3rd IFO unit#2 is essentially done testing. Collecting info from minor static tests are all that remains. Unit #3 is built up to a test state for MIT--looking at coupling from the EM actuators to the sensors. We have a few CPSs left to connect and cable. We should be ready to do this test by Wednesday. Once this test is done we'll need to back track a little to build it right and float the table. Something like another week after this special test. Meanwhile we'll dance large plates for Unit #4 around with the Container to get unit#2 out of the Staging building early next week.
Yesterday I aligned the IR transmission to the TMSY ISC table QPDs.
It was easy to bring the beam on both of the QPDs using M14 (downstream pico mirror). I made a very small PIT adjustment using M4 (upstream) before the IFO decided to not to cooperate.
Today I was just fishing for a good flash and found one (attached). Seems like both of the QPDs are reasonably centered: [P, Y]=[0.05, 0.18] for QPDA, [-0.1, -0.1] for QPDB.
And apparently we're still receiving IR light on ISCTEY, even though I didn't touch periscope. This is good enough.
08:50 Arnaud shaking ETMY for ~ 15 minutes 08:58 Jodi and Joe checking that the viewports staged in the LVEA are the ones listed for installation 09:12 Hugh retrieving 3rd IFO helicoils from the LVEA test stand area 09:15 Andres to HAM5 to work on SRM alignment 09:17 Jason to HAM5 to work on SRM alignment 09:31 Dale to LVEA to take pictures of HAM4, 5 09:31 Betsy to HAM4 09:36 Hugh out of LVEA 09:52 David H. and Thomas V. to LVEA to work on HWS table 09:55 Jeff B. to HAM5 for SRM work 10:28 Travis to LVEA teststand to work on ACB 12:13 David H. and Thomas V. out of LVEA for lunch 12:25 Andres and Jason out of LVEA for lunch 12:49 Karen to end Y 13:00 Hugh looking for hardware in the LVEA 13:16 Hugh out of LVEA 13:25 Andres back to HAM5 13:37 David H. and Thomas V. back to the HWS table 13:46 Peter K. going back into H2 PSL enclosure 13:56 Karen done at end Y 14:13 Jeff B. back to HAM5 15:30 Andres, Jeff B. back from LVEA Richard and I worked on communications to the dust monitor in the H1 PSL diode room.
As Jason said, we ran out of adjustment range on the Top Mass Pitch Slider and there is no pitch adjustment slider at the Intermediate level. To correct the pitch we (1) put the Top Mass Pitch Slider back into its neutral position, (2) Removed the left, right, and T1 BOSEMs (they can interfere with pitch), and (3) made several rounds of moving addable masses from front to back and back to front to dial in the pitch. Once we were close to the correct pitch alignment by shifting addable mass at the Intermediate Mass level, we made the final fine adjustments using the Top Mass Pitch Slider. We reinstalled and aligned the BOSEMs. Transfer functions are running overnight. If these look good, we will be ready for fine tuning on Monday.
This morning I (and a little we):
- used the proper cookie cutters to set the 4 smallish baffles and 1 scraper baffle into place, dogged all ~35 dogs.
- reset the HWS steering mirror in front of SR2 into position, dogged it down.
- attempted to layout the temperature sensor cable using the notes from LLO - this unfortunately didn't go well as I broke one of the sensors off (even though I was warned that this could happen and I was being very careful). LLO reports a broken one as well. Long story short, I set the cable on the table anyways such that the heavy connector weight is on the table. A separate alog will have more details to the break and a fix or swap sometime in a week or 2 after SEI is done.
- Mounted the 4 HWS lenses onto the mounts - note, the HWS spec calls for 8-32s that are too long, we swapped in appropriate ones.
So, the only things "out of spec" on the table as now, which will be addressed before chamber close up are:
- the obvious HWS alignment work
- swap/fix temperature cable (there is a spare)
- add witness 2 light weight witness plates
- add light weight 1" witness optic
- pull FC sheet from SR2-HR
(Betsy, Travis)
The ACB has been fully payloaded, suspended, and coarsely aligned. I'll consult with the experts on fine tuning next week. Then, we'll take it back apart and wrap and bag it for transport to the ITMy staging area.
J. Kissel In light of the recent problems with VEA temperature causing sag in the L1 QUADs -- to the point of rubbing earthquake stops (see LLO aLOG 12633) -- I've gathered a similar 1-year long collection of hour trends of each VEA's temperature vs. vertical displacement of each QUAD. Our temperature appears to be rock solid (certainly within 1 [deg C], and at the end stations, better than +/- 0.2 [deg C]). After installation, the vertical position of QUADs also remains pretty darn stationary, staying within a few 10s of [um] (a more precise assessment would require a better tool than dataviewer).
... it's finally there, thanks to Jamie's great work.
This morning we used ITMY to fine tune the parameters. After increasing the HEPI Boost filters ramping time from 5s to 10s on the vertical dofs, and from 5s to 15s on the horizontal dofs, there were no more saturations of the GS13s during the Turn ON process of HEPI. The SEI manager was able to entirely bring the HEPI, Stage 1 and Stage 2 under full control, including a restore of 300uRad of HEPI pitch offset.
9:29 -> We request the manager to bring the entire chamber from "everything OFF" to "Fully Isolated"
9:31 -> HEPI is fully isolated. The Yaw and Pitch alignments have been restored. The Manager code waits for the T240s to settle
9:39 -> The T240 monitor indicates to the Manager that the T240 have settled. The manager starts isolating Stage 1. The SEI front end code automatically resets the T240 Saturation counter and the WD starts watching the T240s.
9:41-> Stage 1 and Stage 2 are fully isolated. The Yaw offesets have been restored. The SEI system is "Fully Isolated"
We tried this full cycle another time and it worked just as well.
A few notes:
- we need to fix the HEPI boost filters
- we tried to Auto Z the T240s after restoring the HEPI offset. It looks like it could save a couple on minutes in waiting time if needed
- the GS13 trip at the very end of de-isolation process. That's no big deal as we almost never need to fully de-isolate for now, but we should have a look into it.
- there is probably some room to reduce some ramping and waiting time here and there, but more than half of the turn on process will still be dedicated to waiting for the T240s to settle
- in the future, we can think of turning on the ISI in high blend mode while the T240 settle, and then switch to low blend. For that, we'll need the additional guardian node that we talked about to switch the blends and other control parameters.
- it could be nice to add a clock on the T240 monitor screen showing how much time there is still to wait
SRM Jason setting up for pitch measurements Betsy running transfer functions Jeff B. wants to connect the wiring for the bottom two stages (needs to wait for transfer function measurements to finish) HAM4 Last TCS components to be installed: ISI probably ready for balancing next week Betsy installing baffles TCS No work on X or Y CO2 tables, HWS work only: No need for laser hazard ACB Ready to start balancing and suspending Photodiodes need to be tested Staging building Jim W. finishing testing on Unit 2 Apollo Bubba machining parts for TCS Unifirst will be delivering on Thursday for the next couple of weeks Jamie and Robert scheduled for weekend work Rai W. will be here next week to take acoustic measurements of the beam tube Peter K. is working on ISS in the H2 PSL laser enclosure Chris to move 3 IFO PCAL parts from the LSB, VPW and woodshop to mid X and 3 IFO PCAL parts from the LSB to mid Y
Came in this morning to find the BS ISI stage 2 GS13 watchdog tripped. Unclear why.
The strange thing is that the trip appears to have occured at GPS 1084253752, which is 10:30pm last night, whereas commissioning finished up around 4:30am. Did they just run with the BS tripped all night?
The watchdog was reset and guardian recovered everything fine.
The ISI-BS is a little peculiar: we know that the Michelson feedback could send a kick to the ISI and trip ST2 watchdogs. It's very often that the commissioners work with ST2 tripped, and I wouldn't be surprised that's what happened last night.
Given that, you should double check with the crew to see if it was really the case.
This was indeed the case. The michelson lock was kicking the BS and tripping stage 2, so they just ran with it tripped.
This is obviously an untennable solution, so we need to figure out how to prevent the BS ISI from tripping during acquisition.
DetChar line hunters emailed me with some results from their HIFO-X investigations. The line looked to me like lines I had seen before from an I/O box in the test stand (here). Figure 1 shows that, when I partially covered the fan intake of the I/O box that carried the channel, the line dropped in frequency, and returned after I uncovered it. The peak from the second fan, up around 80 Hz, also moved when I partially covered its intake. This confirms that these lines that they found in H1:ALS-X_ARM_IN1_DQ are from the cooling fans in the h1iscex I/O box. In the above reference I note that running similar fans off of a separate power supply reduced the lines that the fans produced in the I/O box channels by about a factor of 10. This suggests that the dominant coupling is through power supply ripple.
In addition, I tested for lines from the h1iscex I/O box switching power supply. These lines are produced by coupling of the large magnetic fields that the supplies generate, to cables and connectors in or near the I/O box (same link as above). The magnetic fields produced by the switchers include rapidly drifting lines from beats between high frequency oscillators and lines from the fans in the switcher. I partially blocked the switcher air intakes to move the fan peak frequency in order to confirm that the field I was seeing on a magnetometer that I had set near the switcher, came from the switchers. Figure 2 shows that there was coherence between channels in the I/O box and the magnetometer reading the switcher field, at the frequencies of the switcher fans. In this particular I/O box, the peaks produced by magnetic coupling of switcher fields were smaller than those produced by power supply ripple from the I/O box fans. The size of the peaks from the switcher depend, in part, on how close the cables pass to its location in the back of the I/O box (here) .
Robert Schofield, Nelson Christensen, Jialun Luo, Patrick Meyers, Michael Coughlin, Eric Thrane, Keith Riles
Here is Patricks report.
model restarts logged for Thu 15/May/2014
2014_05_15 13:16 h1isiitmy
2014_05_15 13:19 h1asc
2014_05_15 13:22 h1broadcast0
2014_05_15 13:22 h1dc0
2014_05_15 13:22 h1fw0
2014_05_15 13:22 h1fw1
2014_05_15 13:22 h1nds0
2014_05_15 13:22 h1nds1
2014_05_15 16:58 h1susetmx
2014_05_15 17:30 h1susetmx
no unexpected restarts. h1susetmx restarts part of 8Hz noise investigation.
Lisa, Kiwamu, Stefan - We had the 18Hz mode of the BS ring up. an additional notch in the MICH loop fixed it. - We tried to use the REFL27 demod phase to reduce the CARM noise in MICH, but this did not work. - We had the BS being kicked too hard by the PRMI lock acquisition, producing a yaw misalignment, resulting in a loss of the DIFF beat note. We disabled the BS top mass feed-back, which solved this issue. - In the process of this debugging we also checked the beat note of DIFF - it was however already pretty well aligned. - Next we noticed that at -1kHz offset we were sitting right on the 2omega arm resonance. This caused large offset changes in the 3f signal. We decided to try using a ~600Hz offset instead. - That turned out to make locking on 1f very difficult. 2 hours later we tried a 2kHz offset (on the wrong side of the 1kHz 2f resonance), which worked fine. - At the 2kHz offset we successfully transitioned to 3f, but as expected, when marching across the 2f arm resonance MICH went unstable. - But we had to increase the REFLAIR_B_RF27_Q gain in the input matrix from 2.5 to 4. - Our next goal was to lock at 2kHz offset, then stay on 1f as we move in to about 600Hz, and then try the transition to 3f there. - another earthquake...
J. Kissel The Messages: (1) The effective bias voltage charge on the test mass is -28 [V_pk], which quite small compared to the BIAS range of 400 [V_pk] (and in conflict with Keita's assessment from the optical levers [see LHO aLOG 11905]). (3) The force actuation strength is asymmetric with respect to bias voltage, confirming Keita's result (see LHO aLOG 11872) (2) The force coefficient at 11 [Hz], measured as a function of bias voltage, is roughly 0.5e-10 [N/V^2], a factor of 8 below the expected 4.2e-10 [N/V^2] (expected from pg 7 of G0900956) DETAILS ------------- Brett: please proof read: ------------- Note, no linearization algorithm was used during this experiment. (1) Using the time-honored MIT method of measuring test-mass charge (e.g. from Brett, John, and Lisa), I drove a single frequency line into the control voltage H1 SUS ETMX ESD drive, looking at the X arm cavity length (as measured by green), while stepping the bias voltage through its entire range. As one steps down the bias voltage, we expect the linear response to drop to zero. Further, one can take the slope of the response as the bias decreases from both the positive and negative side and predict an effective bias voltage created by residual charge on the test mass. I attach the results. Using a linear regression, weighted by the coherence as follows, unc = sqrt( (1 - coh) / 2*nAvgs*coh ) weight = 1 / unc^2; I calculated the intersection of the two slopes to be -27.99 [V_pk]. I took an excessive amount of data points, because I didn't know what I was doing when I started and wasn't sure how the results would turn out. The template is here for excitation: /ligo/svncommon/SusSVN/sus/trunk/QUAD/H1/ETMX/SAGL3/Data/2014-05-15_H1SUSETMX_L3_ChargeTest.xml For the record, I tried using the script recommended by Brett (LHO aLOG 11914), but after updating all the necessary channel names and input variables. it failed deep with in its subfunctions because of some xmlconv library that's now gone missing since 2009. I didn't have the time nor expertise to debug, so I just changed the bias by hand and measured the ten averages with the GUI DTT session, capturing references as I went, and exported at the end for processing. (2) No further details here, it's obvious that the drive strength is weaker with positive bias voltage than with negative. I have no good explanation for this. (3) From these displacement response results, one can also obtain the force coefficient for each bias step. The calculation is as follows: disp_mpk = 1e-12 * sqrt(2) * sqrt(binWidth) * disp_pmrtHz; force_Npk = disp_mpk * 1./compliance_11Hz.mpN; V_CTRL.Vpk = nActs * sqrt(2) * sqrt(binWidth) * esdGain * excChannel.amplitude.V_DAC.VrtHz; V_BIAS.Vpk = bias.V_ESD; forceCoefficient = abs(force_Npk ./ (2*V_CTRL.Vpk * V_BIAS.Vpk)); where disp_pmrtHz = displacement response of the arm cavity length at 11 [Hz] during each bias voltage setting, in [um] (which I subsequently turned into [pm] for plotting clarity) as measured from the calibrated ALS control signal, H1:ALS-X_REFL_CTRL_OUT_DQ sqrt(2)*sqrt(binWidth) = sqrt(2)*sqrt(0.09375 [Hz]), calculation needed to change from noise units ?_{rms}/rtHz to amplitude units of ?_pk 1e-12 = 1e-12 [m/pm] compliance_11Hz.mpN = 5.3e-06 [m/N], TST to TST, L to L transfer function at 11 [Hz], obtained from the QUAD model. excChannel.amplitude.V_DAC.VrtHz = 12.45 [V/rtHz], measured output request voltage from the DAC (calibrated from counts out of the digital last output to ESD, i.e. H1:SUS-ETMX_L3_MASTER_OUT_LL_DQ using the 180bit DAC gain, 20/2^18 [V/ct]) esdGain = 40 [V/V], gain of the ESD driver sqrt(2)*sqrt(binWidth) = sqrt(2)*sqrt(0.09375 [Hz]), calculation needed to change from noise units ?_{rms}/rtHz to amplitude units of ?_pk nActs = 4, since the calibrated output requested voltage is only from one channel. and I've computed the force coefficient, a, using only the linear term, since I used the amplitude of the linear term alone F = a (V_CTRL sin(wt) - V_BIAS)^2 = a V_CTRL^2 sin^2(wt) - 2 a V_CTRL V_BIAS sin(wt) + a V_BIAS^2 [ sin^2(wt) = 1/2 - 1/2 cos(2wt) + O(4w) ] = a(V_BIAS^2 + 1/2 V_CTRL^2) - 2 a V_CTRL V_BIAS sin(wt) + - 1/2 a V_CTRL^2 cos(2wt) DC Term Linear Term Bi-linear Term =>> Linear Term, a = F (2 V_CTRL V_BIAS) Confusingly, this resulting coefficient, a = 0.5e-10 [N/V^2] is a factor of 8 weaker than expected, which is *different* than the factor of 4 weaker that was needed to explain the linear transfer functions taken last week (see the second attachment of LHO aLOG 11676). The script that processes the measurements is here: /ligo/svncommon/SusSVN/sus/trunk/QUAD/H1/ETMX/SAGL3/Scripts/analyzeesdcharge_20140515.m
Jeff, This is getting pretty mysterious. Suggest that you try to establish whether you actually can see the capacitance change with relative motion of the test mass with respect to the recoil mass in each ESD quadrant. The bridge circuit would be a good way of doing this. I will be at LHO starting Monday and could help out with the measurement. One explanation is that you do not really have a solid connection to either the bias or the control electrodes - an open connection with either only capacitive coupling or a high resistance. RW
Jeff, 1 piece of good news - this amount of voltage implies that the isolation performance is probably not compromised by the charge. Long ago I did a rough estimate for how much charge could be on the optic in a blob near the tip of the earthquake stop. https://dcc.ligo.org/T080214 Although the field gradient is the important thing, and this is a function of both of the amount of charge and the spatial distribution there-of, one can say the if the blob is about the size of the stop, then the voltage of it is about 140 V before it compromises the isolation performance. -Brian
J. Kissel, B. Shapiro, Brett has caught a mistake in my calculations above, in that I *should not* multiply the control voltage, V_CTRL.Vpk, by a factor of four (i.e. nActs). My thoughts on including the factor of four were that I was measuring the requested DAC output of *one* quadrant, and since there're 4 quadrants, I add the force created by each of them. However, given how the force coefficient was defined for all four quadrants, it's better to think of each of the four quadrants creating a ring of control voltage, all held at the same requested value. It's then the potentional difference between this control ring and the bias ring that generates the forces on the test mass. Hence the caluclation for the force coefficient should be disp_mpk = 1e-12 * sqrt(2) * sqrt(binWidth) * disp_pmrtHz; force_Npk = disp_mpk * 1./compliance_11Hz.mpN; V_CTRL.Vpk = sqrt(2) * sqrt(binWidth) * esdGain * excChannel.amplitude.V_DAC.VrtHz; V_BIAS.Vpk = bias.V_ESD; forceCoefficient = abs(force_Npk ./ (2*V_CTRL.Vpk * V_BIAS.Vpk)); (Thanks for the clarification Brett!) In addition, while debugging, I caught another error: The uncertainty from each data point as calculated above computes the *relative* uncertainty. As displayed on the graph, since the plot shows absolute amplitude of the displacement, the uncertainty should be displayed in absolute units, as in unc = disp_pmrtHz.full .* sqrt( (1 - coh) / 2*nAvgs*coh ) weight = 1 / unc^2; Finally, even more dumb of a mistake, a copy and paste error meant I was using the asd vector as my coherence vector. All of the above errors, bugs, and mistakes have been corrected, and I attach a revised plot. The new force coefficient is roughly 2.2e-10 [N/V^2].
The cookie cutters did their job and placed the suspension within spec for X, Y, and Z axis positions. The position errors are below:I have begun and mostly completed the setup for the rough pitch/yaw alignment of the SRM-s. This will be completed tomorrow morning and the rough pitch/yaw alignment will follow.
I ran quick V and R TFs and the sus looks healthy to me compared to old references that Arnaud left me. I need to dig up a good L reference TF and run that in the morning, but then we should be good to go on the pitch/yaw tuning.
And L looks good, too!
Yesterday night, I tried to run SR2 M2-M2 and M3-M3 (lower stages) in chamber transfer functions after the osems were centered on wednesday. Although both M2 and M3 watchdogs tripped during the measurement, so I am running it again tonight. (This time, I decreased the drive and increased the watchdog threshold).
Decreasing the drive didn't help either since I ended up with measurements without coherence. This morning I tried to drive M2 stage with high amplitude sinewaves at the resonant frequencies of the suspension for each DOF (L P and Y) to see if the osems would saturate. They don't. So a drive of 500 000 (cts) for L and 20 000 (cts) for P and Y (which is the limit before saturating the DAC) should be optimum at all frequencies. Started a new measurement which will run today.
This time, phase 3a M2-M2 and M3-M3 measurements of SR2, in air, with the HAM-ISI locked were succesful. The actuation is functioning, and the transfer functions for the three degrees of freedom are similar to the model.
There is one interesting feature to note for M2 stage. From 10Hz, the measured tf rolls up, as if some extra zeros were added to the tf. I checked the osem output filters, and they seem to compensate correctly for the coil driver (looking at the state diagram in state 1).
Attached are some SR2 phase 3a spectra for future reference