The TCS CO2 Y table is approximately in its new location. Unfortunately, this new location is partially off the technical slab, one leg is mostly off as seen in the first photo. While lowering the table off of the wheels one bolt sheared off, so I removed the wheel for now and moving will have to be done with a pallet jack. The new baffle hardware has also been installed with a temporary plate. The panel has a hole too large for the new hardware and this plate will be used until a new panel comes in. The next step is to install the new BSC viewport pieces and lightpipe.
I extracted the failed fiber-channel fiber FMM-10M-0018 and routed the replacement FMM-10M-0014 through the fiber tubes and cable trays. While the fiber was being replaced, the redundant routing of E18-1 to LDAS via the two Q-Logic switches resulted in no loss of connection. I also rerouted two management ethernet cables from the surplussed SATABOY to the primary controller card on both E18 RAIDS, we will activate these next week.
WP7215 Chandra, Kyle, Dave:
As per request from the vacuum group, I have added the PT114B Cold Cathode vacuum gauge (and its associated ERROR channel) to the alarm system. It is configured to alarm if its value goes above 2.0e-07 Torr (it is currently at 1.3e-08 Torr and trending downwards). Alarms will be sent to the vacuum group and myself.
Issues with Commissioning mode and issues with Science mode led me to try a new mode, which is Commissioning mode with Makup Air turned down from 100%.
Leaving it set at 40% - JeffK is watching.
J. Kissel Now that MC2 has been fixed (LHO aLOG 39382), other than PR3 (LHO aLOG 39383), all intentionally freely suspended HAM2 / HAM3 suspensions are free of rubbing at the moment: MC1, MC2, MC3, IM1, IM2, IM3, IM4, PRM, PR3. Note, PR2 still has its protective lens cap on, and likely EQ stopped so I didn't both measuring it. Data can be found commited with the 2017-11-10 date stamp in the appropriate folder of the SusSVN. /ligo/svncommon/SusSVN/sus/trunk/HSTS/H1/MC?/SAGM1/Data/*.xml /ligo/svncommon/SusSVN/sus/trunk/HSTS/H1/PRM/SAGM1/Data/*.xml /ligo/svncommon/SusSVN/sus/trunk/HLTS/H1/PR3/SAGM1/Data/*.xml /ligo/svncommon/SusSVN/sus/trunk/HAUX/H1/IM?/SAGM1/Data/*.xml
J. Kissel The only other suspension in HAM2 / HAM3 that is rubbing is PR3. As with MC2, it doesn't look too serious, because the Qs are all nice and high. Probably another grazing EQ stop or two. Black 2017-07-25_1507 pre-vent clean reference Red 2017-11-10_2044 current rubbing state Betsy has been made aware, and will address when convenient.
Problem fixed -- it was the Front HR Upper Right stop grounded on the face of the optic. See LHO aLOG 39416.
J. Kissel, B. Weaver While we waited for the PSL to figure out at what temperature it would like to be (see LHO aLOG 39371), I took top-to-top mass transfer functions of all the HAM2 / HAM3 suspensions. In doing so, I discovered that MC2 was rubbing. As such, Betsy -- while out on the floor for other reasons -- dipped in to HAM3 and found that a few of the barrel stops were grazing the optic. She backed them off, and I re-ran TFs that indeed confirmed this was the source of the rubbing. I attach screenshots of the 6 DOFs of TFs. Black 2017-08-01_1733 -- pre-vent clean reference data Blue 2017-11-10_1722 while MC2 was rubbing Red 2017-11-10_1829 after Betsy releaved the EQ stop rubbing Repeat: MC2 is now free of rubbing.
For future reference -- on the barrel stops that were rubbing the optic: two of the eight were rubbing, on opposite corners (low on one side, high on the other), but it was too dark in chamber to tell to precisely identify which ones.
Posted below are the particle count mean trends for the past 30 days. For the most part the counts are good. There are a few high counts (over 1000) spikes in HAM4 and HAM5. The HAM4 spikes are connected with the door removal. Cannot correlate the HAM5 spikes to a single event, however there was much activity around around HAM5 around this time. I could find no aLOG entries between 10-11 and 10-15 to explain the spike at BSC3 (DM #30). Cleaning around the chambers sometimes stirs up dust, which may explain these counts. That they quickly declined to normal levels indicates these events were a one time occurrence.
this is the target temperature and ISS QPDX and QPDY which tend to come back to these values when the psl is back to typical temperature.
I started to look at times when the fast shutter fired to check if there are times when more energy passed the shutter than desired (in part because of the broken beam dump in HAM6). I wrote a script that looked at about 40 days of minute trend of the AS WFS (which are behind the shutter) and picked out times when they were high. Attached are plots of the three events where the most energy seems to be getting past the shutter in those 40 days. In all of these three cases, the power on the AS_C PD doesn't seem to have exceeded the threshold for the shutter to fire until there had already been several seconds of large power fluctuations at the AS port. The shutter triggers as expected when the power goes over the threshold.
This afternoon Gerard and Koji helped me confirm that the fast shutter is cabled correctly by shining a flashlight on AS_A, AS_B, and AS_C. Indeed AS_C is connected to the fast shutter trigger.
Fil also helped me interpret the PCB layout for the transimpedance amp, I peaked inside the one for AS_C and confirmed that when looking from the front of the chassis (side where the LED is on the board) the red jumpers are on the left side, between pins 1 and 2, which means that the whitening is used. This means that the whitening is correctly compensated in the front end calibration of AS_C.
After talking with Daniel, my confusion was caused by the AS_C readback saturating in the whitening stage of the transimpendance amp. Since the sum output bypasses this whitening stage, it does not saturate and the signal readback by the beckhoff (Trigger Volts) reflects the realistic power on the PD.
So it looks like it is not really feasible to check how much energy is getting past the fast shutter using one of our HAM6 PDs. The AS WFS saturate the ADC during the lockloss transient, so they aren't very useful, and AS_C saturates the whitening stage.
Since Monday, Jason, Travis and I have been working on (amongst other things) the BS elliptical baffle rebuild and realignment. Once all parts were in hand, the rebuild was straight forward. Travis used the removed HR and AR baffle assemblies to line up and preassemble the mounting brackets so that the new baffles went in roughly where the old ones used to be positioned on the BS suspension structure. However when we put the target on the HR panel, we discovered one of GariLynn's earlier worries - the baffle was off center by many millimeters. Looking at the baffle relative to the structure seemed to indicate the same thing - the beam was left and down when looking at the HR surface target (meaning, the baffle was potentially too far up and right relative to the simulated IFO beam).
Unfortunately, this target-mounted-to-the-elliptical-baffle is what was used to align the entire BS SUS/ISI cartridge in the chamber install in ~2013, as per IAS procedure E1200795. This fact lead us to spend a day or 2 sorting out how to tell if the BS optic is misaligned in the chamber (without any IAS measurement ability), and how we possibly could have installed the elliptical baffle out on the cartridge in the first place many years ago. During this we went back in-chamber to make "precise" measurements. We used Class B rulers to measure where the IFO simulation beam was hitting the BS, how well the BS is centered in the structure, and exactly where the beam was hitting the target. Attached are actual sketches and pictures with detailed numbers.
Here's what we were able to measure to within ~1mm error since it's by-eye and other knowns:
1) The beam is hitting the center of the BS optic 2mm to the left of the optic centerline.
2) The optic is suspended in the structure to within 1mm or less of error.
3) The beam is hitting the HR target baffle 5.5 mm left of the target center.
4) Our Y-arm IFO simulator beam which runs between the ITMy center and the SR3 center ran dead center on the ITMY elliptical baffle (prior to it's removal) and the HWSY path a few weeks ago when HAM4 work was checked.
5) Per IAS procedure E1200795, the BS suspension to ISI locations were performed via more direct methods which did not involve the Baffle target, so we believe the BS to ISI mounting is correct.
Point 1) and 2) give us some confidence that the error of the BS optic placement is not as bad as how the baffle target indicates.
Some consult with GariLynn and Jenne, to understand what centering is most important from various aspects (including looking at some modeling done by Hiro in T1400055) and we have come to the conclusion that we will carry on as planned. Namely, to first order it is best to have the baffle aligned very well to the beam. Our next steps will be to recheck the IFO simulation beam pointing again, align the HR baffle to it, and take a series of pictures to ensure that the edges of the baffle are lined up correctly with the edges of the BS optic from the beam POVs.
Also during our walkabout over the last 2 days, we re-interpreted Keita's BS centering/beam clipping alog 28196, pointed out by Sheila. Because it is difficult to see the edges of the BS optic when the baffle is installed, it seems Keita made some geometrical analysis of the HR and AR baffle positions to determine the position of the BS center. However, since we believe the baffle was mounted in the wrong position by a few mm, his centering numbers likely are not correct. Still, his numbers indicate the same directions of error as we see - the beam is hitting left and low of the baffle/optic. I think we can repeat this measurement in the future by scaling the known diameters of the baffle holes and BS optic size on the camera view pictures. Will think on this more.
Attached is the sketch of the vertical beam displacement measurement at the BS HR surface we took yesterday (checked 2x). While it is good that the target position and the optic position (relative to the beam) agree, the beam is low on the both by 3.5mm. We do not understand this. More to story will come when we align more baffles, and get a peek with the PSL beam later today or tomorrow.
(Note, we re re re checked the IFO simulator AUX beam yesterday and it does not indicate any mis-centerings from ITMy center to SR3 center.)
(Jason, Travis, GariLynn via CIT, Betsy)
My link to IAS docs in the above is incorrect. The IAS doc for the baffle and BS alignment procedure is
https://dcc.ligo.org/LIGO-E1200795
Krishna
The End Station VEA temperatures are currently locked to H0:FMC-EY_VEA_AVTEMP_DEGF, which is an average of various sensors mounted to the walls of the VEA. As has been discussed before, what we'd like to hold constant is the temperature of the suspensions or the vacuum chambers. The attached plot shows various temperature sensors (refer to Jeff's alog for calibration) in the VEA which all show a rising trend (the M0 has a negative temp coefficient), whereas the FMC average sensor shows a constant trend. The reason for this is it is getting colder outside, so the walls are cooler. Therefore to keep the walls at the same temperature, the inside has to get warmer.
Robert and others had noted this for the corner station earlier and I've been told that this was fixed at the corner station but not at the end stations. I would recommend fixing this problem for both the end-stations as well. One possible solution is to simply mount the FMC sensors on or closer to the vacuum chamber.
Just wanted to show similar data for EX. Again, all temperature sensors other than the FMC sensors show the mean drift with the approach of the cold weather outside. I again urge this situation be improved by having the FMC sensors closer the chamber.
Krishna
The reconfiguring of BRS-X is complete. The new resonance frequency of BRS-X is 5.6 mHz (T ~180 s) and d is zero for all practical purposes. The BRS-X calibration filters have been modified. I have also modified the tilt-subtraction filter banks. The big change is that there is no acceleration correction for the finite d.
The pdf attachment shows the tilt-subtraction achieved under mild wind speeds of ~10-15 mph. The one noteworthy change is that the tilt-subtraction is slightly better in the 5-20 mHz frequency range, likely due to the lower resonance frequency.
I have also modified the C# code, which calculates the Beam angle, to also make an online subtraction of the reference beam angle. Previously, we did not do this since the reference beam angle noise was usually much smaller than the main Beam angle, hence it didn't help much. However, I have recently noticed that during times of excess temperature noise in the VEA, the reference beam angle noise is worse and does contribute to the main Beam angle. In order to do the subtraction (requires extra calculations), I had to reduce the update frequency of the C# code (from 140 Hz to 70 Hz). I have confirmed that this does not negatively affect the tilt-subtraction, though it does increase the high frequency noise floor slightly (by ~sqrt(2)). This code change will also be implemented at BRS-Y.
The pressure in the vacuum can (BRS_X_PumpPressure.png) is currently at ~1e-6 torr and going down steadily. The mean position (driftmon) of BRS-X was reset on Monday (see BRS_X_DriftMon.png). Acceptable range is +/- 16k counts. It seems to be stable now and I will continue monitoring.
Edit: The capacitive damper/actuator on BRS-X now works the same as that on BRS-Y. The Q is set to ~10 when the angle exceeds the high threshold (which is nominally set to 2000 = 2 micorad). Below that, the Q is set to ~100. It is time to say goodbye to the gravitational damper! It was fun while it lasted !
I adjusted the mean position yesterday after it looked like it was drifting towards the positive end. Currently it looks ok and is at ~8k counts. It's hard to judge the trend over this short stretch, especially given the temperature fluctuations of the end-stations (see 39343).
Krishna
The attached pdf file shows the comparison between BRS-Y, the ground seismometer (an STS-2) and the platform seismometer (a T240), called a PEM signal in this case (since we are using spare PEM channels for it). Also shown are the online tilt-subtracted super-sensor output (online residual) and a second tilt-subtracted signal between the T240 and BRS-Y (PEM residual). Page 2 shows the coherences between various signals and Page 3 shows the wind-speeds. As I showed before, the coherence between BRS-Y and the platform seismometer (T240) is better than that between BRS-Y and the ground seismometer (STS-2).
Note that in this plot I have used the normal calibration factor for BRS-Y and STS-2. For the T240, I matched its output to the STS-2 at the secondary microseism. You'll notice that while the STS-2 and BRS-Y are coherent below 0.1 Hz, their outputs differ by 20 percent. Initially some had suspected we got our calibration wrong, but this is now known to be due to differential floor tilt. For the online tilt-subtraction we use a factor of 0.78 for BRS-Y to correct for this. However, the platform seismometer agrees very well with the raw BRS-Y calibration (we did get our calibration right!). This confirms that the two instruments are now seeing the same tilt.
The tilt-subtracted T240 signal (PEM residual) is now marginally better than the tilt-subtracted STS-2 signal in the 15-50 mHz range. It is possible that this is still limited by temperature noise on the T240, since the tilt-subtracted noise looks similar at lower wind speeds too (not shown). Hugh will attempt to improve the thermal insulation when possible.
The most important test is to now see if the two residual curves diverge even more when wind speeds pickup above 20 mph. If so, this would confirm the differential floor tilt hypothesis. If not, it would suggest some other noise/nonlinearity limits the tilt-subtraction. Unfortunately, it looks like we'll have to wait till next week for higher wind speeds.
Adding one other case with slightly higher wind speeds.
Sheila, Jonathan, Dave:
Sheila had a question about the relative timing of an analog event which was recorded by both a front end computer and a Beckhoff slow controls computer. When looking at the two channels from the DAQ, there was a time difference of about a tenth of a second.
As a test, I have some slow signals coming from front end models and being a acquired by the DAQ through two paths: one direct alongside the fast data, and an equivalent channel coming in via the EDCU. To show the delay, I looked at the h1ioplsc0 model's state word, and manually changed it by running an excitation to set the EXC bit. In the attached plot, the signal being sent directly to the DAQ data-concentration is the upper red plot, the signal being acquired over the network via the EDCU is the lower purple plot. As can be seen, the front end data is packetized into a 1/16th block before sending to DC, which in turn packetizes the data into a 1/16 block and adds the Beckhoff data point. This results in an apparent 2 sample delay (0.125S) in the red plot. In actuality, the red plot is timed correctly, and the Beckhoff event is incorrectly time stamped as preceding the event by 0.1 S.
We think moving the EDCU to a front end would resolve this.
The use of a front-end based EDCU (instead of the DAQ Data Concentrator) is already implemented in the CDS code base. It has already been tested extensively on test stand and, and briefly on L1. There are installation instructions in the DCC. This change is required to ensure EPICS data agreement when multiple Data Concentrators are used to increase redundancy.
Subsequent inquiries concerning my alog has made me realize my entry could be made more clear. The issue is that slow data coming directly from the front end computer to the DAQ data concentrator has a pipe-line delay, whereas data being acquired by the EDCU does not. When looking at the two signals in real time mode, the EDCU signal changes first, followed 3 cycles later (0.18S) by the FEC channel. The data-concentrator takes the pipe-line delay into account by timing the signal from the FEC's time stamp (not the EPICS IOC), meaning that when this event is later replayed by opening frame files, the FEC signal has the correct time, and the EDCU signal erroneously appears to have happened before the event time.
J. Kissel Since HAM4's construction / installation stuff for this vent is complete as of yesterday's HWS Scraper Baffle install (LHO aLOG 39266), and the debugging of SR2's M2 OSEM today (LHO aLOG 39277), I took the afternoon to start B&K hammering all of the new / old baffle equipment and HWS mirror / lens mounts. Note, I deliberately skipped the SR2 cage, since nothing has changed on it since it was originally measured in LHO aLOG 12089, and I trust that Betsy and Travis successfully re-dogged and torqued bolts when they finished the relocation a few days ago LHO aLOG 39240. Will post pictures and results next week.
I'm attaching some plots of Jeff's data. Would be nice if the B&K data were easier to get into a publishable form, I can't guarantee I haven't screwed something up in here, a lot of places where it would be easy to make a mistake. Some of the TFs have almost no coherence, Jeff said it was hard to get the accelerometer close in couple cases.
One extended point about getting data from the B&K machine. It's possible to export one data set at a time (i.e. get the tf & coherence for one channel). Then to get them in a manageable format for matlab, I used sed to remove the last seven lines and the first 84 lines from the exported data txt file. This was some thing of the form:
sed -i '6486,6492d' *100-1100*.txt
to remove the last seven lines of all of Jeff's data files that had 100-1100 in the name (for the frequency band) and:
sed -i '1,84d' *.txt
to remove the first 84 lines from all of the files in the directory. Best to backup your data before doing this, cause sed won't ask if you're sure. I had to try several times to get it right. The '1,84d' tells sed to delete lines 1-84. There's probably some clever way to tell sed to remove the last seven lines, I couldn't find it, so I just looked in the file to see how many lines there were.
Attached are pictures of each setup for the above B&K hammering, in case they need to be reproduced. Jim has volunteered to process the data.