Displaying reports 79821-79840 of 84546.Go to page Start 3988 3989 3990 3991 3992 3993 3994 3995 3996 End
Reports until 10:22, Friday 07 December 2012
H1 SEI
hugo.paris@LIGO.ORG - posted 10:22, Friday 07 December 2012 (4860)
HAM3-ISI - Commissioning Work

Transfer functions and a linearity tests were measured on HAM3-ISI earlier this week.

The linearity tests looks good. Variations in slope are within requirements.

Transfer functions look good too. Concordance with LLO HAM3-ISI are satisfying. Some noise can be seen in high frequencies on the TFs measured with the vertical GS13s. These sensors saturated a bit during the measurement. 

HAM3-ISI has been re-locked, and worked on, since. It is currently locked. We are planning on running a new set of transfer functions, with a slightly lower gain in high frequencies, when HAM3-ISI can be unlocked.

Images attached to this report
Non-image files attached to this report
H1 IOO
giacomo.ciani@LIGO.ORG - posted 08:23, Friday 07 December 2012 (4853)
IO installation activity continued

Early this morning, Cheryl check the alignemnt. She found the beam to be:

- good on all three irises before IM1

- misaligned in the FI

- good in the two irises after the faraday (before and after IM4)

All suspension had unchanged offsets wrt yesterday, in particular:

  IM1 IM2 IM3 IM4
Pit 1000 -1750 1500 0
Yaw -700 0 0 0

 

She checked again and more thoroughly mid-morning, with the same conclusion. She took some picture (to be posted soon)

 

HAM3 ISI was then locked, which did not visibly change the beam reaching HAM2. This allowed David and Luke to torque to spec (100 in lb) all clamps on HAM3 ISI: MC2, PR2, all IO components, cable clamps and ISC breadboard to the table (but not the componenets to the breadboard).

HAM3 ISI was then unlocked (again with no visible shift in the beam) and we proceeded to re-aligning the FI, using IM1 and IM2 (only yaw, as pitvh looked good). Then we used IM3 (again, only yaw) to center the beam on the iris between IM3 and IM4. Finally we centered the beam on PR2 using IM4 in both pitch and yaw (we replaced the PRM surrogate with an AR-AR optic with the same wedge and thickness, to increase the visibility of the transmitted baem). Final offsets:

  IM1 IM2 IM3 IM4
Pit 1000 -1750 1500 -1050
Yaw -1500 -750 500 7050

And it was lunch time...

After lunch, we placed an iris after the PRM surrogate to be used as a reference for the beam out of IM4, and for red laser alignment. We then removed the yaw offset from IM4, and used the pushers to rotate it back untill the beam was centered again on the iris (about 1/4 mm, or less than half a turn). Other miscellana:

- clamp adapeter and clamp placed on the short east side of MC1

- all non-temporary (and a few temporary) clamps torque to spec (100 in lb): MC1, MC3, IM1-4 (at present, with 2 temporary clamps each), MC refl telescopes, IO telescope, IO steering mirrors.

- visble laser set-up ans aligned to the irises. Form now on we can work in laser safe codnition using the red laser.

H1 SEI
vincent.lhuillier@LIGO.ORG - posted 17:31, Thursday 06 December 2012 (4858)
Transfer functions ISI-BSC1

I have attached the transfer functions measured on BSC1. They are slightly different (rigid body modes ~5Hz) from those measured at LLO on BSC1 (similar payload) and BSC8 (the same ISI).

LHO BSC1:
https://svn.ligo.caltech.edu/svn/seismic/BSC-ISI/H1/ITMY/Data/Figures/Transfer_Functions/Measurements/Undamped
H1_ISI_ITMY_TF_L2L_Raw_from_ST1_ACT_to_ST1_CPS_2012_12_04.fig
H1_ISI_ITMY_TF_L2L_Raw_from_ST1_ACT_to_ST1_L4C_2012_12_04.fig
H1_ISI_ITMY_TF_L2L_Raw_from_ST1_ACT_to_ST1_T240_2012_12_04.fig
H1_ISI_ITMY_TF_L2L_Raw_from_ST2_ACT_to_ST2_CPS_2012_12_04.fig

H1_ISI_ITMY_TF_L2L_Raw_from_ST2_ACT_to_ST2_GS13_2012_12_04.fig

LLO BSC1:
https://svn.ligo.caltech.edu/svn/seismic/BSC-ISI/L1/ITMY/Data/Figures/Transfer_Functions/Measurements/Undamped
LLO_ISI_BSC1_TF_L2L_Raw_from_ST1_ACT_to_ST1_CPS_2012_11_07.fig
LLO_ISI_BSC1_TF_L2L_Raw_from_ST1_ACT_to_ST1_L4C_2012_11_07.fig
LLO_ISI_BSC1_TF_L2L_Raw_from_ST2_ACT_to_ST2_CPS_2012_11_07.fig
LLO_ISI_BSC1_TF_L2L_Raw_from_ST2_ACT_to_ST2_GS13_2012_11_07.fig

LHO BSC8:
https://svn.ligo.caltech.edu/svn/seismic/BSC-ISI/H2/ITMY/Data/Figures/Transfer_Functions/Measurements/Undamped/
LHO_ISI_BSC8_TF_L2L_Raw_from_ST1_ACT_to_ST1_CPS_2012_05_21.fig
LHO_ISI_BSC8_TF_L2L_Raw_from_ST1_ACT_to_ST1_L4C_2012_05_21.fig
LHO_ISI_BSC8_TF_L2L_Raw_from_ST2_ACT_to_ST2_CPS_2012_05_21.fig
LHO_ISI_BSC8_TF_L2L_Raw_from_ST2_ACT_to_ST2_GS13_2012_05_21.fig




 

H1 SEI
hugh.radkins@LIGO.ORG - posted 16:35, Thursday 06 December 2012 (4857)
Rework Cables at Corner3 WBSC1
There were some oddities in the transfer functions Vincent collected so we went to the ISI.  Corners 1 and 2 looked pretty good but Corner 3 never does.  So we reworked it some to hopefully improve the results--yet to be determined.
A couple before and after images not all that revealing.  It is obvious we did something but not that obvious in the photos that it is better--you gotta be there!
Images attached to this report
LHO General
corey.gray@LIGO.ORG - posted 16:04, Thursday 06 December 2012 (4856)
Day Operator Summary

EX
In-chamber cleaning continues
New HVAC system for the Lab is now online after being serviced today

BSC1
Hugh & Vincent worked on/around cabling up on the BSC-ISI to troubleshoot some noise on the BSC-ISI

IO Work
The team planned on checking torque-ing for MC2 (requiring HAM3 ISI to be locked), and alignment work continues (so we've remained in Laser HAZARD all day)

Rest of Day's Activity

H2 INS
bubba.gateley@LIGO.ORG - posted 13:12, Thursday 06 December 2012 (4855)
BSC 5
We air brushed lower sections 1,2,3,&4 and floor sections 1,2,&3. We also completed the hand brushing on the fins. Stand down on ICC for the day to torque bolts on HAMs 4&5 doors.
LHO General
patrick.thomas@LIGO.ORG - posted 13:07, Thursday 06 December 2012 - last comment - 16:37, Tuesday 11 December 2012(4854)
dust monitors
The dust monitor at location 8 in the LVEA, labeled S, gave a calibration warning and was turned off. This was in the small clean room between HAM 2 and 3 with the auxiliary optics. Today I removed the dust monitor at location 1 in the end Y VEA labeled L and replaced S with it.
Comments related to this report
patrick.thomas@LIGO.ORG - 16:37, Tuesday 11 December 2012 (4895)
Attached are plots of dust counts > .3 microns and > .5 microns in particles per cubic foot from approximately 6 PM Dec. 5 to 6 PM Dec. 6. Also attached are plots of the modes to show when they were running/acquiring data.
Non-image files attached to this comment
H2 INS
bubba.gateley@LIGO.ORG - posted 08:52, Thursday 06 December 2012 (4852)
BSC 5
Brushed with drills all sections from bottom of collar to floor and began hand brushing fins yesterday.
H1 IOO
giacomo.ciani@LIGO.ORG - posted 01:20, Thursday 06 December 2012 (4850)
FI isolation ratio, power budget and more HAM2 activities

[David, Rodica, Luke, Giacomo]

After the HAM3 ISI was unlocked this morning, we verified that the table moved small enough that the MC was still flashing.

We then verified the alignment through the HAUX and FI up to IM4, that was still good.

We prepared two iririses at the the nominal height of the beam on the table, placed them before and after IM4 and aligned them to the IR beam to serve as references for the visible laser we will be using for alignment of the auxiliary optics. However, we then realized that IM4 only "nominally" aligned in both pitch and yaw, so this will need to be tweaked tomorrow.

After that, we aligned the REFL beam to the input beam using the PRM surrogate, and the backward rejected beam to the HAM1/2 viewport; we then measured the input beam power (505 uW), and tried to measure the power in the backward beam reflected off of MC3, but we could not distinguish it from the background. Based on the uncertainty on the background measurement (25 nW) we estimated an isolation ratio > 40 db.

Finally, we measured the power in various location of the forward beam (in uW +- 1 uW):

after MC3 = 524

after IM1 = 504

after IM2 = 505

after IM3 = 494

after IM4 = 494

after PRM sur = 15

This yield a 96.2% transmission through IM1 (but we have the wrong polarization), a 97.8% combined "transmission through FI and reflection off of IM3" (although reflection through IM3 should be basically 100%, as it is in the right polarization) and a 3% (as expected) transmission thorugh the PRM surrogate.

Based on these numbers, the REFL beam at at the HAM1/2 septum viewport should be 469 +- 5 uW.  We measured 466 uW: apparently we didn't loose any beam on the way... :-)

LHO General
patrick.thomas@LIGO.ORG - posted 19:37, Wednesday 05 December 2012 (4851)
plots of dust counts
Attached are plots of dust counts > .3 microns and > .5 microns in particles per cubic foot from approximately 6 PM Dec. 4 to 6 PM Dec. 5. Also attached are plots of the modes to show when they were running/acquiring data.
Non-image files attached to this report
H1 PSL
david.barker@LIGO.ORG - posted 18:06, Wednesday 05 December 2012 (4849)
diode room temperature fluctuation

we just got an alarm on the diode room overtemp. Looking at a trend, it appears the room temperature started fluctuating at 4am this morning, and recently got very cold, and the heated up to the alarm point at 70F. It is cooling down at the moment. Michael was notified, he will take a look at it tomorrow.

LHO General
cheryl.vorvick@LIGO.ORG - posted 16:13, Wednesday 05 December 2012 (4847)
Ops Day Summary:
- Cabling around BSC1
- IO work in HAM2
- SEI work on HAM3
- Changes to BSC1 IOP watchdogs
- Low battery on Mid-X fire panel
- Reboots of the OPS machine to restore both screens
H1 ISC
corey.gray@LIGO.ORG - posted 14:05, Wednesday 05 December 2012 - last comment - 14:15, Thursday 10 January 2013(4845)
H1 EX TransMon Suspension Green-Light QPD Sled Complete (& In Storage)

(Corey, Keita)

My mode-matching lessons from master Jedi Kawabe continue with the building of the EX Green QPD Sled.  This Sled is one of two on EACH Transmission Monitor Suspension (TMS); the other is an IR QPD Sled (to be assembled next).  We actually built this Sled twice.  After completing it the first time, Keita noticed, "this sled looks like EY.  It's supposed to be a mirror image!"  It was all a learning experience.  So, we ended up re-building the sled (it went much quicker since we, in essence, already had an assembly dry run).

Once the Sled was completed, we draped wipes over all optical components, wrapped the entire assembly in foil, double-bagged it, and placed the entire thing in a large plastic bin for storage under our Optics Table in the Optics Lab (the HAM1WFS Sled is also stored here). 

Keita has plots and data from our mode matching measurements and will post a more thorough document about our EX Green Sled work to the DCC.

Note:  The "J-Clip" Black Glass Beam Dumps on our Steering Mirrors are tough to install.  There's a screw on the mount which interferes with the J-Clip and makes installing/removing these parts tough.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 12:40, Tuesday 18 December 2012 (4960)

I have uploaded all photos for this EX Green Sled on ResourceSpace, here.

corey.gray@LIGO.ORG - 14:15, Thursday 10 January 2013 (5067)

Forgot to measure distance between optical components on this Sled, so it was opened up and these measurements were made.

For measurements below, the lenses are measured on the "backface" of their Lens Holder.  The Mirrors & Beam Splitters are measured from their glass "front faces".  The QPDs are measured from the QPD Housing plate (D1002110).  Measurements were measured with a scale & all measurements are in mm.

  • L1 to BS1 = 35
  • BS1 to QPD1 = 88
  • BS1 to L2 = 233
  • L2 to SM1 = 68
  • SM1 to SM2 = 59
  • SM2 to L3 = 282
  • L3 to SM3 = 117
  • SM3 to QPD2 = 77
LHO VE
kyle.ryan@LIGO.ORG - posted 12:11, Wednesday 05 December 2012 (4843)
IP9 pump #1 (pumpA) taken offline briefly
Was considering changing from STEP to FIXED (5000V) voltage but didn't
H1 CDS
david.barker@LIGO.ORG - posted 11:53, Wednesday 05 December 2012 - last comment - 17:41, Wednesday 05 December 2012(4841)
IOP model for h1seib1 modified to permit 10 Dolphin IPC errors per second

WP 3589

I modified the IOP model for the BSC1 SEI system (h1seib1) to permit up to 10 IPC receive errors per second from the h1iopsusb123 sender (SUS ITMY). We are currently experiencing about 5 errors per day on this Dolphin link, we currently dont know what the problem is. We hope the upgrade to RCG2.6 will resolve this issue.

I did a cursory test of the IPC watchdog by PANICing the SUSB123 DACKILL and verifying that the SEIB1 tripped. It is not possible to test that an error rate of >10 will trip SEIB1 without rebooting the SUSB123 and possibly disrupting the mode cleaner work.

Comments related to this report
david.barker@LIGO.ORG - 17:41, Wednesday 05 December 2012 (4848)

We had a single IPC error this afternoon and the SEIB1 IOP ran through it without DACKILL'ing the ISI. So far, so good.

H1 SEI
hugo.paris@LIGO.ORG - posted 17:44, Tuesday 04 December 2012 - last comment - 09:26, Wednesday 05 December 2012(4831)
HAM3-ISI - Unlocked, Balanced and Measurements Running

Jim, Hugo,

IO signed off on HAM3 this afternoon. We went in and balanced the ISI. The payload is not supposed to change anymore. We recorded the CPS readouts for both locked and unlocked configurations:

  Locked (Counts)

Unlocked 
(Counts)

Shift
(Counts)
H1 -380 87.98 467.98
H2 170 504.36 334.36
H3 -60 139.12 199.12
V1 120 145.64 25.64
V2 -350 -518.82 168.82
V3 250 108.37 141.63

Requirements are (E1000309-v12): 
shift<1600cts 
Readouts<2000cts

The locked/unlocked shifts are way within requirements. We are looking forward to hearing back from IO on how unlocking affected them, if it did.

All electronics are powered back up. covers are held up with clippers and testing signs are on. The first measurements for the final in-chamber testing of HAM3-ISI will start tonight.

 

Note: The HAM-ISI master model was updated by LLO today. We are still running the previous version. I will soon transfer the update here.

Comments related to this report
hugo.paris@LIGO.ORG - 09:26, Wednesday 05 December 2012 (4839)

Giacomo, Hugo,

We checked that the cavity was still flashing with the ISI unlocked. It is.

We then tried turning on the damping and the controllers level 2. The cavity was still flashing.

H1 SUS
betsy.weaver@LIGO.ORG - posted 15:43, Tuesday 04 December 2012 - last comment - 12:19, Wednesday 05 December 2012(4828)
PR3-01 Left Primary Prism mis-glued (again) in position

Yesterday I spent the day rebuilding the HXTS prism gluing measurement apparatus in order to accomodate the HLTS sized optic.  At the end of the day I finally glued the prism on.  Today, Gerardo removed the fixturing and sees that the prism is 2mm out of spec in the pitch-direction.  Ugh.  The d-value direction (or distance up from the scribe line) has been corrected.  Both of these dimension differences from the first round of gluing can be seen in the attached picture where the phantom footprint from the last glued on prism was.  The new prism should line up with the phantom line on the left end of the prism, but should remain at the current horizontal position on the line.  I estimate that this error would induce roughly ~40mRad of pitch error.  Because this glue bond is still somewhat fresh (only an overnight room temp cure) and the position error is so large, Gerardo is placing the prism down into an acetone bath for the night to remove it. 

Mulligan-again for tomorrow. 

It is unfortunate that you cannot check any of the setup measurements once the prism is in the fixture and glued down.  We *think* this happened because the measurement apparatus is not very good at staying alignment when traveling up and down (away from the optic) in order to adjust for focus.  You focus on the scribe line on the optic during setup and then you must slide up to focus on the notches on the prism which are many mm of focus different.  Likely this focal plane change has some sideshift (on the order of the 2mm error we now see).  I'm not sure what a good fix for this is this.  I'll try removing some of the brackets between the traveling bore-scope and the horizontally mounted height guage.

Images attached to this report
Comments related to this report
betsy.weaver@LIGO.ORG - 12:07, Wednesday 05 December 2012 (4842)

Playing with the measurement apparatus today, Gerardo and I discovered that the bore scope 1) wobbles up and down relative to g, and 2) runs downhill by ~3mm over a 300mm length due to the weight if itself hanging off the end of the horizontally mounted height guage (see pic attached).  Both piggy-backed jacks have slop in this direction.  I can remedy 2) via shimming the entire stack of joints, but I'm not likely to be able to improve 1) without rearranging the entire measurement motivation.  Hopefully 2) was the larger contributor to Monday's error.  The top portion of the apparatus is the same as what I used to glue prisms to MC2 and PR2, so we would have see some slop then as well, however since the optics were smaller, the travel (and subsequent shifting of load) must have been less noticeable.

Images attached to this comment
betsy.weaver@LIGO.ORG - 12:19, Wednesday 05 December 2012 (4844)

Attached is the LLO gluing apparatus, shown with an HLTS optic.  It also is stacked lab jacks.

Images attached to this comment
H1 SUS
mark.barton@LIGO.ORG - posted 14:42, Tuesday 04 December 2012 - last comment - 10:59, Wednesday 05 December 2012(4824)
PR3 OL values
Mark B.

I took OL readings on PR3 (and calculated appropriate gains and offsets) after Travis installed OSEMs on PR3 and left them backed out. 

M1T1  26124.3  1.1483561  13062.15
M1T2    30353 0.98837018   15176.5
M1T3  28842.1  1.0401462  14421.05
M1LF  25990.7   1.154259  12995.35
M1RT  26134.2  1.1479211   13067.1
M1SD  28493.2  1.0528828   14246.6
M2UL  18073.3  1.6599072   9036.65
M2LL  20597.1  1.4565157  10298.55
M2UR  19602.2  1.5304405    9801.1
M2LR  17998.4  1.6668148    8999.2
M3UL -3.19153 -9399.8803 -1.595765
M3LL  23289.9   1.288112  11644.95
M3UR  24780.1  1.2106489  12390.05
M3LR    17455  1.7187052    8727.5

There's something wrong with M3UL (not fully backed out?), but I'll enter the remaining gains and offsets to the OSEMINF screen.
Comments related to this report
mark.barton@LIGO.ORG - 15:15, Tuesday 04 December 2012 (4825)
Mark B.

I entered the above gains and offsets except that I used 1.000 and -15000 for M3UL. I then created a new h1suspr3_safe.snap file. I archived the old as h1suspr3_safe20121005.snap based on its modification date, and made a spare copy of today's new one as h1suspr3_safe20121204.snap.
mark.barton@LIGO.ORG - 10:59, Wednesday 05 December 2012 (4840)
Mark B., Travis

Travis replugged the cable and M3UL came good. Its OL was

M3UL 17553.2 1.7091  8776.6

I entered the gain and offset and redid the safe.snap file (spare copy as h1suspr3_safe20121205.snap).
Displaying reports 79821-79840 of 84546.Go to page Start 3988 3989 3990 3991 3992 3993 3994 3995 3996 End