EX Ring Heater Chassis is now powered on.
We turned off the 9, 45 and 118 MHz sidebands at the rack beside the PSL enclosure.
This was to hopefully do OMC scans with no sidebands on at some time this week.
Attached are photos featuring Sheila and Georgia showing where to turn off the 9 and 45 MHz in the electronics rack on the opposite side of the PSL enclosure from the main entrance door.
You have to turn off these two amplifiers.
The second photo shows where to unplug the cable for the 118 MHz at the bottom of the rack.
Sheila, Trent, and Matt We turned the 9, 45, and 118MHz sidebands back on, and plan to rescan the OMC with these on.
WP 11742
Field cabling to SQZT8 is reconnected.
Mon Mar 04 10:09:19 2024 INFO: Fill completed in 9min 15secs
Travis confirmed a good fill curbside.
FAMIS 20018
PSL incursion last Tuesday (alog76002) explains several abnormal trends happening on that day, including the rarely-done increase in pump diode currents in AMP2.
For FAMIS #26287: All looks mostly for the last week for all site HVAC fans (see attached trends).
TITLE: 03/04 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: EARTHQUAKE
Wind: 15mph Gusts, 14mph 5min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.20 μm/s
QUICK SUMMARY:
SEI_ENV error has been fixed; issue was a typo where SEI_CONF was requested to go to the "EARTHQUAKE" instead of "EARTH_QUAKE", which is the correct (and silly) state name.
The air handling units at the corner station have been operating with many functions in a manual setting. This has taken automatic control away from the DDC system and made for inefficiencies throughout the system. After discussing with Richard, we have given automatic control back to the supply air temperature set point function as well as to the dampers to see what effect this has in terms of efficiency and temperature control of the LVEA. Because the dampers will now modulate more frequently, this will cause fluctuations in the vibrometers that will be evident in the trends. These changes in control will be evaluated over the next couple days to determine effectiveness.
Trent, Georgia, and Craig We came in to take OMC scans to determine the finesse. We wanted to take scans with the 9 and 45 MHz sidebands on and off. Setup: - Took the IMC offline and ran the dark offset scripts [/opt/rtcds/userapps/release/isc/h1/scripts/dark_offsets/dark_offsets_exe.py] - Turned on DC3 and DC4 by turning on the inputs (left on during measurements) - Turned on the OMC ASC by changing the master gain from 0 to 0.025 (left on during measurements) - Turned off the offset on OMC PZT2 - Ran an OMC scan [/ligo/home/trent.gayer/OMC_scans/2023_03_03_single_bounce_omc_scan.xml] Analysis: - Analyzed the scan with the following command [python3 /ligo/gitcommon/labutils/omc_scan/OMCscan.py 1393538828 95 "2W single bounce side bands nominal (45 @ 27.0dB, 9 @ 23.4dB)" "single bounce" --verbose --make_plots]. The data looks strange on the log scale because the signal goes negative. This script generated the first attached plot. - Added a dodgey little offset (0.001) to OMC-dcpd_sum to fix the negative numbers - We changed the duration time from 95 to 80 so that we only included 2 carrier peaks instead of 3. This helped with the peak identification which can be seen in the second attached plot. We also changed the gps time seen in the following command [python3 OMCscan.py 1393542033 80 "2W single bounce side bands nominal (45 @ 27.0dB, 9 @ 23.4dB)" "single bounce" --verbose --make_plots] What's the finesse: - To calculate the finesse we ran the file [/ligo/gitcommon/labutils/omc_scan/fit_peak.py]. We had to change variables gps_start, duration, description, mode, and num_fsr since those were hard-coded in. - We got the third attached plot from this code. - This plot gives two HWHM's, one from the data at 0.341 MHz and one from the lorentzian fit at 0.327 MHz. This gives two finesses: 388 using the data, 405 using the fit. We think that the fit is more trustworthy than the data because it uses more of the linewidth. - The variance given by curve_fit within the code is 1.16E-08. Take the square root to get the standard deviation. We estimated the error to be 0.04 No Sidebands: - We tried to find the button that turns off the 9 and 45 MHz sidebands were unsuccessful. In the meantime, we decided to just change the RF set for both sidebands to 4dBm. This is the lowest the sliders could go. - The fourth attached plot shows the signal with and without the sidebands
Sun Mar 03 10:08:56 2024 INFO: Fill completed in 8min 52secs
Now we are transitioning from winter to spring and the TC-mins have been well below -100C, I've lowered the trip temp from -60C to -90C, this is shown in the Y-cursor on the plot.
Following up the recent measurement (alog75927) the dip in the middle of the SHG sinc function seems real. SHG was locked when the data was saved and the dip in the ndscope wasn't a result of data averaging. I'm taking another set of measurements with more data points to confirm. The measurement will take about 5 hours. The start time was ~00:20.
This morning's usual conda update, which runs at 1200 UTC, seems to have uninstalled all packages from the CDS conda environment (the default environment) on opslogin0.
A re-run of the update process at 1800 UTC restored the packages.
The reason for the uninstall isn't known, and the update process reported no errors.
After a recent update to opslogin0, mentioned in this alog, some users had frequent session lock ups when changing focus or pasting text into the nomachine client.
On Friday at 2030 UTC, we reimaged opslogin0 back to Debian11 and reinstalled software.
Opslogin0 was brought back into service at about 2330 UTC.
Sat Mar 02 10:08:57 2024 INFO: Fill completed in 8min 54secs
The pressures: HAM7: ~4.55E-7 Torr HAM8: ~1.1E-6 Torr Corner: ~1.0E-7 Torr EX: ~1.3E-8 Torr Today's activities: - EX RGA was done, and it was found satisfactory - EX large ion pump (IP12) was valved in, and the pressure immediately fell to 1.3E-8 Torr from 2.2E-8 - EX further schedule: Turbo pump valve-out: 3-4; RGA scan #2: 3-4; GV20 open: 3-4 - The HAM8 RGA bakeout was ramped up, will be on throughout the weekend - The HAM7 RGA bakeout was also ramped up, and similarly stays on throughout the weekend - the bake will be finished on Monday morning - Corner & Filter cavity further schedule: Turbo pumps valve-out: 3-4; RGA scan #2: 3-4; GV5 & GV7 open: 3-4; HAM7 and HAM8 valve-in: ~3-6. Note: the bottleneck is the stabilization of the large ion-pumps. If that doesn't happen until 3-4, the opening of the GVs needs to be shifted later - GV7 all metal valve was opened, the AIP was already able to take over the pumping
Post EX Vent PCAL EndX Station Measurement
A rare Non Tuesday PCAL End station measurement was done on leap day Feb 29th 2024, the PCAL team(
Francisco L., Julian G, & Tony S.) went to EndX with Working Standard Hanford aka WSH(PS4) and took an End station measurements.
The EndX Station Measurement was carried out according to the procedure outlined in Document LIGO-T1500062-v15, Pcal End Station Power Sensor Responsivity Ratio Measurements: Procedures and Log, and was completed by 11:45 am.
Note:
After the normal measurement.
Measurement Log
First thing we did is take a picture of the beam spot before anything is touched!
We expected the beams to move due to the the vent, and it does seem like both beams have moved. It may be neccisary for us to adjuct the beams. I believe the distance between the holes on this target is 5mm center on center.
Martel:
Martel Voltage source applies voltage into the PCAL Chassis's Input 1 channel. We record the GPStimes that a -4.000V, -2.000V and a 0.000V voltage was applied to the Channel. This can be seen in Martel_Voltage_Test.png. We also did a measurement of the Martel's voltages in the PCAL lab to calculate the ADC conversion factor, which is included on the above document.
Plots while the Working Standard(PS4) is in the Transmitter Module during Inner beam being blocked, then the outer beam being block, followed by the background measurment: WS_at_TX.png.
The Inner, outer, and background measurement while WS in the Receiver Module: WS_at_RX.png.
The Inner, outer, and background measurement while RX Sphere is in the RX enclosure, which is our nominal set up without the WS in the beam path at all.: TX_RX.png.
The last picture is of the Beam spots after we had finished the measurement. I did not attempt to adjust the beam positions.
All of this data is then used to generate LHO_EndX_PD_ReportV2.pdf which is attached, and a work in progress in the form of a living document.
All of this data and Analysis has been commited to the SVN :
https://svn.ligo.caltech.edu/svn/aligocalibration/trunk/Projects/PhotonCalibrator/measurements/LHO_EndX/
PCAL Lab Responsivity Ratio Measurement:
A WSH/GSHL (PS4/PS5)FrontBack Responsivity Ratio Measurement was ran, analyzed, and pushed to the SVN.
The analysis of this measurement produces 4 PDF files which we use to vet the data for problems.
raw_voltages.pdf
avg_voltages.pdf
raw_ratios.pdf
avg_ratios.pdf
Obligitory BackFront PS4/PS5 Responsivity Ratio:
PCAL Lab Responsivity Ratio Measurement:
A WSH/GSHL (PS4/PS5)BF Responsivity Ratio measurement was ran, analyzed, and pushed to the SVN.
The analysis of this measurement produces 4 PDF files which we use to vet the data for problems.
raw_voltages2.pdf
avg_voltages2.pdf
raw_ratios2.pdf
avg_ratios2.pdf
This adventure has been brought to you by Francisco, Julian, & Tony Sanchez.
TITLE: 03/01 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
OMC measurements ongoing. RGA work throughout site today. Gate valves set to open Monday morning.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 23:29 | SAFETY | LASER SAFE | LVEA | N | The LVEA is LASER SAFE | 03:14 |
| 16:05 | FAC | Tyler | MY | N | Fire antenna upgrade | 17:34 |
| 16:14 | FAC | Karen/Kim | LVEA | N | Tech clean | 16:50 |
| 16:46 | SEI | Jim | Remote | N | ISI HAM 8 measurements | ?? |
| 16:56 | TCS | Camilla | LVEA | N | Look for parts | 17:22 |
| 17:02 | VAC | Jordan | HAM 7 | N | Increase HAM 7 RGA | 18:28 |
| 17:03 | FAC | Randy | W Bay | N | Craning | 17:41 |
| 17:42 | PCAL | Tony/Julian | PCAL Lab | Y | Measurements | 17:59 |
| 17:45 | PEM | Robert/Michael | LVEA | N | PEM checks | ?? |
| 18:47 | VAC | Gerardo/Jordan | EX | N | RGA scans | 20:34 |
| 18:54 | FAC | Randy | EY/EX | N | Boom lift for cameras | 20:54 |
| 19:00 | PCAL | Tony | PCAL Lab | Y (LOCAL) | Measurement | 20:46 |
| 19:01 | HWS | Camilla/Georgia/Craig/Swadha/Julian | Optics Lab | Y (LOCAL) | Measurement | 20:28 |
| 19:03 | SQZ | Nutsinee/Dhruva/Naoki | SQZT0 | Y (LOCAL) | SQZ work | 20:24 |
| 19:11 | PEM | Robert/Michael | MY/EY | N | PEM measurements | ?? |
| 19:33 | ISC | Sheila/Elenna/Jennie | CR | N | OMC alignment | ?? |
| 19:35 | OpLev | Fernando | LVEA/EX/EY | N | OpLev chassis work | 22:49 |
| 21:05 | SQZ | Dhruva/Camilla | SQZ tables | N | Clean up | 21:19 |
| 21:13 | VAC | Jordan | HAM 7 | N | Turn up RGA | 21:21 |
| 21:20 | SUS | Rahul | CR | N | HAM 7 TF health checks | 21:50 |
| 21:30 | FAC | Mitch | LVEA | N | Grab serial numbers | 21:38 |
| 21:58 | SQZ | Nutsinee | SQZT0 | Y (LOCAL) | SQZ work | 22:15 |
| 22:08 | VAC | Jordan/Gerardo | EX | N | Turn on ion pump | 22:59 |
| 22:11 | SQZ | Camilla/Julian/Dhruva | HAM Shack | N | Move sqz table | 22:59 |
| 23:00 | VAC | VAC team | LVEA - GV7 | N | Annulus ion pump work | 23:43 |
| 23:06 | SQZ | Dhruva/Nutsinee | CER | N | Cabling | 23:52 |
| 23:51 | PCAL | Tony | PCAL Lab | Y (LOCAL) | LLO sphere measurement | ?? |
[Sheila, Jennie, Elenna]
Here are some notes about how we by-hand improved the OMC alignment
As a final check I turned on both OMC ASC and AS WFS centering and the loops converged appropriately.
Elenna and I tried to take a single bounce OMC scan after this. We closed AS centering loops (DC3 and DC4) by turning on the inputs, closed the OMC ASC by setting the master gain up one click (I think it was at 0.25?). We turned off the offset on PZT2, and ran an old scan template. Elenna realised that we need to reset the dark offset for the DCPDs, so that's something we'll need to do next time.
We opened the OMC ASC but I think we left the centering loops closed sorry!