Displaying reports 74001-74020 of 76956.Go to page Start 3697 3698 3699 3700 3701 3702 3703 3704 3705 End
Reports until 22:45, Tuesday 05 June 2012
H2 CDS
david.barker@LIGO.ORG - posted 22:45, Tuesday 05 June 2012 (3041)
FMY one stop cable change, still running after 10 hours
The latest change to h2susb78 (FMY front end) was to swap out the one-stop PCI bus extender fiber optics cable between the IO Chassis and the computer. The IOP was restarted at noon, it is still running after 10.75 hrs.
LHO General
patrick.thomas@LIGO.ORG - posted 18:07, Tuesday 05 June 2012 (3040)
plots of dust counts
Attached are plots of dust counts > .5 microns.
Non-image files attached to this report
LHO General
jonathan.berliner@LIGO.ORG - posted 18:00, Tuesday 05 June 2012 (3039)
Tuesday Ops Log
- BSC1: moving garbing room, setting up lazy susan. Cheryl de-installed ITMY, preparing it to be sent to KAGRA. ICC will commence from north side of biergarten.
- BSC6: Long pump-down begins today, with Gerardo leading.
- Praxair delivery for CP6 and CP8.
- Electrical contractor working on DC power supplies at EY.
- FMY electronics still misbehaving...Richard addressing.
- Apollo grouting at H2 input, HAM7, MC legs.
- PSL working on controls, DAQ.
- Platt Electric makes delivery for Richard.
- One Apollo delivery in the afternoon.
- Transit of Venus broadcast in Control Room. Some visitors on site expected for LHO's special event. Unfortunately, the sky was overcast for the entire day, so the sun was not visible at LHO as of 18:00. Check back here on 8 Dec 2125, LHO's next chance.
- OSB doors locked at 16:45.
LHO VE
kyle.ryan@LIGO.ORG - posted 15:55, Tuesday 05 June 2012 (3038)
Y-end switched over to Turbo pumping - Also, water condensate in QDP80 exhaust
I noticed condensed water vapor collecting at the exhaust of the QDP80 -> My measuring of the purge air dew-point prior to pumping yesterday was of the air exhausting into the room from the check valve (acting as a point-of-use pressure relief).  This had been the nominal procedure until recent years after we had observed that the purge air drying towers could be "starved" in a maximum demand case, such as full-open purge air valves in conjunction with one or more chamber doors being removed.  We found then that the measured dew-point of air sourced only from the VE (during pressure equalization "blow-down" prior to pump-down) could be different than that of the air sourced only from the purge air header.  This could result from those scenarios where the drying towers were starved at the time that the door(s) were reinstalled.  Once the doors are installed, there is minimal air exchange between the relative "wet" air in the VE and the relatively "dry" air that the, now not-starved drying towers, were supplying to the header.  

This has not been observed at the Corner Station as we haven't been able to "starve" the drying towers with nominal purge air demands.  

We intended to make it standard practice to measure the dew-point of the air exhausting into the room during the "blow-down" step when preparing to pump down a -mid or -end volume.  
LHO VE
john.worden@LIGO.ORG - posted 15:09, Tuesday 05 June 2012 (3037)
test

See if I can post a plot......

Images attached to this report
LHO General
patrick.thomas@LIGO.ORG - posted 18:40, Monday 04 June 2012 (3033)
plots of dust counts
Attached are plots of dust counts > .5 microns.
Non-image files attached to this report
H1 SEI
hugo.paris@LIGO.ORG - posted 17:44, Monday 04 June 2012 (3028)
HAM2 - Actuator Ground Check

Hugh, Hugo,

LLO observed grounding issues with actuators on HAM-ISIs (see LLO aLog #2890) . Actuator cables have their shielding covered by a fairly large mesh. If the cable is pinched against a wall, or set in tight contact with a CPS sheild (which is grounded to the ISI), the actuator gets grounded to the ISI.

We checked the grounding status of all actuators of HAM-ISI Unit #4 (HAM2 Chamber) by testing the continuity between the shielding pin of the actuator cable and the ISI. Even though most actuator cables are tied with CPS shields (picture 1), no actuator were grounded to the ISI on this unit.

We also noticed remains of aluminium bands at the connection between the actuator and its cable, that we removed. To do so, we had to open the door of Act-H1 (picture 2). This door still has to be torqued down with a torque wrench. It will be taken care of tomorrow.

Images attached to this report
H1 DAQ
david.barker@LIGO.ORG - posted 16:49, Monday 04 June 2012 (3032)
DAQ restarted to resync all DAQ systems
I restarted H1 DAQ, now h1fw0 and h1fw1 are writing identical frames.
H2 CDS
david.barker@LIGO.ORG - posted 16:48, Monday 04 June 2012 (3031)
More testing on FMY front end
h2susb78 (FMY) remains unstable. We have been making incremental changes to pin down the problem:

Reattached to Dolphin network

only run the IOP model

reseat all ADC/DAC cards

rearrange ADC/DAC cards to LHO CDS standard (ref Rolf's IO Chassis document)

We have been stable for 2.5 hours with the latest configuration: Dolphin attached, IOP model only, LHO-CDS card layout. Will run with this overnight.
LHO VE
kyle.ryan@LIGO.ORG - posted 16:38, Monday 04 June 2012 (3030)
Y-end pumping misc.
Kyle
Purge air dewpoint measured <-35C now that doors and dome have been on for a few days and the flow demand is low enough for the drying towers to be effective (found pressure relief valve for scroll compressor #2 is stuck open and won't re-seat -> valved-out output of compressor #2 and de-energized it).  

Began pumping Y-end this morning.  

Kyle
~1600 hrs local 
Y-end pressure at 2.8 torr, going home now -> Closed O-ring valve at Turbo header, closed 10" gate valve at MTP inlet, switched safety valve switch to "Closed" position to close the safety valve, cracked open valve between Purge Air header and Turbo header to let the QDP80 pump a slight viscous load overnight. 

Will restore roughing configuration in the morning then switch over to MTP when pressure low enough.
H2 SEI
filiberto.clara@LIGO.ORG - posted 16:34, Monday 04 June 2012 - last comment - 10:44, Tuesday 05 June 2012(3029)
Modifications to HEPI Pier Interface Module (D080521) - BSC6
Powered down HEPI valve drive chassis and ±24V power going to HEPI Interface modules. Replaced R13 from a 2 KOhm resistor to a 33.2K Ohm resistor on D080521 units. This changes the gain of the L4C channels from 22 to 333, per document E1200420-v1. Tested units after mods, gain ~330. Serial Numbers of units modified: S0900178, S0900236, S0900202, and S0900234. Will reinstall units tomorrow morning.
Comments related to this report
filiberto.clara@LIGO.ORG - 10:44, Tuesday 05 June 2012 (3035)
All units reinstalled and powered up.
X1 SEI
corey.gray@LIGO.ORG - posted 16:00, Monday 04 June 2012 (3025)
HAM ISI Assembly Work

(corey, eric, greg, hugo, jim, mitch)

#6

Now that we had some hardware processsed, we were able to continue building up Actuators.

#7

Stiffener Assembly completed.  The Support Posts were installed (discovered we were missing a Gang Barrel Nut [it was in our "dirty" bin]); will want to get it processed before we pull down springs.

Stage0 Assembly moved to Test Stand.

Stage1 plate put on Assembly Stand.

Images attached to this report
X1 SEI
hugo.paris@LIGO.ORG - posted 13:28, Monday 04 June 2012 - last comment - 11:27, Tuesday 05 June 2012(3026)
HAM-ISI - L4C huddle test at reception - Shipment #3880

The set of 6 horizontal L4Cs received in shipment load #3880 were huddle tested this morning, 

We noted a few points that we need to be careful about in order to perform this test correctly:

Spectra are attached.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 14:51, Monday 04 June 2012 (3027)

Attached is a photo of the lined-up L4C set up.

Images attached to this comment
hugo.paris@LIGO.ORG - 11:27, Tuesday 05 June 2012 (3036)
H1 INS
jodi.fauver@LIGO.ORG - posted 08:04, Monday 04 June 2012 (3023)
BSC1 ICC-HAM2 ISI Install Prep
On Friday, after spending some time with Hugh, Bubba and I made a brief checklist (See below) to coordinate our efforts in the BSC1-HAM2 area.

1. Friday pm
     -Second cleaning BSC1
2. Friday pm
     -Move A-frames and I-beams to HAM 2 area
3. Monday am
     -Move cleanroom from HAM4 to HAM5
     -Remove doors and dome from BSC1
     -Stage Optics extract equipment at BSC1 South
     -Install SEI Soft Roof and adjust cleanroom location at HAM2
4. Tuesday am
     -Move Garbing/Staging cleanroom from HAM2 to BSC1 South
     -Optics de-install BSC1 (Lead: Cheryl, Apollo help)
     -Move Garbing/Staging cleanroom from BSC1 to HAM2
5. Tuesday pm
     -BSC1 ISI de-install (Contact Dale)
6. Wednesday am
     -Set up A-frames, etc at HAM2 
7. Wednesday pm
     -Install HAM2 ISI



H2 SUS
jeffrey.garcia@LIGO.ORG - posted 22:41, Sunday 03 June 2012 (3022)
H2 SUS ETMY M0 R0 TFs before BSC 6 chamber close-out
The attached are the latest M0/R0 transfer function measurements on H2SUSETMY taken on the night of 06/02/2012.  Both chains appear to have no sign of rubbing and have most of their resonances coinciding with the predicted model.  The R0 chain appears to have a cross-coupled resonance in the Longitudinal DoF, but otherwise a very clean measurement.  This measurement suggests the top masses on H2SUSETMY are free-swinging without obstructing forces.  H2SUSETMY is ready for the BSC 6 pump-down. 
Non-image files attached to this report
H1 DAQ
david.barker@LIGO.ORG - posted 18:03, Friday 01 June 2012 (3021)
H1 frame writer h1fw0 up and running
Dan, Jim and Dave

We have built up the primary H1 frame writer system, which consists of

Sataboy QFS file system in LDAS server room.
Solaris QFS writer in MSR room.
h1fw0 frame writer, on the 10GigE DAQ network and writing to the solaris box over a private 1GigE NFS link.

h1fw0 is writing frames which are identical to h1fw1.
H2 ISC
keita.kawabe@LIGO.ORG - posted 15:34, Wednesday 30 May 2012 - last comment - 10:37, Monday 04 June 2012(2985)
Note to self: Serial number of the broken channel in AI chassis

D070081 S1102755, the e-traveler of which is available here: https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=58957

Comments related to this report
filiberto.clara@LIGO.ORG - 10:37, Monday 04 June 2012 (3024)
ISC Anti-Image Chassis (S1102755) found to have bad channel on one of the filter boards (D070081 Rev 5 SN S1106145) CH4. U1 output railing at 14V. Replaced filter boards: serial number S1106145(Rev5) and S1106146 (Rev5) with S1201597 (Rev6) and S1201598 (Rev6).
Displaying reports 74001-74020 of 76956.Go to page Start 3697 3698 3699 3700 3701 3702 3703 3704 3705 End