Displaying reports 81661-81680 of 84673.Go to page Start 4080 4081 4082 4083 4084 4085 4086 4087 4088 End
Reports until 16:03, Tuesday 12 June 2012
LHO VE
kyle.ryan@LIGO.ORG - posted 16:03, Tuesday 12 June 2012 (3101)
BSC6 annulus
BSC6 annulus at rough vacuum -> valved-in aux pump cart to BSC6 annulus @ ~1515 hrs. local.  Also, energized BSC6 annulus ion pump.
H1 FMP
jodi.fauver@LIGO.ORG - posted 15:29, Tuesday 12 June 2012 (3100)
HAM5/6 ICC
Cleanroom was moved over chambers and bolts were broken on all but one door.
H1 General
rainer.weiss@LIGO.ORG - posted 15:14, Tuesday 12 June 2012 (3097)
Comparative plot of initial and advanced LIGO BSC pumpdowns
The pdf file shows a log/log plot of the pumpdown of initial LIGO BSCs and the advanced LIGO BSC 8 in the LVEA as well
as the current one at the yend. The BSC 8 pumpdown is below the others most likely because there were several days of pumping
not accounted for before the broken feedthrough was replaced. The BSC 8 pumpdown is besides also anomolously fast. The pumpdown curve for the current advanced LIGO at the yend shows a somewhat smaller exponent n<1 P(t) ~ 1/t^n where t is the time. The areas for the yend pumpdown are:
BSC chamber = 5.2 e 5 cm^2
ISI         = 1.2 e 6
Quad        = 2.3 e 5
Transmon    = 1.6 e 5

there are two BSC chambers being pumped together one having the advanced LIGO components and the other the initial LIGO
components. The total area is 2.7 e 6 cm^2. Using the empirical Dayton relation for water outgassing, the outgassing rate
varies as J(300K) = 1.7e-7/t(hours) torr liters/sec/cm^2/hour. The predicted water vapor flow is then 4.6 e-1/t(hrs) torr liters/sec/hour.
Assuming 1500 liters/sec for the turbo pump speed, the pressure of water after 10 days is estimated as 1.3 e -6 torr. Not a hugh
amount different than an extrapolation of the data would indicate.

In summary, the slow pumpdown is unfortunately to be expected had we only put the known numbers into a calculation before hand.
The question now becomes how to best deal with this.
Non-image files attached to this report
H1 FMP
jodi.fauver@LIGO.ORG - posted 14:31, Tuesday 12 June 2012 (3095)
BSC1 ICC
Wipe down was completed early this morning and second vacuum quickly followed. Once the dust barriers were removed, Robert S. went into the chamber to access BSC3 and perform some test with regard to the black residue (the material formerly known as "re-oxidation") left from Chamber Cleaning. After lunch, the chamber inspection process was completed and FTIRs were taken. In addition, the dome was documented, welds were vacuumed and wiped,walls were vacuumed, FTIRs were taken and the dome was prepared for re-install. By about 2pm, the dome was ready to fly back to the chamber. The BSC flooring passed FTIR and is wrapped-bagged-tagged and waiting in the VPW for pick up. We expect to install the flooring and then the doors and dome tomorrow.
LHO VE
john.worden@LIGO.ORG - posted 14:25, Tuesday 12 June 2012 - last comment - 15:22, Tuesday 12 June 2012(3093)
An old BSC9 (ENDX) pumpdown - April 2000

The first pumpdown of BSC9 with the iLIGO stack.

Images attached to this report
Comments related to this report
john.worden@LIGO.ORG - 15:22, Tuesday 12 June 2012 (3098)

Same plot but longer. This shows the impact of ~2 weeks of heating by allowing the building temperature to rise to ~90F.

Images attached to this comment
H2 SUS
jeffrey.kissel@LIGO.ORG - posted 13:56, Tuesday 12 June 2012 - last comment - 12:13, Wednesday 13 June 2012(3089)
H2 SUS ETMY Lower Stage Coil Driver Noise
J. Kissel, P. Fritschel

Of interest to several on-going investigations, Peter and I took a look at the noise monitor channels for H2 SUS ETMY for the UIM (L1) and PUM (L2) stages. These signals pick off the output of each differential coil driver channel, and convert to a single ended, high-passed monitor signal, with a calibration of

Coil Output Noise [V_out/rtHz] = Noise Monitor Signal [ct/rtHz] * ADC Gain [V/ct] * Monitor Board Gain [diff. V_out/ sing. V_mon]  

where, since the high pass filter is flat by 10 Hz, we've assumed the Monitor Board is only a scale factor. Those gains are 

ADC Gain = 40 / 2^16 [V/ct]
Monitor Board Gain = 392 [Single-ended Volts Out / Differential Volts In]


According to the design studies [UIM = T0900233; PUM = T0900277], the output noise of the coil driver should be around,
 
     (Equivalent Current Noise) * (Out Resistors + Coil Impedance) = (Output Voltage Noise)
     (across the coil [A/rtHz])   (            [V/A]             )   ( [V/rtHz] (@ 10 Hz) )

UIM:         2e-12              *              7.84e3              =         1.5e-8 

PUM:       2.3e-12              *              4.42e3              =         1.0e-8


in the lowest noise modes. Note that this is what Ron Cutler calls the "component noise," which we traditionally call the "coil driver noise," or "output referred noise" the self-noise of the coil-driver due to the resistors, op-amps, etc. on the board. What he calls the "input noise specification" is the DAC noise, which is claimed to be 100 [nV/rtHz].

We see from the results attached, the results are more like 100 nV/rtHz. However, this was measured in the "acquire" modes of each driver, so we expect the noise to be basically the same as the noise input to the driver, i.e. the DAC noise, which we indeed expect to be about 100 nV/rtHz.
Non-image files attached to this report
Comments related to this report
jeffrey.kissel@LIGO.ORG - 14:19, Tuesday 12 June 2012 (3091)
J. Kissel, P. Fritschel

We've since measured the noise in the lowest noise modes,
UIM: with all low-pass (LP) filters ON (i.e. setting the UIM BIO State Request to 4.0)
PUM: with acquire (Acq) bit OFF and and low-pass (LP) ON (i.e. setting the PUM BIO State Request to 3.0)
(with both COIL/TEST Enable bits set to 1.0)

and the results are more like what's expected from the design studies

     (Measured Output Referred Noise)
     (      Lowest Noise Mode       )
     (    [V_out/rtHz] @ 10 Hz      )

UIM:             ~1.5e-8 

PUM:             ~1.5e-8 


Unlike the earlier measured noise, the input DAC noise is filtered down by some factors, so the "component noise," the self-noise of the resistors, op-amps, etc. is "exposed." 
- For the UIM, the input/DAC noise is squashed by 3 10Hz low pass filters, so the dominant noise is the coil-driver, component self noise at all frequencies (above 10 Hz). One can just barely see a little bump creeping in around 300 Hz from the DAC noise, which is from the [z:p]=[60:325] frequency response inherent to the output stage.
- For the PUM, the DAC noise is only filtered out in the region around 10-20 Hz (in the "tough" region where the SUS noise is potentially dominant in the DARM spectra), but otherwise rolls back up according to the [z:p] = [13:130] frequency response inherent to the output stage (with the Acq bit OFF), so at high frequency the output noise re-asymptotes to 100 [nV/rtHz].

A couple of other things to notice when comparing the above data with this data:
- In the UIM driver, whose output noise is dominated by DAC noise in Acq mode, and Component Noise in Low Noise mode, one can clearly see 60Hz lines in the Component Noise.
- The spikes in the PUM output noise have shifted in frequency, and are not 60 Hz lines... not sure what that means or why.
Non-image files attached to this comment
jeffrey.kissel@LIGO.ORG - 14:28, Tuesday 12 June 2012 (3094)
This data can be found committed to the SusSVN repository here:

/ligo/svncommon/SusSVN/sus/trunk/QUAD/H2/ETMY/Common/Data/
2012-06-12_H2SUSETMY_L1L2_NoiseMon.pdf [first attachment]
2012-06-12_H2SUSETMY_L1L2_NoiseMon.xml [first measurement]
2012-06-12_H2SUSETMY_L1L2_NoiseMon_LowestNoiseModes.pdf [second attachment]
2012-06-12_H2SUSETMY_L1L2_NoiseMon_LowestNoiseModes.xml [second measurement]

where the "*LowestNoiseModes.xml" has the first measurement as references.
jeffrey.kissel@LIGO.ORG - 12:13, Wednesday 13 June 2012 (3111)
J. Kissel

Another measurement for these two driver to facilitate on-going electronics studies: leaving both drivers in low noise mode (UIM: LP1, LP2, LP3 all ON; PUM: Acq OFF, LP ON), but switching between the COIL In (connected to the AI/DAC) and TEST In (assumed to be an open DB9 connector).

Attached are the results. You'll notice that there are is no change in the noise floor between the two states on the UIM driver, but for the PUM the four channels get totally different noise (from the COIL In state, and from each other).

What did we expect? It's a long story (eventually, the story will be told in L1200193), but in short:
- Each coil driver board (yes, all of them) has a equi-potential voltage reference plane to which on-board components are grounded (called "0V" on the schematic). 
- The given coil driver chassis forms a second equi-potential plane (which we'll call "ground" for now)
- The "0V" reference plane is connected internally to pin 5 of both the "COIL In" and "TEST In" DB9 connections (called "DEMANDS" and "Front Panel Test Inputs" on the schematics), as well as to several of the output pins.
- External to the chassis, the system wiring diagrams (yes, all of them) show that all of these pins are shown to be "NC" or "not connected" to cables going to and from these chassis.
- It's unclear *how* they are not connected: is the pin is shorted to the chassis, to the backshell, or maybe the cable doesn't have a pin in it's female socket ... could be any number of things.
- In the as-measured configuration of the electronics, the "COIL In" DB9 is connected to the full signal chain as shown in the system wiring diagram (D1002741); the "TEST In" DB9 is open to air (and not shown in D1002741).
- In general, the chassis "ground" is free to swing with the surrounding environment, whose changing electric field can then interact with the reference ground "0V" on the boards, and also interact with the the components on the board.
- IF and ONLY IF the differential paths are identical (which, in the real world is not possible because of component tolerances), this changing field would be common-mode to the two positive and negative paths, and cancel. 
- However, IF the paths are not perfectly the same, the common-mode surrounding field will couple differentially to the components and cause noise for various reasons.

The HOPE was that there was no such coupling between the "0V" reference plane and the "ground" plane of the chassis going on, the switch between "COIL In" and "TEST In" would merely remove the (filtered) 100 [nV/rtHz] Input DAC noise, and we could therefore measure the component, self-noise of the board at the output.

For the UIM board, the noise level remained roughly the same. We expected the noise in the "COIL In" configuration to be dominated by the component noise, so if we've "turned off" the DAC noise by switching to the TEST In configuration, we indeed expect no change. GOOD!
For the PUM board, the DAC noise was not filtered as much as the UIM board in the lowest noise mode and is therefore dominant, so we expected to see the noise on all channels to simultaneously drop to the component, self-noise noise level when switching to "TEST In." Instead we see what's shown -- each channels noise is differently elevated, and its frequency response has changed.

I don't want to make claims just yet of exactly what's happening (which is why I said "for various reasons), but the proposal L1200193 will suggest what to do next.

Weeeeeee-ew. How do you say ... l'enquête se poursuit!


Non-image files attached to this comment
LHO VE
john.worden@LIGO.ORG - posted 09:50, Tuesday 12 June 2012 (3090)
iLIGO pumpdown in 2000

This appears to be the first pumpdown of BSC10 in 2000.

Images attached to this report
H1 SUS
jeffrey.bartlett@LIGO.ORG - posted 17:11, Monday 11 June 2012 (3088)
Move HLTS PR3 to LVEA
[Jeff B, Travis S, Andres R, Gerardo2 M]

Today we moved the HLTS PR3 from the test stand in the Staging Building to the LVEA. This is the first of the Hanford Triple suspensions to be moved to the LVEA. We need to make some minor adjustments to our lifting gear for future HxTS moves, but in general, things went smoothly and with no serious problems encountered.

Gross weight of PR3, without vibration absorbers, is 210lbs. 
Images attached to this report
H1 SYS
hugh.radkins@LIGO.ORG - posted 16:50, Monday 11 June 2012 (3087)
WHAM2 E-FeedThrus Swapped
PSL had a need to access a particular feedthru for their In-Vacuum Cable runs.  Although the LHAM2 layout managed to reflect this it did not get propagated to LHO documents.  So we had to swap the feedthrus on D2 & D5.  The layout is D1002873.  Version v6 shows how we initially installed them.  In v7 there is a text file to the effect of the change but the layout itself is not yet updated.
There are two open ports now on D5 as these take 5-way Coax.  These Feedthrus are in C&B now and I hope we can get these on before the next pump down.
LHO General
corey.gray@LIGO.ORG - posted 16:17, Monday 11 June 2012 (3081)
DAY Operator Summary

Tomorrow Barker & Columbia will take H2 down for timing work

LHO VE
kyle.ryan@LIGO.ORG - posted 16:15, Monday 11 June 2012 (3086)
Swapped parts and got iLIGO RGA working at Y-end
6 days of turbo pumping, pressure @ 2x10-6 torr, scan attached.
Non-image files attached to this report
H1 FMP
jodi.fauver@LIGO.ORG - posted 14:23, Monday 11 June 2012 (3085)
HAM5/6 ICC
Work permits pulled for In-Chamber Cleaning.
H1 FMP
jodi.fauver@LIGO.ORG - posted 14:22, Monday 11 June 2012 (3084)
BSC1 ICC
First vacuum and wipe-down are complete. Second vacuum is likely to be completed by the end of the day. We expect to complete work in the dome by lunch tomorrow. We anticipate FTIR results for the permanent flooring either today or tomorrow. If all goes well, we may be out of BSC1 (including dome and door replacement) by tomorrow afternoon.
Logbook Admin General
jonathan.hanks@LIGO.ORG - posted 13:43, Monday 11 June 2012 (3083)
A RSS feed is now available for the LHO logbook
For the last several weeks we have been testing a rss feed of the alog.  It is now being moved to be a publicly exposed and advertised feature.

The feed is located at rss-feed.php.  If you are using a RSS aware browser you should be able to find the feed in whatever method your browser exports feeds.  For example in Firefox the 'Subscribe to this page...' entry of the bookmark menu becomes available.

This update is scheduled to be rolled out to the LLO logbook tonight.
LHO VE
john.worden@LIGO.ORG - posted 10:07, Monday 11 June 2012 (3082)
ENDY pumpdown

END Y after 6 days of pumping. No change in trend - suggests this is not an air leak.

Images attached to this report
X1 SUS
stuart.aston@LIGO.ORG - posted 19:33, Sunday 10 June 2012 - last comment - 16:19, Wednesday 27 June 2012(3056)
AOSEM responsivity measurements
[Stuart A, Mark B, Jeff B, Vern S]

Whilst last visiting LHO I was able to quickly make some open-light and one dimensional responsivity measurements using three dirty AOSEMs and a test-jig kindly loaned from Mark. The test-jig has previously been used for characterising BOSEMs, and so had to be reconfigured to accommodate the smaller AOSEM coilformer. More importantly, rather than using the rectangular flag employed for the BOSEM, a ~1" long x ~2 mm diameter cylindrical flag was provided by Jeff B.

A UK production Satellite Box (D0901284) was connected up to the AOSEM under test using a dirty in-vacuum quadrapuss harness (D1000234). The Satellite Box was provided with it's required supply lines via a Satellite Box Testing Board (courtesy of Filiberto). For electronics set-up please see image 504 below. A DVM was used to read-out the amplified voltage signal via the diagnostics port (J4) on the Satellite Box (Pins 9 and 28). Note that, the production Satellite Boxes have a input gain of 242k V/A or 0.242 µA/V (double-ended).

Image 506 (below) shows the opto-mechanical set-up for the reconfigured test-jig, including the translation stages and flag assembly. For these tests, only the responsivity is sought, and therefore a one-dimensional characterisation along the sensitive axis is adequate.

When connected up to the Satellite Box, each of the AOSEMs had the following open-light differential voltage measurements:-

- Unit #1, open-light = 14.75 V (i.e. an open-light photo-current of ~61 µA). Corresponds to ~24k counts
- Unit #2, open-light = 10.14 V (i.e. an open-light photo-current of ~42 µA). Corresponds to ~17k counts
- Unit #3, open-light = 12.19 V (i.e. an open-light photo-current of ~50 µA). Corresponds to ~20k counts

Over a ~0.7 mm operating range, these AOSEMs were found to have the following responsivity (see plot below):-

- Unit #1, responsivity = 18784 V/m (i.e. 78 mA/m).
- Unit #2, responsivity = 13028 V/m (i.e. 54 mA/m).
- Unit #3, responsivity = 15721 V/m (i.e. 65 mA/m).

These responsivity results can be compared with the default value we have previously assumed of ~80 mA/m (see LLO aLog entry 2715).

To summarise, these measurements can be used to validate our assumption of using the AOSEM calibration factor of, 1/(80e-3 [A/m] * 240e3 [V/A] * (2^16)/40 [cts/V]) = 3.2e-8 [ct/m], is consistent for units with open-light counts above Jeff K's goal of 25k.
Images attached to this report
Non-image files attached to this report
Comments related to this report
stuart.aston@LIGO.ORG - 07:58, Wednesday 13 June 2012 (3109)
Please find the responsivity plot showing all three units tested below.
Non-image files attached to this comment
mark.barton@LIGO.ORG - 16:19, Wednesday 27 June 2012 (3281)
Mark Barton and Szymon Steplewski

The responsivities of the three units test by Stuart have a scatter of about 18% (stdev//mean). However this scatter is dominated by a term proportional to the open light voltage (or counts). If you scale the responsivity to an effective OL count of 30000, as is routinely set in the OSEMINF block, the scatter is much reduced (to 0.6%). Therefore the number that it is useful to quote is the average of the scaled responsivities. See attached spreadsheet.

However although this data set is useful for making the above point, it was still taken with the wrong flag (2.5 mm instead of 2 mm) and so should not be considered final.
Non-image files attached to this comment
H2 ISC
alberto.stochino@LIGO.ORG - posted 10:46, Saturday 09 June 2012 - last comment - 14:06, Tuesday 12 June 2012(3079)
ALS VCO has mismatched power levels
Yesterday Keita and I found that the output of the ALS PLL Phase-Frequency Discriminator unit was noisy and oscillating between its voltage rails.
We traced the problem back to a very noisy output signal from the frequency divider which provides the LO to the P-F Discriminator board.
Going up the chain, we found that the frequency divider unit was getting 0dBm instead of the nominal 13 dBm from the VCO unit. 

Apparently the VCO unit is not working properly. We removed it from the rack and took it to the corner station for inspection.
We are going to check it inside to find the cause of the mismatched power levels.
Comments related to this report
alberto.stochino@LIGO.ORG - 14:06, Tuesday 12 June 2012 (3092)
Paul Schwinberg checked the board in the EE shop and found that the RF levels were actually correct.
It's not clear why the board was malfunctioning when Keita and I measured the levels on Friday.

We took the board to the end station and reinstalled it back into the rack.
This time the output level was okay: about +13 dBm.
Displaying reports 81661-81680 of 84673.Go to page Start 4080 4081 4082 4083 4084 4085 4086 4087 4088 End