Had to power up the ESD HV supplies this morning for testing the charge on the optic. Once again one of the supplies would not stay on. As it ran through diagnostics during start up it would trip off. We replaced this unit. The next problem was the DAC cable was on the wrong connection on the AI board. This probably happened during Power board check a few weeks ago. After this was fixed had to unplug and plug back in DAC cable at ESD to clear error there. This has been seen in the past and resembles a blown chassis by railing outputs at 430Vdc. The system was then restarted and appears to be working
model restarts logged for Tue 05/Aug/2014
2014_08_05 10:16 h1hpietmy
2014_08_05 10:16 h1iopseiey
2014_08_05 10:16 h1isietmy
2014_08_05 10:20 h1iopsusey
2014_08_05 10:20 h1susetmy
2014_08_05 10:20 h1sustmsy
2014_08_05 13:02 h1fw1
Unexpected freeze of h1seiey, unexpected dolphin glitch of h1susey during recovery, unexpected h1fw1 restart.
Corner Station: Pumping continues throughout the day HAM6: Table is ready for beam Replacing feed through for fast shutter Mounting Viewport emulator on north side of chamber OpLev: Alignment on X-Arm and Y-Arm EE: Installing whitening chassis for OpLevs End-Y: Working on charging experiment End-X: Installation of Tip-Tilt equipment
Performance is another question but at least it is stable. No trips of the ISI or HEPI since before 1700pdt yesterday.
(Borja)
I have continued the coil balancing work that Jeff and Arnauld did yesterday (aLog entry 13203). In these measurements I have concentrated on SR2 and redone stage M3 (with an improved balance) and tried to balance stage M2, however in trying to do so I encountered some problem as reported on the notes attached below, it is worth noticing that tunning of the UL coil on stage M2 has no effect at all on the output signals which may indicate that the coil is actually not connected.
Summary of balancing performance:
| SUS | STAGE |
|
||||||
| SR2 |
|
|
Summary of the optimum balancing Gains:
| SUS | STAGE | OSEM | GAIN |
| SR2 | M2 | UL | 1 |
| LL | -1.95 | ||
| UR | -1.26 | ||
| LR | 0.09 | ||
| M3 | UL | 0.976 | |
| LL | -1.1 | ||
| UR | -1.005 | ||
| LR | 0.963 |
Apollo installing viewport gatevalves on H1 BSC chambers in LVEA for ionizer equipment 09:03 Nathan starting unattended laser work in the optics lab 09:12 Hugh to HAM4 to remove ameristat and unlock HEPI 09:18 end Y transitioned to laser safe 09:32 Jeff B. and Andres to HAM6, contamination control check 09:41 Travis checking on mobility experiment on west door of HAM3 09:46 Jim B. to check on SEI IOP (unexpected shutdown at 8:41) 09:47 Betsy picking up equipment in LVEA 10:13 Dave and Jim B. restarting end Y SEI, will take down end Y ISC and SUS (on same Dolphin network) 10:16 Hugh done unlocking HEPI 10:39 Dave and Jim B. restarted the mid X weather station 10:56 Sheila to IOT2L, if it has been moved into place will install light pipes 11:00 Bubba to end X to retrieve part for door removal 11:00 Jordan, Paul and Sudarsham to Y1 beam tube enclosure, accelerometer measurements 11:08 Jason and Doug to begin alignment of ITMX optical lever, Arnaud to put ITMX mirror into nominal position 11:18 SnoValley to see John W. 11:34 Paradise water delivery 11:34 starting HAM6 door removal 11:43 Peter K. to end Y to take pictures through viewport 12:03 Krishna, Eric and Jeff K. to end X to work on BRS 13:08 Christina to end X and end Y to install magnetometers 13:12 Aaron to start drilling in the old H1 PSL chiller room (WP 4777) 13:39 Paul and Jordan to end X for PEM measurements 13:57 Dan and Koji to HAM6 to install fast shutter 14:17 Gerardo, Rai and Kyle working on ionizer experiment at end Y 15:43 Fire department investigating trouble panel alarm at mid Y 16:45 Nathan supervised by Dick G. in optics lab Maintenance tasks: PSL chiller filled yesterday, left alone reset HEPI overflow counters for HAM3, BS. John W. confirmed work was done regarding this alog. I set HVE-MY:Y5_246BTORR.HIHI back to 5e-08.
WP 4776 I stopped conlog 1.3 on h1conlog at 17:26 PDT. I ran the script to create a new channel list and started conlog 2.0 on h1conlog2 with it. The database is being replicated to a read only copy on h1conlog3. The web search interface can currently be accessed from an internal CDS machine at http://h1conlog3. I am in the process of creating a backup of the 1.3 database.
Jeff K., Krishna V., Erik S. Today we started with the assembly of the left arm of the vacuum can. The older flexures on the balance were damaged during transport so we replaced them with another pair Krishna had brought. We then inserted the balance into the 6-way cross and suspended it successfully. We were then adjusting masses on the balance to lower the resonance frequency close to 10 mHz. By the end of the day we got the frequency close to 20 mHz. Pictures of the assembly process attached in assembly order!
Will resume attended rough pumping of Vertex, XBM and YBM combined volumes tomorrow
Alexa, Sheila
We saw that there was no signal on the PSL periscope PD, so we entered the PSL to investigate. There is currently 170mW of light entering the periscope, and 0.7uW incident on the PD. We measured the voltage from the PD using an osciliscope, it has a 13 mV offset and 4 mV of signal. (both negative) This gives 0.38A/W, (we did not change the gain switch, so the gain setting should still be 15kOhms), and the pick off ratio (power on PD/power into HAM1) is 0.004. These are not so different from the measurement Paul reported in alog 9865 We will stick with the old calibration which was made with more light on the diode.
We did not finish checking the calibration of this PD because there is also a problem with beckhoff. Everything on corner chassis 3, 4, 5, and 6 is NO_COMM. The problem with beckhoff was fixed by unplugging and reconnecting the cable between Corner Chassis 2+3, which could be a bad cable that needs to be replaced.
[Dan Koji]
A first fast shutter was placed at the approximate location on the HAM6 table. The cable has been connected to the shutter.
The feedthru end of the cable is waiting for replacement of a 2.75" feedthru flange. This flange is D3-3 according to D1002877.
The table space is really tight. The space for the shutter was just barely OK to place it behind OM3. It yet needs precise aligment.
The path for the (expected) reflected beam from the shutter was cleared by moving the beam dump for ASAIR beam diverter
The golden beam dump was installed at the edge of the table. This was realized by moving the cable post for the beam diverter.
Discussions with MIT (RichM) and looking closer at the very controllers & filters I plotted showed the problem.
While the developed controller I showed in the SEI Log, looked like it should not have been terrible at dealing with the potential instability at 8hz, the filter I posted in the LHO alog, was in fact a design unable to deal with this problem with strong peaking and marginal phase room at 8hz. Once I realized these two views of the ETMY controller could not be the same, I knew somewhere the problem was twisted. So I painstakingly went through all the filter design steps and sure enough, the design was there but was not saved correctly or prepared properly. The Blue traces are the new X controller in the attached for ETMY while the Red traces are from the ITMX which is how ETMY appeared before.
There is of course no free lunch and if I understand and can explain (mostly for my own benefit). The large phase bump in the 8ish Hz area pulls the controller away from instability and the design inherently has less gain peaking (maybe that is the same thing.) On the other hand, if the zero in the plant (which can move around) moves away from this design point and/or the designer is too aggressive at matching the plant, the controller will develop something... (gain peaking?)
At the moment, ETMY is running under full Guardian Management in FULLY_ISOLATED. Don't want to get ahead of myself but it has been almost 15 minutes now and Rai & Gerardo are still down there working on the chamber. I have had one previous trip of the ISI for L4Cs but HEPI did not trip. So, at least we are in a new epoch for BSC10 HEPI.
Summary : We tested charging/deionizing of the unsuspended, isolated ITMY (Corning ETM02) with a new electrometer, the Alphalab Ultrastable Surface DC Voltmeter. We first measured the field at the HR surface of the optic interleaving a series of timed deionization runs with the TopGun Deionizer. Next we applied and ripped FirstContact, and repeated measurements/TopGun nitrogen deionization. The deionization process appeared to take several minutes, having some effect out to nine minutes - however we have to repeat the measurement to assess charge on the barrel and AR optic surface (G. Moreno, N. Robertson, M. Landry, with C. Torrie and R. Abbott).
Details :
We set ETM02 (recently employed in BSC8/1 as the pilot ITMY for single-arm/HIFO experiments) upright on a teflon V-block in a cleanroom of the west bay of the LVEA ("fiber welding cleanroom"). We made measurements of the electric field 1" from the center of HR surface of the optic, and four measurements halfway between the center and the limb of the optic (right, top, left, bottom). Initially we simply applied the TopGun nitrogen in a series of 3 minute applications. Later we applied FirstContact, let it dry overnight, and the pulled (with concurrent TopGun dionization), and made more field measurements interleaved with de-charging. The data are below.
All values in negative kiloVolts (-kV) as read from the hand-held meter, unless otherwise signed positive. Field values in kV/m can be obtained by scaling by ~30X.
| Trial | Vc | Vr | Vt | Vl | Vb |
| 1 | 2.4 | 2.7 | 3.2 | 2.7 | 2.6 |
| 2 | 2.2 | 2.2 | 2.4 | 2.3 | 1.8 |
| 3 | 0.11 | 0.14 | 0.10 | 0.15 | 0.10 |
| 4 | 0.02 | 0.05 | 0.035 | 0.03 | 0.03 |
| 5 | 0.02 | 0.035 | 0.01 | 0.03 | 0.035 |
| 6 | 0.005 | 0.005 | +0.020 | 0.025 | 0.015 |
| 7 | 0.150 | 0.70 | 0.03 | 0.160 | 0.11 |
| 8 | 0.108 | 0.130 | 0.045 | 0.23 | 0.05 |
| 9 | 0.01 | +0.01 | 0.035 | 0.08 | 0.01 |
where
Vc = raw voltage (kV) 1" above center of HR surface
Vr = raw voltage (kV) 1" above center-right (i.e. at a radius of +34cm/2, 0 degrees rotation angle) of HR surface
Vt = raw voltage (kV) 1" above center-top (i.e. at a radius of +34cm/2, 90 degrees rotation angle) of HR surface
Vl = raw voltage (kV) 1" above center-left (i.e. at a radius of +34cm/2, 180 degrees rotation angle) of HR surface
Vb = raw voltage (kV) 1" above center-bottom (i.e. at a radius of +34cm/2, 270 degrees rotation angle) of HR surface
and trial data were taken under the following conditions:
Trial 1 - Initial measure of electric field, HR side of optic, prior to application of FirstContact (FC), or TopGun deionizer (TG)
Trial 2 - same as trial 1, but 24 hours later, to see if there is some discharge in air (there is, ~25% lower than trial 1)
Trial 3 - After 3 min of TG deionization
Trial 4 - After 3 min of additional TG (6 min total)
Trial 5 - After 3 min of additional TG (9 min total)
Trial 6 - No additional TG, but after 3h delay
Trial 7 - FirstContact applied, then removed in a 2 min pull, with concurrent TG (2 min), plus additional 2 min TG thereafter
Trial 8 - After 2 min of additional TG (6 min total)
Trial 9 - After 3 min of additional TG (9 min total)
Individual measurements of the field could take 3-4 minutes to stabilize in the Voltmeter, i.e. values read out on the hand-held unit may have initially read hundreds of volts, falling and stabilizing to a seemingly stable number over the 3-4 minute time frame.
We wil repeat these measurements and include barrel and AR surface tests. However, in consultation with C. Torrie and R. Abbott, and in order to be conservative in closing BSCs 1, 3 and 9, we opted to extend nominal few-minute TopGun blowing times for test masses and reaction masses to nine minutes total, i.e. 4.5 min for a given test mass HR face, 4.5 min for the AR gap, 4.5 min for the reaction mass upstream face, 4.5 min for the gap. We cycled between surfaces and gap in 1 minute intervals, summing to 9 min per optic.
While doing cabling for HAM6 in the CER, noticed that the following cables for ISCT1 in ISC-C2 were plugged in backwards. Swapped the following at the EtherCAT Corner 5 Chassis. Cables are connected as listed below and match the pull list E12000408. Cable_ISC_328 connected to Port 9 (DC PD's ISCT1) Cable_ISC_326 connected to Port 10 (Auxiliary ISCT1) Filiberto Clara
(Sheila, Alexa)
After fixing the corner beckhoff, we noticed that the PSL persicope PD was still not reading the correct voltage based on yesterday's measurement alog 13222. It turns out that swapping back cable ISC_326 and ISC_328 fixes this problem.
As desgined from D1100583, E1200077:
The Auxiliary ISCT1 cable ISC_326 from Concentrator 1 --> EtherCat Corner Chassis slot 10
DCPDs ISCT1 cable ISC_328 from Concentrator 2 --> EtherCat Corner Chassis slot 9 --> System Manager L9-10 EL3104 Adapter 9
The System manager is linked according to the specification above. However, with the proper configuration the readback was not connected. Maybe it's an internal swap in the EtherCat Chassis? We have flipped the cables at the concentrator.
Current Configuration:
The Auxiliary ISCT1 cable ISC_328 from Concentrator 1 --> EtherCat Corner Chassis slot 9
DCPDs ISCT1 cable ISC_326 from Concentrator 2 --> EtherCat Corner Chassis slot 10 --> System Manager L9-10 EL3104 Adapter 9
I have updated the MEDM screens which are snapshotted and displayed on the web page:
https://lhocds.ligo-wa.caltech.edu/screens/
[Jeff Arnaud]
Tonight we balanced the coils of the lower stages of MC2 SRM and SR2. The MC2 notes attached are explaining the procedure in detail. Below is summarized the ASD ratio after/before the exercise for each suspension and each level.
For some reason M3 stage of SR2 was harder to balance than the other ones, so we gave up on it for now and will come back to it later.
| SUS | STAGE | ASD RATIO before/after balancing | |
| PITCH | YAW | ||
| MC2 | M2 | 19.71 | 2.63 |
| M3 | 21.27 | 13.52 | |
| SRM | M2 | 9.95 | 38.53 |
| M3 | 6.96 | 3.8 | |
| SR2 | M2 | ||
| M3 | 107.7 | 5.12 | |
And the gains which were found optimum for each coils
| SUS | STAGE | OSEM | GAIN |
| MC2 | M2 | UL | 0.988 |
| LL | -0.992 | ||
| UR | -1.007 | ||
| LR | 1.012 | ||
| M3 | UL | 1.082 | |
| LL | -0.948 | ||
| UR | -1.051 | ||
| LR | 0.922 | ||
| SRM | M2 | UL | 0.935 |
| LL | -1.024 | ||
| UR | -0.971 | ||
| LR | 1.063 | ||
| M3 | UL | 0.972 | |
| LL | -1.014 | ||
| UR | -0.972 | ||
| LR | 0.964 | ||
| SR2 | M2 | UL | |
| LL | |||
| UR | |||
| LR | |||
| M3 | UL | 1.003 | |
| LL | -1.050 | ||
| UR | -0.951 | ||
| LR | 0.996 |
Measurements will be running overnight to measure the cross couplings transfer functions for SR2 SRM and MC2
There is a discrepancy in the text. While it says that SR2 M3 was not balanced however in the results table it is SR2 M2 the one blank. I can confirm that SR2 M2 is the one not yet balanced.
This plot is interesting. It seems the only moderately pronounced peak in the horizontal ground spectrum wanders, seen from 8 to 11hz changing quite rapidly.
The attached plot's current traces are with HEPI loops closed and the ISI Damped. While the middle graph shows all four local IPSs have the strong 8hz peak (the dashed REFs are with the HEPI loops open), the peak only shows in the X & Y and not the RZ cartesian traces (top graph). Also, note the bottom graph where the ground sensor pretty much has nothing at 8hz but does have a minor peak just above 9hz that is also peaking up in the local sensors.
The second plot shows just the ground Seismometer with X & Y traces from last night (Dashed) and the others from this morning. The peaks in that area come and go and wander around so it may or may not be a problem or just a red herring (are those edible?)
I am attaching the spectrograms for the X, Y, and Z directions of the STS Seismometer in ETMY. I used 19 continuing hours, starting 2014-07-22 01:00:00 UTC. There is a feature that is present all the 19 hours: Around 10.5 Hz in X direction. Around 9 Hz in Y direction. Around 10.5 Hz in Z direction. More features can be seen wandering along the 19 hours around 3-5 Hz and 8-10 Hz, for X, Y, and Z directions. In the spectrograms, each count is 1 nm/s /sqrt(Hz).
Continuing with the investigation on the 8 Hz, I am attaching the spectrograms for the X, Y, and Z directions of the GND STS in EY. Comments on the spectrograms: - Feature wanders between 7.5 to 12.5 Hz. - Depends on the time of the day. - It is present every 15 to 30 minutes. - Displacement amplitude higher than 2 nm. 6 hrs were used for each spectrogram, starting: - August 01, 2014 00:00:00 UTC (Figure 1) - August 01, 2014 06:00:00 UTC (Figure 2)
The 8 hz motion seen here is most likely related to the "pier resonance" Laura Nutall has a nice set of plots in the DCC https://dcc.ligo.org//LIGO-G1400820 which show this motion. Likely you are seeing the floor component of this motion. Rich M. has data showing that (at MIT) the slab bending is an important component of this motion
I investigated the GND SDS and PEM MIC channels using the coherence tool at 100mHz bandwidth and found several peaks between 5 and 9 Hz. I've attached some slides with zoomed-in plots.
This morning after Jim locked the BSC1 ISI, I applied First Contact to the ITMy CP-AR surface via the spray cone technique. We then made final preps to the SUS locking down nuts, closing the ring heater, etc.
Particle counts in chamber before we started, but after Mitch had walked through for access to the X-spool ~an hour earlier:
0.3um 30
0.5um 10
1.0um 10
Particle counts after FC spraying was done, taken nearish door ~10 mins after spraying complete, 3 people working in chamber:
0.3um 840
0.5um 430
1.0um 260
Greg also looked at the TCS mirrors in BSC2 while we were there - more from him later I suspect.
We wiped our way out of BSC2 and BSC1.
I then went into BSC3 and wiped the floor.
We broke for lunch.
After lunch we used the N2 gun and removed the FC from the CPx-AR and ITMx-HR. We then alternated blowing on the ITMx-HR and gap between optics for 1 min intervals until each set of surfaces had seen ~5min of N2 deionization at 10psi. I blew the barrels a little while as well.
After unclamping the TM and CP, we set the 1" witness optic and the 3" witness plate on the QUAD SUS and 1 3" WP horizontally on the floor in the center of the chamber. A quick check of TFs in V, P, and T showed a healthy suspension, so we closed the BSC3 door.
Moving down to BSC2, we pulled the FC on the BS-AR. It tore across the top and then as we pulled it down across the optic it left 2 ~2mm chunks of FC in the center ~4 inches of the optic. We determined that we would need to respray clean this surface (phiszzll) so we aborted the BSC2 and BSC1 chamber closeout.
We pulled the BS-HR FC to make sure it wouldn't leave anything else either.
Jim locked the BSC2 ISI again and we mounted the FC spray cone to respray FC on the BS-AR and HR surfaces. We reinforced the edges of the sheets with paint-on FC as usual. Tomorrow we will reattempt to pull the BS and ITMx FC sheets and move on to close these chambers.
Time of FC pull on ITMx was ~1:30. Door was attached at ~2:00. The BSC1 door is still off however.
During this spray-on First Contact reapplication of the BSC2 BS-HR and AR surfaces, the particle counts in the neighboring BSC1 chamber climbed to:
0.3um 34,440
0.5um 11,970
1.0um 4,696
sorry, wrong date. Should be Tuesday 5th August.