Recent attempts at sealing the ceiling tiles and damp mopping/wiping the floors and walls etc. have had virtually no impact on the particulate monitoring counts in room 169 (OSB bake-oven room) -> Recalling that the particulate count increase roughly coincided in time with the decision to keep the door closed between the bake-oven room and the adjacent vacuum prep lab., I decided to prop open the door and leave it open overnight. The result was a return to traditional particle counts in both rooms, i.e., a major improvement in the bake-oven room and no change (or a slight improvement) in the vacuum prep. lab -> I'm leaving this door open until overruled by a higher power
- FredR in place of MikeL for INS coordination today - Reibold on site, cautioned against bringing in Mountain Dew and paper towels to LVEA (contamination concerns) - Laser Hazard all day today for squeezer work (compromise with Doug Cook and IAS in exchange for no laser hazard Wed. - Fri.) - Jodi staging in HAM1/South Bay area for BSC8 ICC - GregG working around HAM7 - Braising at EY - Test stand assembly at EY 0900 - Diamond Frieght shipment for TerryS and BetsyB 0910 - Scrap wood bin replacement 0931 - UniFirst arrives 1108 - Septic Tank trunk arrives 1126 - Walter and Gregorio to MY 1200 - Praxair begins filling wrong tank by LVEA, Kyle fixes situation 1330 - RichardM and CyrusR move H2 Y-arm racks to accommodate monument surveying. Dust alarm by ISI stand as GerardoM and KyleR were working in the area 1332 - Kyle begins closing GV5 1500 - Gown room placed near BSC8
Co-ordination Planning for LVEA 02-05 August 2011 Tuesday, 02 Aug 2011-Laser Hazard Kyle to remove pump cart from near BSC-8 and hard-close GV-5 Richard / Apollo to slide the ISI racks forward to accommodate survey crew on Y-arm ICC to stage all possible items to the PSL-1 area, including 2 garbing/staging cleanrooms Wednesday, 03 Aug 2011-Laser Safe-Crane work restricted during shots Doug and crew to take required shots along Y-arm Kyle to vent volume needed for BSC-8 entry? Thursday, 04 Aug 2011-Laser Safe-Crane work restricted during shots ICC to move large cleanroom over BSC-8 chamber (as long as shots are finished) ICC to remove cleanroom from BSC-7 and set it down out of the sight lines for new H2 shots (Dome cleanroom) Doug and crew to take required shots along X-arm Friday, 05 Aug 2011-Laser Safe-Crane work restricted during shots ICC to move dome cleanroom into place near HAM 11-12 (as long as shots are finished) Doug and crew to complete survey work
We tested a clean method of power cycling a front end. First all user models were killed, followed by the iop. At this point the only things running were the awgtpman process which were restarted by monit. We then IPMI power cycled the frontend (h2susauxb478) and did not affect the daq status of the other running front ends.
I'll write this up as the reboot procedure for frontends in the wiki.
We then simulated a loss of the h2boot server by disconnecting it from the H2FE LAN. The front end medm screens froze up, but did not go "white screen". All medms just froze in a "good" state. The control room workstation of course slowed because they tried to mount /opt/rtcds, and no new medms could be opened because of the file server loss. When h2boot was re-attached to the LAN everything came back alive. Vincent looked at an ISI fast channel and verifed the front end was running and sending data to the DAQ for the whole time.
The H2:SEI system was renamed H2:HPI
The BSC8 model name was changed from h2seiitmy to h2hpiitmy. All corresponding INI, PAR files where also changed. The DAQ was reconfigured to use the new files.
The overview MEDM screen was also changed, and the old h2seiitmy target moved to the target_archive area.
In other CDS news, the new frame files had errors in their names. H-H2-R should have been H-H2_R. This was changed for all frames on h2fw0,1 and all existing frame files were also corrected.
(Corey, Eric, Fabrice, Jim)
BSCISI #2
Reamed out the Base Flanges for the Vertical GS13's. They were installed via the forklift (see photos).
Here are the Vertical GS13 serial numbers:
Corner1: 88 (not vacuum-ready, must be replaced!)
Corner2: 52 (not vacuum-ready, must be replaced!)
Corner3: 48 (not vacuum-ready, must be replaced!)
Trilliums were fitted with 2.5" long bolts (really need the 3" ones, but they're being baked). Once the Trilliums were bolted down we installed the Horizontal L4Cs (one of which is a "bad" one which is not for use in our vacuum system and will need to be replaced.
Here are the Horizontal L4C serial numbers:
Corner1: 34 (this is the bad one!)
Corner2: 30
Corner3: 10
Eric's installed the remaining Capacitive Position Sensors, so now all of those are also on the system.
Installed Horizontal GS13 Walls (Stage2), removed excess weights, removed Stage1-2 Alignment Pins, unlocked Stage1-2, balanced, adjusted lockers for horizontal alignment, and then called it good. Tomorrow, we'll install Trillium Walls, run cabling, and address any final balance issues. Then the system is ready for testing.
BSCISI#3
Installed & torqued down the third Blade Post (pulled out of oven recently).
The dome was returned to BSC-7 this morning. During the inspection of the dome flange o-rings, a fiber (saved) was found and removed. Kyle came out and took a look at the fiber and told the crew what to beware of, etc. Since no further issues were encountered, the dome was put in place and secured. After lunch, Mark L. and I went into the chamber to remove the dust barriers, inspect the beam tube convolutions, and vacuum them if needed. We did end up vacuuming with the LLO-designed bellows vacuum attachment. Mark also inspected the floor on the way out of the chamber and removed a couple of "spots". The final planned activity of the day was replacing the door on the chamber. The door interior was inspected once it was inside the cleanroom. The welds were not nearly as bad as those in the dome and the door body was not very dirty either (neither left much visible residue on a clean glove, even with a couple of attempts). The decision was made not to do any vacuuming or wiping on the door, but to leave well enough alone. The door was replaced and secured.
- CarolW and FredR presiding over INS today - ICC: Dome being returned to BSC7 - Drilling and grouting at MX for spool placement. Shooting for Wed. (transmission of rental forklfit burned out). - Reminder about aLOG rule regarding conflat flanges 0810 - Cardboard recycling truck returns with covered bin 0815 - Reibold arrives to work by H2 Diode Room 0852 - GregorioT at MY 1300 - LVEA to laser hazard for squeezing. IAS may begin work on Wednesday 1415 - Dale leads tour for two guests in LVEA 1500 - Patrick to EndX to install a dust monitor 1511 - GregM informs me that Oracle will deliver the tape library tomorrow (Tuesday)
I put the MetOne 227B serial number 980500281 at end X location 1.
I have just set the Epics alarm values for it.
R. Lane H2 SUS ITMY R0 TF, round 2.
R. Lane H2 ITMY M0 TF Round 1 Complete. Notice shift of third pitch mode frequency.
[This is work from Friday]
(Chris, Corey, Eric, Jeff, Joe, Jim, Mitch, Natalie)
Assy #2
Installed Trilliums
We don't have the called out 1/4"-20 x 3" bolts (they were used for Vertical GS13s on #1---because procedure erroneously called out 1/4-28 bolts...so the Trillium bolts for Assy#2 were used instead), but went ahead and installed/positioned these seismometers. We had (1) 3" bolt and I used this to atleast check that it would thread into a couple of the holes for each Trillium (more 3" bolts are currently in a bake load). We have 2.5" long bolts and may use them instead. Here are where the Trilliums were installed:
Corner 1: s/n 001
Corner 2: s/n 24
Corner 3: s/n 15
L4C Swap
Installed new & freshly leak tested pod. Note: These pods had noticeable Aluminum oxide particles/marks on them, and required a few wipes to remove the loose particles (but we couldn't get rid of all aluminum oxide marks).
Corner 2: Vertical L4C s/n 127 (replaced s/n X-45)
Don't have torque values for 10-24 generic bolt in our procedure so I went with a value of 22.8 inch-lbs obtained from engineersedge.com (these are bolts which are used to secure the Vert L4C down.
Installation of Remaining Capacitive Position Sensors (CPS)
Due to issues with soldering flux for some of our Class-A CPS's, we were short Class-A CPS's. We are going to use some TEMPORARY Class-B CPS's instead (these are only to be used for testing, and must be removed before the system is installed in a BSC Chamber).
Flexure Serial Numbers
While we're at it, thought I'd also post the s/n's for the Flexures. Note---these are the second set of Flexures installed on this assembly. We installed a second set in the hopes of remedying the "twist" in the system we observed (it didn't help). Here are the Flexures & their locations:
Corner1
0-1: s/n 142
1-2: s/n 127
Corner2
0-1: s/n 144
1-2: s/n 128
Corner3
0-1: s/n 133
1-2: s/n 138
Assy#3
Plates removed from oven & some taken to Staging for helicoiling.
The main network connect at LHO is undergoing planned maintenance this weekend at pnnl. The backup connection went down during this work. It is back up as of 7:30 pacific. The maintenance on the main connection is scheduled to complete 2pm pacific today.
Betsy, Lisa Betsy and I tried to clean the silver coated primary mirror (D1000075-v1) of the H2 OAT Transmon telescope. We did as follows: 1) Blow off the dust from the mirror 2) Soak the mirror (but not the surface) in DI water + 1% liquinox for about 10 minutes 3) Scrub the edge and the back with the soapy solution 4) Remove the soap with DI water At this point we noticed that the back surface and the barrel still had marks (I think they used a pencil or something similar to define the alignment reference lines before scribing them). So we decided to scrub with methanol to try to remove these lines. By doing that, we noticed that sticky brownish stuff remained attached to our wipes..(see picture). We locate the problem in the bevel at the edge of the coating. We continued to wipe down (kind of aggressively) until the wipes remained clean. So, we can summarize the procedure with: 5) Wipe down with methanol the barrels, in particular the bevel, and the back surface, until the wipes remained clean. 6) Sticky stuff were also present at the very edge of the surface. We removed them by wiping (more gently) with methanol We might have removed some pieces of the small area at the edge of the mirror where the coating was damaged. After that, we moved to the surface. We tried to remove some of the particles on the surface by wiping down with methanol, but very gently, as we worried that we could damage the coating. We are sure we removed at least one spot, which made us think that these spots are not inside the coating. However, we can't remove most of them. So, the message: we are ready to do an FTIR test on the substrate, to see how the cleaning went. About the surface, we removed the dust, but we didn't really remove the spots that are there (only a very small fraction), and it is really hard to judge if wiping down with methanol really helps. I brought Keita and Bram to look at the mirror, and we tried again, unsuccessfully, to attack some of the spots. By looking at the mirror with an inspection lamp showed greenish halos and thousands of spots all around the surface (those probably due to the coating itself). So, the plan is to go on with the FTIR test. For the surface, probably the best idea we had so far is to leave it as it is.
Joe did the FTIR test on the substrate today. We focused on the back side of the optics were the (pencil?) marks are, a piece of the barrel, and the bevel all around the coating, which was the most dirty part. Results in 1-2 weeks.
Cheryl took pictures of the surface of the mirror. You can see a wide collection of scratches, bubbles and splatters on the surface. The tiny points are most likely imperfection of the coating itself. Some of the big splatters could be removed, but not easily.
Construction of H2 PSL chiller room Mid Columbia Forklift arrived on site Boom truck rental delivery Cleaning of BSC7 dome
> .5 micron particle counts plots attached for locations in the labs and LVEA. They were zero during this time at mid X. LVEA locations: 3 ISI cleanroom 4 SUS cleanroom 5 "beer garden" 7 near previous location of H2 electronic racks lab locations: 1 Optics Lab 1 2 Vacuum Prep Lab 3 Bake Room
We are proud to announce that we have finished vacuuming and wiping down the BSC-7 dome. Post-work FTIR samples have been taken and the conflat has been returned to its original location (or the nearest parallel dimension) and torqued down to spec. The dome is ready to be reattached on Monday morning.