)
End Y fiber PLL
Max, Sheila

We went out to the Y end and first tweaked the alignment of the beam from the fiber using a fiber laser (there is such a small amount of light coming from the PSL fiber that it is difficult to see.)  We saw a beat note easily once we had all of the cables connected correctly.  We checked that this signal gets all the way to the timing comparator, (frequency counter?) and we saw that the other input to the timing comparator is at 79.2 MHz.  However, the beckhoff channel for the beat note frequency is always 0.  

We moved on to locking, we were able to lock (using only the PZT, no temperature control) with the laser current at 1.737 and the temperature at 31.45, with a common gain of -22dB and fast gain of -4 (giving a ugf of 3.5kHz).  The OLG measured with these settings is attached, I was able to turn the gain up a bit (ugf around 10 kHz) but the lock was not very stable there.  

The next steps are to turn on the temperature control and get the frequency counter working again.  


Non-image files attached to this report
H1 ISC
rich.abbott@LIGO.ORG - posted 18:54, Thursday 21 March 2013 (5860)
ISCT1 LSC-REFL-AIR-A RFPD Signal Chain Calibration
Kiwamu, Keita, Filiberto, Rich

Finished installation of all RFPD cabling inside ISCT1.  Received LSC diode by Fedex from Caltech.  Ran through same procedure as Lisa and Matt did when they verified the calibration of the MC length diode in log entry 5277.

Data Taken on LSC-REFL-AIR-A RFPD

System Constants:
LSC Detector Serial Number - S1203919
LSC Detector Frequencies - 9 MHz and 45 MHz
LSC Detector RF Transimpedance - 341 ohms at 45 MHz
LSC Detector DC Transimpedance - 100 ohms at BNC Jack on detector body
LSC Detector Photodiode Responsivity at 980nm - 0.67 A/W
Laser Calibrator Head Serial Number - S1300150
Calibrator Output Power - 4mW at 980nm
Calibrator Head Gain - 13 mW/V (From Lisa and Matt)

Measured Parameters:
RF drive amplitude into calibrator head - 0.1Vp-p at 45.497379MHz
DC Output of RFPD Head (at BNC) - 0.165 VDC
Measured Counts of RFPD DC - 538 Counts (consistent with DC output of head and factor of two differential gain).
I and Q beat note counts - 3400 Counts p-p
Measured RF input to demodulator - 180 mV p-p at 45... MHz

Calculated Parameters:

Responsivity = 538 counts/(1638 counts/V * 200 V/A *4e-3 W) = 0.41 A/W (0.37 A/W by Lisa and Matt)

Expected RF to Demodulator = 341 V/A * 0.41 A/W * 0.013 W/V * 0.1 Vp-p = 182 mVp-p (180 mV measured)

Check of Laser Calibrator Head against LSC RFPD measured parameters:

(This calculation must correct for the amount of light that doesn't hit the RFPD diode.  This is seen in the last calculation:)

Calibrator head gain = 0.180 Vp-p / (0.67A/W * 341 V/A * 0.1 Vp-p)  = 7.9 mW/V

The incident power and observed DC photocurrent requires following correction factor:
4mW * 0.67 A/W * 100 V/A = 268 mVDC vs the actual measured 165 mVDC, therefore the correction factor of 268/165 is applied
Calibrator head gain (corrected for light spillage) = 7.9 mW/V * 268/165 = 12.8 mW/V (vs. 13 mW/V from Lisa and Matt)


Conclusion is that the LSC REFL-AIR-A RFPD and calibrator head seem to be functional within reasonable levels and is in agreement with the measurements taken by Matt and Lisa.
LHO VE
kyle.ryan@LIGO.ORG - posted 16:36, Thursday 21 March 2013 (5859)
X-end pumping started (BSC5 dome leak fixed)

The BSC5 dome leak repair effort worked (unaided annulus ion pump in equilibrium @ 8 LEDs with X-end vented) 

John W. started roughing the X-end earlier today -> I closed the safety valve then the 10" valve @1615 -> will resume pumping tomorrow
Displaying reports 80041-80060 of 85743.Go to page Start 3999 4000 4001 4002 4003 4004 4005 4006 4007 End