Displaying reports 76501-76520 of 76888.Go to page Start 3822 3823 3824 3825 3826 3827 3828 3829 3830 End
Reports until 16:02, Monday 13 December 2010
H2 INS
dani.atkinson@LIGO.ORG - posted 16:02, Monday 13 December 2010 (409)
Ops Day Shift Summary
  • Doors remain off HAM12 and covers on, but no work occurred there today.
  • There's a work permit about moving a clean room at MY, which presumably happened.
H2 INS
patrick.thomas@LIGO.ORG - posted 17:26, Friday 10 December 2010 - last comment - 14:38, Wednesday 15 December 2010(408)
Ops Day Summary
10:10 Recycling pickup

1:15 south door of HAM 12 cloth removed, north door cover removed shortly after
~4:55 both doors of HAM 12 cloth covered
Scrubbing HAM 12 from 3:56 - 4:13, attached is trend of dust levels in the LVEA during this time
Location 1: Inside ISCT4
Location 2: Outside South West corner of clean room
Location 3: Inside North East corner of clean room
Location 4: Inside South East corner of clean room
Location 5: Inside "beer garden"
Location 7: Between HAM7 and HAM8
Location 8: Between HAM1 and HAM2
Location 10: Inside H1 PSL
Non-image files attached to this report
Comments related to this report
jodi.fauver@LIGO.ORG - 14:38, Wednesday 15 December 2010 (415)
Synopsis of Chamber Cleaning Test at HAM 12 (Complete report may be accessed at T1000732)

Participants: Rodney and Zack Haux, Eric James, Mike Zucker, Jodi Fauver with Patrick Thomas on dust monitors, Dani Atkinson on DCC look-ups, and Chris Soble, Joe Valdez and John Worden on tool mods/repairs

Upon our initial entrance into the clean room,  Mike discovered that one HEPA fan on the top of the cleanroom was found turned "off". Recommending INS crew locally check all fan units on each clean room with both a particle counter and an anemometer  each time the cleanroom is rigged. The adjustable-speed knob on these fan units, which cannot be seen from floor level, is not a good feature.

Initial assessment inside the chamber showed there was significant particulate matter. Oxidized surfaces yielded the brown-yellow stain on a wipe as seen in other chambers. Inside the support tube nozzles (non-oxidized) there was a "dry riverbed" of sparkly particles which appeared metallic or perhaps glassy.  They were collected on a wipe from one of the nozzles for further examination. Running a finger down the center of the nozzle left a visible clean streak. 
Several rinsate samples were conducted as a part of the initial assessment. 

The rotary brushing tool was tested on the same area where the rinsate sample was taken. We tested the Festool power brush tool and vacuum shroud developed for oxide removal.  There are substantial mechanical revisions needed to the shroud assembly and brush arbor which we need another meeting to work out so I won't get into specifics. Nevertheless, after much "field improvisation" we were able to get the tool working and ran a successful test.

Videos of the brushing test are found at G1001144-v1.

We used a "surplus" 60" nozzle dam, whose provenance we could not immediately reconstruct,  to block the MC tube aperture


The HEPA vacuum, hose and C-3 hose sleeve worked fine. Suction at the tool face was good; with the brush running at speed (high range) but vacuum off, tens of thousands (22,099 counts) of pppcf registered an inch from the brush. This dropped to zero counts (resolution 20 ppcf) with the attached HEPA vac running.

The final set of tests was to make sure that we did not introduce HC's. An FTIR sample was taken per standard procedure from the scrubbed and wiped zone, as well as an undisturbed control zone and a liquid control. 

H2 General
jeffrey.garcia@LIGO.ORG - posted 15:59, Thursday 09 December 2010 (407)
Ops Day Summary
~10:30 - Cleaning by ham7 

~11:00 - Ground Water in to sample water well

~2:30 – Both doors off HAM12

~3:00 – crew out to test new “scrubber” for in-vacuum cleaning.  Work continues by 4:00pm.

LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:27, Thursday 09 December 2010 (406)
HAM12 doors removed
Kyle, Ski, Joe, Chris -> Removed HAM12 North and South doors.  This is the 1st time these doors have been removed since being baked out.  O-rings completely stuck like "glue" for entire contact area.  Much viton material "donated" from O-rings to compressing flange.
H2 DAQ
david.barker@LIGO.ORG - posted 08:39, Thursday 09 December 2010 (405)
new awiki advligo wiki server
Jonathan, Patrick, Dave.

On Tue 7th we ported the advance ligo wiki service from the old iligo wiki machine (called wiki on the 10.2 network behind the ruby NAT router) to a new GC machine dedicated to the advligo wiki. The new machine is a centos linux, using ligo.org authentication. The new machine uses the lastest moinmoin version, whereas the old wiki had a very old copy of moinmoin.

The move required:
Copying the data content (2.9GB of files) and porting from old to new wiki format.
Transposing authors from the local accounts to the ligo.org equivalents
Automatically redirecting access to the old advligo URL to the new URL

The new wiki is at https://awiki.ligo-wa.caltech.edu

Questions, Comments, Problems should be emailed to wiki-help@ligo-wa.caltech.edu
H2 INS
cheryl.vorvick@LIGO.ORG - posted 16:31, Wednesday 08 December 2010 (404)
H2 Deinstall: removal of plumbing between chiller closet and TCS table
- Zach, Rodney, Cheryl

Removed plumbing, including all copper pipe and hoses, between the H2 TCS tables and the chiller closets.  Tables are only tethered by the card access system, since H1 and H2 TCS enclosures are tied together to one card-swipe box.
H2 INS
dani.atkinson@LIGO.ORG - posted 16:05, Wednesday 08 December 2010 (403)
Ops Day Shift Summary
  • HAM7 was closed up and the clean room moved over to cover HAM12 in preparation for tomorrow's dirty work.
  • NSF tours were taken through the LVEA.
  • Cheryl dismantled some of the TCS plumbing, leading to some minor leaks of propylene glycol, which were cleaned up.
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:58, Wednesday 08 December 2010 (402)
Kobelco "Alert" bogus
The Corner Station purge air compressor (Kobelco) has had a "Service Alert" ever since the power glitch a few days ago. The PLC memory battery failed and the various service parameters have defaulted to initial (not applicable) values.  Operationally, the purge air is fine. 
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:54, Wednesday 08 December 2010 (401)
HAM7 doors
Kyle, Corey, Joe, Chris -> Hung West and East doors on HAM7
LHO FMCS
mark.lubinski@LIGO.ORG - posted 09:00, Wednesday 08 December 2010 (400)
site inspection
Annual site septic field inspection.
Drain field was rotated
LHO FMCS
mark.lubinski@LIGO.ORG - posted 07:57, Wednesday 08 December 2010 (399)
X mid roll up door
X-mid door installed not complete
H2 General
jonathan.berliner@LIGO.ORG - posted 17:14, Tuesday 07 December 2010 (398)
Ops Day Log
Major work:
- NSF Review Begins...Tour scheduled for 1330
- HAM7 passive stack extraction
- aLIGO Wiki upgraded
- Door on HAM7 still off
- Praxair Delivery
- Closing HAM7 and craning clean-room from HAM7 to HAM12 not completed at time of writing

Times in PST:
0835 - Overhead doors arrive at MX
0847 - Corey out to HAM7 with Cheryl, Jeff, Rodney, Ski, to move MMT3
0905 - Squeezer on
0934 - Les Schwab arrives with tires
1131 - EX CP8 alarms, due to fueling by Praxair
1134 - Corey confirms that HAM7 is done
1331 - Jodi begins testing rotary tool at MX...disappointing results
H2 INS
corey.gray@LIGO.ORG - posted 14:08, Tuesday 07 December 2010 (397)
HAM7 iLIGO Seismic Isolation Stack Removal
[9:45 -11:15am]
(Corey, Jeff, Rodney, Ski, Zach)  

After helping out with moving SOS's around, the HAM7 stack removal commenced.  The procedure went smoothly.  The hardware is piled on top/next to the HAM8/9 hardware.  This pile of hardware will be moved out of the LVEA as soon as we receive recycling bins.
Images attached to this report
H2 INS
david.barker@LIGO.ORG - posted 08:47, Tuesday 07 December 2010 (396)
advligo wiki being replaced with awiki
The old advligo wiki was transitioned to read-only mode at 8am. Its data content is being transferred to the new awiki server (latest moinmoin with ligo.org authentication). We hope to have the new server ready for use by end of business.

Dave, Patrick, Jonathan H.
H2 General
cyrus.reed@LIGO.ORG - posted 16:32, Monday 06 December 2010 (395)
Ops Day Shift Summary
Today's major activities:

  • HAM7 optics removal (complete)
  • HAM7 prep for SEI stack removal.
  • Some on site deliveries.
  • The other usual miscellaneous stuff.
Also note that there are occasional high temp alarms for LVEA Zone 4F due to the increase in equipment added by the squeezer group. These are OK (unless the temperature continues to rise, or other zones also go into alarm, obviously).
H2 General
david.feldbaum@LIGO.ORG - posted 16:25, Monday 06 December 2010 (394)
HAM7 deinstall (DF, D.Tanner, Mike, Betsi, Rodney, Carolyn)
We have removed all the optics from HAM7. This includes:

H2 MMT3 LOS                          -- to be transported out of LVEA by crane

H2 MC1  
H2 MC3
H2 MMT1  
H2 SM1
H2 SM3                              --  stored in the optics lab

H2 old style Faraday isolator
~ 16 DLC mounts with mirrors    
~ 2 Tanner mounts                   --  being packaged for shipping to the UF.


Thanks to everyone for helping to make this operation go smoothly and efficiently. 
LHO FMCS
kyle.ryan@LIGO.ORG - posted 17:13, Friday 03 December 2010 (393)
VE power failure recovery
Custom battery backups for MTP levitation worked correctly following power failure today for all spinning MTPS on site.  All isolation valves "safety" valves worked correctly and isolated valved-in MTPs from foreline header at loss of power -> Restarted QDP80s and MTPs and resumed pumping (YBM, Vertex, XBM, X-end).  Had to switch back to turbo for HAM6 and valve-out ion pump.  Had to restart aux. carts pumping HAM1 and GV10 annuli.  
LHO FMCS
kyle.ryan@LIGO.ORG - posted 17:03, Friday 03 December 2010 (392)
HAM 7, 8 and 9 doors
Kyle, Ski, Jim, Rodney, Zack - Hung West doors on HAM9 and HAM8.  

Chris, Joe - Removed all but (4) "cracked loose" bolts from HAM7 East and West doors
H2 INS
dani.atkinson@LIGO.ORG - posted 15:59, Friday 03 December 2010 (391)
Ops Day Shift Summary
Doors went back on HAMs 8 and 9, and HAM 7 was prepped for entry Monday (including removal of IOT7 and ISCT7 enclosures). We had a very brief power outage in the morning and appear to have recovered, except for the possible death of h0pemms. Richard has also installed a camera for outreach purposes along the Y-arm in the LVEA, looking towards the BSC8/HAM10 area, to catch the upcoming single-arm work.
LHO FMCS
dani.atkinson@LIGO.ORG - posted 11:08, Friday 03 December 2010 (390)
Power Flicker
We had a power outage of about a second at 9:41PST. We're still restoring some of the systems on site. H2 deinstall activities in the LVEA were only minimally effected.
Displaying reports 76501-76520 of 76888.Go to page Start 3822 3823 3824 3825 3826 3827 3828 3829 3830 End