TITLE: 05/23 Eve Shift: 2330-0500 UTC (1630-2200 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: Corey
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 9mph Gusts, 4mph 3min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.10 μm/s
QUICK SUMMARY:
IFO is in ENGINEERING and aligning
Now with all chambers vented, we are aligning cavities with the following done today and yesterday:
Continuing to align cavities until we can make it through an initial alignment (and if the stars align too, potential full IFO locking)
Camilla, TJ
I went to turn on the CO2 lasers to prep for locking today. I found both power supplies on the mechanical room mezzanine needed to have their outputs turned on. For TCSX, I then was able to turn the controller on, turn the key, hit the gate button, then turn on the laser via medm as usual. For TCSY though, the controller complained of a Flow Alarm as soon as the unit was turned on, and turning the key or hitting the gate would not clear it. The flow was reading 2.45gpm according to the paddle wheel flow meter on the floor, and before the vent we were just above 2.5gpm on the floor and 3.4gpm at the chiller. We had reduced the flow of this chiller back in December with Robert (alog81246), so I tried bumping up the flow slightly to 2.6gpm on the floor in the hopes to clear the flow alarm. Now, the flow alarm wasn't present when turning the unit on, but then when I turned the key and hit the gate button, the flow alarm came back.
At this point Camilla and I checked cable connections, tried turning the chassis off and on while waiting a bit, patting our heads while rubbing our bellies, and some other non-fruitful things. Eventually we moved the flow back up to 3.8gpm at the chiller and 2.8gpm at the floor and the flow alarm never showed up. We tried to bring the flow down a bit, but the flow alarm would return. We have no idea why the controller isn't happy with us running the flow at levels that we have been for all of 2025. For now, sorry Crab Nebula.
Richard, Jonathan, Erik, Dave:
To help the vacuum team remotey monitor HAM1's ion pump controller over the weekend pump-down, I have set up a temporary web cam, attached to a ladder and positioned close to the Varian front panel. This is a fish-eye camera, originally in the MSR and called msrcam. The camera is connected via POE ethernet to the Mech Room VAC rack ethernet switch (port 13 of sw-mech-aux , 106 VLAN). The POE injector is on the top of the rack.
Erik created a virtual FOM on cdsws12 display 5, which captures a chromium browser viewing the camera. This image updates every minute.
For timestamping, I've borrowed a wall clock from the OSB.
To ensure HAM1 VACSTAT alarms are sent to team-VAC over the weekend, I have temporarily rescinded the two-or-more-gauges rule. Any single VACSTAT alarm will sent cell phone text messages.
This is for FAMIS #26416.
Laser Status:
NPRO output power is 1.842W
AMP1 output power is 70.19W
AMP2 output power is 140.3W
NPRO watchdog is GREEN
AMP1 watchdog is GREEN
AMP2 watchdog is GREEN
PDWD watchdog is GREEN
PMC:
It has been locked 4 days, 6 hr 50 minutes
Reflected power = 23.09W
Transmitted power = 105.5W
PowerSum = 128.6W
FSS:
It has been locked for 0 days 0 hr and 14 min
TPD[V] = 0.82V
ISS:
The diffracted power is around 3.9%
Last saturation event was 0 days 3 hours and 31 minutes ago
Possible Issues:
PMC reflected power is high
On May 15, 2025, "close-out" photos were taken of everything on the new HAM1 SEI ISI Optics Table a few days before HAM1 was sealted up & pumped down. Took almost 300 photos/videos (~66Gb)! These photos/videos have been uploaded to this google drive location:
https://drive.google.com/drive/folders/1w4GwB5H2c7Dgw37FxRgLK0ganJ1nycxs?usp=sharing
Notes:
Fri May 23 10:19:34 2025 INFO: Fill completed in 19min 30secs
TITLE: 05/23 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: Ryan C
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 4mph Gusts, 1mph 3min avg
Primary useism: 0.01 μm/s
Secondary useism: 0.10 μm/s
QUICK SUMMARY:
Sheila is sorting through the state of alignment which will then lead to continuing ISCT1 alignment work out on the floor. Mitch and Randy are at EX starting on the wind fence.
Janos Today morning the pressure in HAM1 rose quite quickly to ~1E-3 Torr. As I was driving to the site, Richard found out that the new Agilent leak checker, which backed the turbo, stopped. So he valved out the turbo via its main gate valve. After arrival, I valved out the leak checker, valved in the Supersucker cart's Anest Iwata ISP500 pump, and restarted the turbo, then valved it back again. The pressure very quickly dropped to ~7E-6 Torr (roughly where it was before the incident). Since then, everything is nominal. In the afternoon around 3 pm I valved in IP13 (500 l/s Starcell) to HAM1. The pressure nicely dropped to the low E-6s, however, it started growing. I checked the controller in the MER, and found that it is unable to hold the usual -7000 Volts, in fact, it was around -3000 Volts, and dropping (towards 0). Moreover, I found that the controller's comm cable is not wired properly to CDS, its channel reads IP1/B ion pump. So I valved out the Ion-pump. With Dave, Fil, Richard, and Patrick we looked into the problem, and we quickly found that the Ion-pump's comm cable physically was not wired in at all. I quickly plugged the valved out Ion-pump to an IPC mini, which obviously hardly could hold the pressure, but the voltage still slowly converged to -7000 V. After this, I located a spare controller (brand new, identical to the one we used), also attached a bypass connector to the comm outlet, and plugged the Ion pump to this one. It quickly reached the nominal -7000 Volts. (See the new (left) and old, broken down (right) controller on the IP-controller rack in the MER). Early next week, after (hopefully) a successful leak check on HAM1, the Ion-pump will be valved in permanently. The comm cable wiring will also be finalized later.
TITLE: 05/22 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Another busy day! After some pumpdown troubleshooting this morning, ISCT1 was rolled back into place, its bellows were attached, and beam alignment on the table is ongoing. Cycled ISC_LOCK through DOWN and SDF_REVERT, but ran into an issue where ETM ESD chassis needed to be restarted after the power outage last night. I also ran a quick rotation stage calibration.
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
14:58 | FAC | Kim, Nellie | LVEA | N | Technical cleaning (Nellie out @ 16:00) | 17:12 |
14:59 | FAC | Chris | LVEA | N | Retrieving parts | 15:02 |
15:21 | VAC | Janos | LVEA | N | Troubleshooting HAM1 pumpdown | 16:01 |
15:43 | SEI | Jim | LVEA | N | Locking HAM1 HEPI | 15:53 |
15:55 | FAC | Richard | LVEA | N | Checks | 16:03 |
16:00 | AOS | Jeff | OptLab | N | Dropping off parts | 16:13 |
16:07 | SEI | Mitchell, Randy, Corey | EX | N | Wind fence work | 19:19 |
16:19 | ISC | Camilla, TJ, RyanC, Oli | LVEA | N | Moving ISCT1 into place | 17:04 |
16:27 | FAC | Janos, Chris | LVEA | N | Retrieving rigging equipment | 16:29 |
16:59 | FAC | Richard | LVEA | N | Checks | 17:09 |
17:04 | ISC | Camilla, TJ | LVEA | N | ISCT1 bellows | 17:16 |
17:16 | CDS | Fil | LVEA | N | Cabling ISCT1 | 19:59 |
18:39 | SAF | Camilla, TJ | LVEA | N | Looking for RS key | 18:47 |
19:37 | VAC | Janos | LVEA | N | Checking on HAM1 bellows | 19:46 |
20:03 | ISC | TJ | LVEA | YES | Transition to Laser HAZARD | 20:25 |
20:59 | SEI | Corey | EX | N | Wind fence work | 21:39 |
21:06 | CAL | Tony | PCalLab | Local | 21:14 | |
21:14 | ISC | Elenna | LVEA | YES | ISCT1 alignment | Ongoing |
21:16 | ISC | TJ | LVEA | YES | ISCT1 alignment | 23:26 |
21:34 | VAC | Janos | LVEA | - | Valve in ion pump to HAM1 | 22:34 |
21:40 | EE | Fil | EX | N | Checking ESD HV chassis | 22:09 |
21:41 | EE | Marc | EY | N | Checking ESD HV chassis | 22:09 |
22:18 | ISC | Sheila | LVEA | YES | ISCT1 alignment | Ongoing |
23:02 | ISC | Camilla | LVEA | YES | ISCT1 alignment | Ongoing |
After ISCT1 alignment worked wrapped up for the day, I ran a calibration sweep of the PSL rotation stage following the steps outlined in alog79596.
The measurement file, new calibration fit, and screenshot of newly accepted SDFs are attached.
Power in (W) | D | B (Minimum power angle) | C (Minimum power) | |
Old Values | 94.908 | 1.990 | -24.819 | 0.000 |
New Values | 95.252 | 1.990 | -25.787 |
0.000 |
Interestingly, even after updating the calibration factors and searching for home on the stage, there are still 2.2W into the IMC with a 2.0W request, so this may need revisiting later.
TJ, Camilla, Sheila, Elenna
We went out to ISCT1 to realign all ALS paths. The baffle align scripts were successfully run for the ITMs and TMS. I moved the BS to improve the MICH alignment. We then misaligned the ITMs and went to the table.
TJ and I were able to find both green beams and the PSL red beam coming in on the periscopes. The PSL ALS beam was mostly hitting the beamdump that Sheila and Betsy had previously put on the path, but was slightly off. TJ moved the upper periscope mirror to center the green beams and the PSL beam. We got everything pretty well placed on the periscope, and then TJ improved the lower periscope green mirror to get each beam aligned onto the prism.
Sheila and I were able to get the beam aligned for the ALS X path and saw it on the camera. We moved the diode around until we got pretty good alignment. Then, I adjusted ETMX by hand to improve both the diode flashes and the camera image. At some point I hit a wall and found that moving TMSX also helped the alignment considerably. Eventually everything was well-aligned enough that I could let the ALSX guardian run through ETM TMS WFS offloaded.
I tried doing the input align with the X arm, but couldn't get LSC TR norm flashes good enough. I had to move PR2 a lot in yaw. I also tried some moves with IM4. Gave up for the day.
Meanwhile, TJ, Camilla, and Sheila touched up the ALS Y path and the PSL ALS path. The Y arm diode and camera are now well enough aligned that we could run the ALS Y guardian.
The PSL path needs more work, and currently the beam is dumped just before the SHG.
We removed all cables belonging to the analog cameras as well as a 12V power distribution box. Removed the video feedthrough panel and replaced it with a PEM feedthrough panel that previsouly was mounted on the other side.
We removed the cables associated with the 2 original in-air WFS. Removed the 2 feedthrough panels associated with the WFS.
We de-cabled the Mad City Lab PZT steering mirror, but did not remove it yet.
(CoreyG, MitchR, RandyT)
Wind Fence News
Today Location #4 (of6) had fabric panel started it was attached above the middle (so, 3 of 5 horizontal cables were secured to this panel). The panel was then secured at this stage since the afternoon winds were beginning to pick up.
At this point we moved to location #5 (of 6) and continued attaching the big/thick horizontal cables (bottom was installed last week, so the remaining 4 were tensioned-up/installed.
Bee News
After this work was done, several NEW bee swarms were observed along the X-arm as we drove back to the Corner!
(Earlier this week an X-arm bee swarm was observed and a bee person installed a bee hive box; this box seems to be getting populated, but we did see some bees continuing to go into the Beam Tube at this location).
But today, we saw (3) NEW Swarms at the base of the Beam Tube Enclosure---their swarms appeared within 2hrs! The bees are entering at the joint between the cement enclosures. Many of the joints have holes in the cauking toward the ground and this is where the swarms were centered; as we drove back to the corner several more of these holes had smaller groups of bees investigating these holes. Mitch went to notify Richard about the situation when we got back to the Corner Station.
An apparent 10-Hz comb at 1028, 1038, 1048... Hz was spotted while updating the lines lists. The peaks are right on integer frequencies (to within a single bin in 7200s SFTs).
I took a closer look and found that it's actually a single line jumping around in the spectrum. Anybody recognize this?
The line can also be seen in H1:PEM-CS_MAG_EBAY_LSCRACK_Z_DQ. It seems like it started coupling to DARM after the O4a/b break.
Details:
History of the line in DARM:
Comparison of magnetometer and strain data (y-axis for all plots is frequency; label got cut off for some reason):
Oli, Edgard.
On Tuesday, Oli tested the SR3 OSEM calibration factors mentioned in the comments of [LHO:84296] and summarized in [LHO:84531] and took a new suite of HAM5 ISI to SR3 M1_DAMP transfer functions (the measurements also live in /HLTS/H1/Common/Data/ and are dated for May 21st of 2025).
The calibration factors from [LHO:84531] (taken on May 7th) featured a seemingly crazy change on the T1 OSEM calibration of 2.4539 x. So we wanted to doublecheck that the numbers actually made sense before proceeding with OSEM estimator work.
The measured SUSPOINT V to M1_DAMP_{ V , R , P } show that the calibration factor was largely correct.
The first attachment shows the SUSPOINT V to M1_DAMP_{ V , R , P } in measured on May 7th before using the new OSEMINF gains. In it, it can be seen that there is a very clear crouss-coupling from V to R, which is mediated by the T1 OSEM in SR3. Dividing the length-to angle over the length-to-length at 10 Hz to get a sense of the cross-coupling we get 3.3 rad/m for R and 0.65 rad/m for P.
The second attachment shows the SUSPOINT V to M1_DAMP_{ V , R , P } measured on May 21st after using the new OSEMINF gains. The V to R (and to P) improves significantly with the new calibration factors. This is best seen by comparing the relative amplitude of the V to V transfer function (in red) with the V to R (in blue), and the V to P (in green), through which we get 0.4 rad/m for R and 0.1 rad/m for P. Therefore, the apparent cross-coupling has been greatly reduced, which confirms that the T1 factor was likely correct, and we can proceed with the rest of the procedure.
[NOTE: We use relative factors for the comparison, because all OSEMs were miscalibrated by a factor of 1.3-1.4, so directly comparing the amplitudes from may 7th to May 21st would be inaccurate]
These improvements are encouraging enough that we feel comfortable moving forward with the M1 OSEM calibration for SR3. To do so, Oli is hard at work rescaling the gains of the SR3 loops. We will post when that steps is ready
As a sidenote, I ran the calibration script from [LHO:84531] on the May 21st HAM5 to SR3 data to see how stable the ISI to OSEM calibration is likely to be.
The TL;DR is that most OSEM gains are estimated to remain almost the same, the only suggested gain change above 1% is the T1 OSEM which is suggested to change by 6%, which is small enough that we will leave it alone for now. These results imply that the calibrations are good enough that they won't change by much on a weekly basis.
We will NOT adjust the SR3 M1 OSEMINF gains again with the values listed below.
This is the output of the script:
%%%%%%
We have estimated a OSEM calibration of H1 SR3 M1 using HAM5 ST1 drives from 2025-05-21_0000 (UTC).
We fit the response M1_DAMP/HAM5_SUSPOINT between 5 and 15 Hz to get a calibration in [OSEM m]/[GS13 m]
The H1:SUS-SR3_M1_OSEMINF gains at the time of measurement were:
(old) T1: 3.627
(old) T2: 1.396
(old) T3: 0.952
(old) LF: 1.302
(old) RT: 1.087
(old) SD: 1.290
The suggested (calibrated) M1 OSEMINF gains are
(new) T1: 3.435
(new) T2: 1.389
(new) T3: 0.952
(new) LF: 1.296
(new) RT: 1.088
(new) SD: 1.292
To compensate for the OSEM gain changes, we estimate that the H1:SUS-SR3_M1_DAMP loops must be changed by a factors of:
L gain = 1.002 * (old L gain)
T gain = 0.998 * (old T gain)
V gain = 1.029 * (old V gain)
R gain = 1.029 * (old R gain)
P gain = 1.003 * (old P gain)
Y gain = 1.002 * (old Y gain)
This message was generated automatically by OSEM_calibration_SR3.py on 2025-05-22 20:49:42.062366+00:00 UTC
%%%%%%
J. Kissel Now that PM1, RM1, and RM2 are safely functional on the new ISI HAM1, in the h1iopsush2b front-end model, I've - set H1:IOP-SUS_${OPTIC}_DK_BYPASS_TIME to 600 seconds H1:IOP-SEI_HAM1_DK_BYPASS_TIME - set H1:IOP-SEI_HAM1_DK_BYPASS_TIME to 999999999 (~1e9) seconds, as is seemingly common in most SWWDs - hit RESET on each of the SUS DACKILLs and the SEI DACKILL to arm them - initialized the PM1 channels in the safe.snap and accepted and monitored their current values
J. Kissel, T. Shaffer In the current O4 paradigm of SDF practice, we've minimized the number of .snap files to track by accepting the settings of some suspension whose setting don't change between "IFO down" and "Observing." That includes SUS RM1 and RM2, which live on the sushtts model -- that also now is home to PM1. RM1 and RM2 are ALIGNED at the moment, with damping loops and alignment offsets ON, and yet their settings do not show up as "different" from the safe.snap. This disagrees with the principle of "safe" but it's how we're doin it. As such, I've accepted PM1's settings in the ALIGNED state into the sushtts safe.snap.
TITLE: 05/22 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 11mph Gusts, 6mph 3min avg
Primary useism: 0.03 μm/s
Secondary useism: 0.09 μm/s
QUICK SUMMARY: HAM1 pumping continued overnight, but starting about 1.5 hours ago the pressure started rapidly climbing. No cause determined as of yet. VAC team has been contacted.
EDIT: Had the wrong channel trended, corrected in current attachment.
The gate valve on top of HAM1 was closed and the pressure is now holding; trend attached.
Note that we currently have a potentially confusing situation of two EPICS pressure channels for HAM1, only one of which is correct:
H1:VAC-LY_X0_PT100B_PRESS_TORR Is the correct channel, current value 1.3e-05
H0:VAC-LY_X0_PT100B_PRESS_TORR Is NOT the correct channel, unfortunately is misreports a better vacuum than we have, current value 1.5e-07
I went through all the vacuum MEDM screens and replaced the "H0" channels with the "H1" where ever I found them. Old MEDMs may still have the wrong value.
Vacuum FOM (nuc22) updated to new HAM1 gauge.
I've edited the caqtDM UI file for the Vacuum FOM to correct the HAM1 PT100B channel and remove the PT100A entry.
Troubleshooted, see here: aLog no. 84556