Displaying reports 62581-62600 of 82999.Go to page Start 3126 3127 3128 3129 3130 3131 3132 3133 3134 End
Reports until 16:11, Thursday 27 August 2015
H1 General
nutsinee.kijbunchoo@LIGO.ORG - posted 16:11, Thursday 27 August 2015 (20964)
Ops Day Shift Summary

(All time in UTC)

15:15 Christina opening the roll-up door, OSB receiving area

15:30 Christina done

16:36 Kiwamu to electronics area by PSL and HAM6

16:59 Sudarshan has been doing Pcal swept sine. Now done.

           Kiwamu done

17:00 Observing intent bit set. SDF hasn't been cleared at this point. See attachment.

17:34 Bubba to Mid station

18:03 Intent bit switched to Commissioning. Flipped DHARD 20-30 Hz BP filters.

18:05 Intent but switched back on

18:33 Kyle to beam tube near EY to make measurement. 300 m away from EY.

18:36 Wind picking up. Reaching 30 mph.

           Intent bit swited to Commissioning. Daneil to CER.

18:53 Daniel back. Intent bit Observing.

19:00 Calibration group taking over. Bring interferometer to down. Intent bit set to Commissioning

19:11 Kiwamu to LVEA doing OMCDCPD measurement

19:23 Fire protection Specialists back on site. Fire suppression in Network Room.

19:30 Sheila to LVEA looking for Kiwamu.

19:38 Kyle back

20:47 Sheila locking MICH

           Something water on site. Couldn't hear the guy. Let a white pick-up truck in.

21:09 Bubba done

21:42 Travis, Sudarshan, Darkhan to EY (Pcal calibration)

19:02 Hand the ifo over to Patrick

Images attached to this report
LHO FMCS (DCS)
bubba.gateley@LIGO.ORG - posted 15:56, Thursday 27 August 2015 (20963)
New DCS room fire suppression system
Installation began yesterday on the fire suppression system for the new DCS room by a 2 man crew from Fire Protection Specialist. They started working on conduit runs for the warning lights, pull handles and abort switches.

This portion of the install is expected to be completed by EOB tomorrow.

Long lead items such as the tank and agent are expected to arrive next week and will be installed along with the piping and spray nozzle.

Images attached to this report
H1 ISC
sheila.dwyer@LIGO.ORG - posted 15:21, Thursday 27 August 2015 - last comment - 03:46, Friday 28 August 2015(20961)
changing RF phase in HAM6 racks.

Evan, Sheila

While the IFO was down for some calibration measurements, we made another attempt at phasing AS36. 

We first redid the dark offsets, this was an important step.  Then we locked the bright michelson with 22 Watts of input power. 

We steered the beam onto each quadrant of AS_A by maximizing the DC counts, then phased 36 to minimize Q.  There were several things that made this seem much more promising than any of our previous attempts to phase these WFS:

Both of these things are firsts for these WFS as far as I'm aware, so this seemed like real progress.  

We started to do the same procedure for AS_B 36, but after we phased the first quadrant the phase jumped.  Kiwamu was in the rack working on the calibration measurements of the DC PDs at this time and reported that he had plugged a signal into the patch panel.  After this I looked at the A signals again, and they did not make sense any more. I tried repeating the procedure above for A, and found that the phases needed to minimize Q with the light maximized on each quadrant had changed by -15, -10, 0, and -20 degrees for quadrants 1,2,3,4.  

It seems like we need to make a thorough check of the HAM6 racks before we continue trying to make sense of AS WFS.  

Just for the record the momentarily sane phasings were:

segment phase (degrees)
1 -155
2 -175
3 -165
4 -158
Comments related to this report
evan.hall@LIGO.ORG - 03:46, Friday 28 August 2015 (20978)

Stefan and I did a wiggling test of the cables in the HAM6 rack while the interferometer was locked.

We watched AS90I, AS45Q, and all the quadrants of the AS WFS (36 and 45 MHz). The only thing we saw was a 5% fluctuation in AS90I in response to the 90 MHz LO cable being wiggled. [Although once the beam diverter is closed and the AS90 signal is attenuated, the response to wiggling is much stronger—something like 20% to 40% fluctuation.]

H1 CAL (CDS)
jeffrey.kissel@LIGO.ORG - posted 13:30, Thursday 27 August 2015 - last comment - 17:28, Monday 31 August 2015(20958)
IFO Taken down to take LSC and END SUS DAC DuoTone Timing Checks
J. Kissel, K. Kawabe, S. Karki

We've broken observation mode such that we can enable the DAC DuoTone timing readbacks on the front ends that are responsible for DARM control, i.e. h1lsc0, h1susex, and h1susey. We needed to take the IFO down for this because the last channel on the first DAC cards for the end station SUS are used for top-mass OSEMs for damping the suspensions. If the damping loops get a two sign waves at 960 and 961 [Hz] instead of the requested control signal for one of the OSEMs, then we get bad news.

Here are the times when the DAC DuoTone switches were ON for the following front ends:

h1susex and h1susey --- 19:04 to 20:04 UTC (12:04 to 13:04 PDT)
h1lsc0 --- 19:16 to 20:06 UTC (12:16 to 13:04 PDT)

Though all relevant channels (ADC_0_30,  ADC_0_31, DAC_0_15) are free on the h1lsc0 front end, we elected to turn the DAC DuoTone off, so that we aren't in danger of an oscillitory analog voltage being sent around the IO chassis that's used to measure the OMC DCPDs.

Data and analysis to come. 

The IFO will be staying down for a few hours, while we finish up some electronics chain characterization of the OMC DCPD analog electronics (along with some other parasitic commissioning measurements).
Comments related to this report
keita.kawabe@LIGO.ORG - 16:24, Thursday 27 August 2015 (20962)

I showed Sudarshan which signal to look at and how to analyze them. He will make an awesome drawing of how things are connected up in this alog.

The first and second attachment shows the duotone timing of the signals pulled from the IOP channels (all 64kHz). The results are summarized in the following table.

Measurement time (UTC)

IOP ADC0 Ch31 (direct) (us) ADC0 Ch30 (loopback) (us) Round-trip (us)
27/08/2015 19:16:11.0 LSC0 7.34 83.78 76.44
SUS_EX 7.25 68.90 61.65
SUS_EY 7.26 68.93 61.67
27/08/2015 22.32:20.0 ISC_EX (PCALX) 7.32 68.93 61.61
ISC_EY (PCALY) 7.26 68.90 61.84

As per yesterday's alog, duotone is about 7.3usec delayed behind LSC ADC, and actually this turned out to be the case for all ADCs.

According to Zuzsa Marka, duotone was "delayed a bit above 6 microseconds compared to the GPS 1pps" (report pending), so probably this means that the ADC timing (i.e. time stamp of ADC) is decent.

Duotone round trip delay for all IOPs except IOP-LSC0 is about 61us or about 4 64k-clock cycles. For LSC0, this was about 5 64k-clock cycles.

I don't know where the difference comes from. This is totally dependent on how the 64kHz ADC input is taken, routed to 64kHz DAC when "DT DAC" bypass switch is in "ON" position (third attachment), and finally output by DAC, but I don't think there should be difference between LSC and everybody else. At least LSC DAC timing doesn't come into the DARM timing.

The next table is for 16kHz pcal channels on the frame. The measurement results as well as the channel names are shown in the last attachment.

UTC user model ADC0 Ch31 (direct in)
(raw, raw-decimation)
loop back Round trip
27/08/2015 22.07.23.0 CAL-PCALX (63.30, 7.37)

ADC0 Ch30 (direct in without AI and AA)
(raw, raw-decimation)
(124.92, 68.99)

61.62
ADC0 Ch28 (with AI and AA)
377.72
 
CAL_PCALY (63.24, 7.31) ADC0 CH30 (direct in without AI and AA)
(raw, raw-decimation)
(124.89, 68.96)
61.65
ADC Ch28 (with AI and AA)
377.07
 

For Ch31 and Ch30, the routing is done bypassing the user model, the signals are merely imported into the user model and decimated.

Sudarshan found the 4x decimation filter delay to be 19.34deg or 55.93us at 960.5Hz, and "raw-decimation" number is obtained by just subtracting this from the raw number. This is consistent with the 64kHz result, so from now on we can look at 16kHz signals as far as pcal is concerned.

I don't know anything about AA and AI, so I'll leave the analysis to Sudarshan.

Relevant scripts and dtt templates are in /ligo/home/keita.kawabe/Cal/Duotone.

Images attached to this comment
sudarshan.karki@LIGO.ORG - 17:28, Monday 31 August 2015 (21043)

Keita's alog explained the timing on Duotone to ADC and DAC to ADC loop as well. Additionally in pcal, channel 28 is routed through the analog AI and AA chasis. The details about how the channels are connected can be found in the attached schematics.

 

From the schematics we can see there are three (3) 4X decimation filters (two downsampling and one upsampling) in this particular chain (Channel 28). This amounts 3*55.93 us = 167.79 us of delay (each of these filter produce phase delay of 19.34deg or 55.93us at 960.5Hz). The analog AA and AI chassis produce phase delay of 13.76  degrees which amounts to about  39.82 us at 960.5 Hz from each chassis totaling in 79.64 us of time delay.

Total Delay = 3*55.93+2*39.82 =247.73 us.

Column 3  contains the measured (raw) time delay and "raw- total delay".

Column 4 contains the roundtrip time (raw-timedelay-7 us) = ~ 122 us (8-64 KHz cycle).

UTC Channel ADC CH 28 LOOP BACK (FILT DUOTONE) Round trip
27/08/2015 22.07.23.0
CAL_PCALX

ADC0 Ch28 (with AI and AA)

(raw, raw-(3*decimation+2*analog AA/AI))

(377.72, 130.29)

 122.92
CAL_PCALY

ADC Ch28 (with AI and AA)

(raw, raw-(3*decimation+2*analog AA/AI))

(377.07, 129.64)

 122.33
 

 

UTC user model ADC0 Ch31 (direct in)
(raw, raw-decimation)
loop back Round trip
27/08/2015 22.07.23.0 CAL-PCALX (63.30, 7.37)

ADC0 Ch30 (direct in without AI and AA)
(raw, raw-decimation)
(124.92, 68.99)

61.62
ADC0 Ch28 (with AI and AA)
377.72
 
CAL_PCALY (63.24, 7.31) ADC0 CH30 (direct in without AI and AA)
(raw, raw-decimation)
(124.89, 68.96)
61.65
ADC Ch28 (with AI and AA)
377.07
 
 
Images attached to this comment
H1 PSL
jeffrey.bartlett@LIGO.ORG - posted 12:17, Thursday 27 August 2015 (20957)
PSL Chiller 60 Day Trends
Posted below are the plots for the PSL chiller for the past 60 days. The regeneration of the crystal chiller DI-Filter is good news. We went from used 70% of capacity to 50% capacity. Jason is looking into calibration questions with flow sensors on both chiller units.    
Images attached to this report
H1 DetChar
nairwita.mazumder@LIGO.ORG - posted 11:02, Thursday 27 August 2015 (20956)
LHO DQ shift 24th-26th August
Detailed report: https://wiki.ligo.org/DetChar/DataQuality/DQShiftLHO20150824

  • There were 4 science locks between 24-26th August with ~20% total duty cycle.
  • Calibration has started since Monday, 24th August.
  • Tuesday was a heavy maintenance day at LHO. Two small locks on 24th and 25th had less than 5 minutes span. But mostly focussed on the long locks.
  • The locks had EY 60Hz magnetic glitches which might have caused the big dips in the inspiral range. (PEM-EY_MAG_EBAY_SUSRACK)
1st day Lock:
  • Steady lock with inspiral range around 62 MPC.
  • Interferometer lock was broken to start Calibration at 16:05 UTC. (alog)
  • Other than few loud glitches (which caused some dip in the inspiral range) lock looks pretty clean.
  • High SNR glitch rate was very low throughout the lock.
  • 60Hz magnetic glitches can be seen at End Y
  • Hveto was not that much effective for the triggers above ~100Hz. A few angular channels came up as the most significant in hveto.
  • The first dip in the inspiral range seems to be related to some magnetometer in seismic (as well as in suspension) rack at End Y.
  • There was no major seismic activity during this ~2.5 long lock.
2nd day Lock:
  • Steady lock with a inspiral range of 65 MPC. Possible lock loss reason : delivery truck was passing by (alog) and ASC-POP glitch - " ~16s before and ASC-PRC2 starts to oscillating at about the same time ( and the oscillation became really huge about ~ 6s before lockloss). They were both high frequency (>128 Hz)". (Lock loss plot)
  • Some non-stationarity at the low freqquency (below 20Hz) between 12:00 to 13:00 UTC and nearly end of the lock
  • Small variation in the spectrum below 40Hz
  • Loud Glitch rate was low except the time between 12:00 to 13:00 UTC, where we had a loud glitch causing a dip in inspiral range (came down to ~10MPC)
  • Most of the loud glitches visible in glitchgram were vetoed out by hveto, might be related to PEM accelerometer or seismic channel.
  • There was an earth quake at Northern Mid-Atlantic Ridge with magnitude 4.9 at 13:23 UTC which might be the reason of the last huge dip in the inspiral range.
  • Few loud events (New SNR >7.5) were seen in BBH search and low-mass CBC search.
3rd day lock:
  • The pattern is same as previous two days with inspiral range ~60MPC which eventually ends up at ~68MPC
  • After Tuesday's maintenance few new features can be seen in the spectrum (alog)
  • ETMY saturation occurred several times during this lock.
  • 1 Hz comb (offset by 0.5 Hz) was found at below 70Hz which was believed to be related to PEM channels, also some excess noise in PRCL. This issue has been fixed (alog).
  • This lock also had some very loud glitches few of them are EY magnetic glitches.
  • ASC-X_TR_A_PIT_OUT_DQ and ASC-REFL_B_RF9_Q_YAW_OUT_DQ had significant contribution on Hveto. PEM-EY_MAG_EBAY_SUSRACK_X_DQ came up as the most significant channel in iDQ as well as the winner of 3rd round Hveto.
Note: UPV and STAMP PEM were not up for any of these days. The loud glitches need be followed up more thoroughly.
H1 CDS (DAQ)
david.barker@LIGO.ORG - posted 10:41, Thursday 27 August 2015 (20955)
CDS model and DAQ restart report, Wednesday 26th August 2015

ER8 Day 10. No restarts reported.

H1 SYS
jameson.rollins@LIGO.ORG - posted 10:25, Thursday 27 August 2015 (20954)
new OBSERVATION_OVERVIEW screen

New OBSERVATION_OVERVIEW overview screen

I have added a new screen that sumarizes the overall OBSERVATION status of the detector:

$USERAPPS/sys/common/medm/OBSERVATION_OVERVIEW.adl

It is meant to be informative and (hopefully) self explanatory for the operators.  It includes all things going into determining OBSERVATION status:

When the system is not ready the screen looks like this:

The EXCITATION monitor will turn red if there are any excitations present.  Once GRD-IFO_OK is ready, and there are no excitations, the READY box will turn green.  Once the operator then sets the INTENT bit to "UNDISTURBED", the whole box will turn green to indicate that we are in OBSERVATION MODE:

Hopefully it is self explanatory, but please let me know if there are any questions.

I have embeded this screen into to the GUARDIAN_OVERVIEW screen as well.

Images attached to this report
H1 General
edmond.merilh@LIGO.ORG - posted 08:23, Thursday 27 August 2015 (20953)
Shift Summary - Owl

ALL TIMES IN UTC

Arrival: IFO is unlocked. Sheila and Evan in and out of the LVEA taking ASC measurements. Wind calm. Seismic calm. Patrick on Evening duty.

On Site: Kissel, Balmer, Driggers, Hall, Dwyer, Hoak, Cahillane and Darkhan

ACTIVITY LOG:

LOCK LOG:

Summary:

H1 PEM (ISC, PEM, SUS)
richard.mccarthy@LIGO.ORG - posted 08:23, Thursday 27 August 2015 (20952)
Testing of Comb Frequency induced when connecting RF to PEM
IN a follow up to the work done Tuesday and Wednesday that introduced the 1Hz comb in the PRCL, SRCL path and removed it the following morning by disconnecting the 9 and 45MHz LO signals to the PEM interface chassis for the room antenna.   

With the IFO locked I reconnected the 9MHz cable and the 1Hz comb was present.  I then disconnected it and tried to work with the 45MHz.  The IFO is far more sensitive to work with the RF distribution chassis and we ended up losing lock.
Once Ed M. re aligned and  got the system locked again we did not see the 1Hz with the 45MHz connected to the PEM.  I then installed a Baluns on both the 9MHz and 45MHz lines and the signal did not show up in the spectrum.  
We will leave it connected as is until Tuesday when we can move the baluns to a less intrusive location probably at the PEM rack.   They are now on the distribution chassis somewhat blocking the connections next to them. Hopefully this has not introduced any other problems.
H1 General (DetChar)
edmond.merilh@LIGO.ORG - posted 03:26, Thursday 27 August 2015 (20951)
Observation Intent Bit/ Observing Mode
H1 CAL (CAL)
craig.cahillane@LIGO.ORG - posted 00:26, Thursday 27 August 2015 - last comment - 18:45, Thursday 27 August 2015(20946)
Preliminary Strain Uncertainty Carpet Plots
C. Cahillane

I have managed to use ER7 data produce preliminary carpet plots of frequency vs. strain magnitude and phase based on the Uncertainty Estimation paper T1400586.
The code that generates these plots may be found here: /ligo/svncommon/CalSVN/aligocalibration/trunk/Runs/S7/Common/MatlabTools/strainUncertainty.m

Darkhan recently did a similar study to this looking at error in magnitude and phase of Delta_L_ext when kappa_C, kappa_A, and f_c changed.  
My study currently looks at the error in magnitude and phase of strain when the magnitude and phase of kappa_tst and kappa_pu vary, as well as kappa_C and f_c.  (Recall that in general kappa_tst and kappa_pu can be complex.)

Right now I believe there is a serious error in the code, because the plot of the optical gain (plot 5) and the plot of the cavity pole (plot 6) show there is absolutely no error in strain even if these values differ greatly from the expected value.  The cavity pole varies by up to +- 100 Hz and does not vary by more than 1%.  The result is robust: I have calculated the strain using two independent methods and still I get these odd results.  These are my results right now, and this is why I call these plots preliminary.

I do believe the magnitude kappa_tst (plot 1), phase kappa_tst (plot 2), magnitude kappa_pu (plot 3), and phase kappa_pu (plot 4) plots look sensible.  Any phase in kappa_tst is generally intolerable for high frequency phase information, while phase in kappa_pu yields high error in low frequency phase information.  Since we do not expect any phase component at all in kappa_tst and kappa_pu, this makes sense.
Also, the magnitude of kappa_tst and kappa_pu must be tracked carefully at high and low frequency respectively.  10% errors in these magnitudes are enough to give more than 9% errors in strain magnitude.

Note that these results use ER7 data (GPS_start = 1116990382).  I'll soon be able to get ER8 data when it is all available (go calibration week!)


Non-image files attached to this report
Comments related to this report
craig.cahillane@LIGO.ORG - 00:41, Thursday 27 August 2015 (20949)CAL
I believe my "no uncertainty" issue with the optical gain and cavity pole may be related to this graph.
The 1/C*d_err term in blue is completely overwhelmed by the A*d_ctrl term.  My reconstruction of hMag may be improperly weighting these two factors.
That is why the Actuation terms (kappa_tst and kappa_pu) have sensible errors, but the Sensing terms (kappa_C and f_c) don't have any effect whatsoever.
Non-image files attached to this comment
craig.cahillane@LIGO.ORG - 18:45, Thursday 27 August 2015 (20969)
I have posted some less preliminary plots of the ER7 data.  I have now dewhitened the data, which has properly scaled the gain such that the inverse sensing term is no longer overwhelmed by the actuation term.  
The spikes everywhere are due to a single-pass fft I have taken.  I am working on a proper fft algorithm now.
Non-image files attached to this comment
H1 ISC
stefan.ballmer@LIGO.ORG - posted 00:08, Thursday 27 August 2015 - last comment - 15:02, Thursday 27 August 2015(20947)
trying to phase the AS_B 90MHz signals - but !?!
While trying to phase AS_B 90MHz signals (hooked up to AS_B_FR45), we noticed that the phase to the signal changes dramatically with the amopunt of power on the quadrant.

Attached is a time series of the DC power (Blue. 0 is on top, more power goes negative), as well as I and Q phase.

On this plot we first maximized the light on Seg1, then phased all signal into I, then noticed that the phasing changes with power on the segment, then reduced the power into the DRMI in 4 steps. As you can see the phasing dramatically changes with the power on the diode...
Images attached to this report
Comments related to this report
sheila.dwyer@LIGO.ORG - 00:18, Thursday 27 August 2015 (20948)

Here are the 36 signals at the same time.  As the power drops by roughly a factor of 2, the signals also drop by roughly a factor of 2, without any apparent change in the phase.

Images attached to this comment
stefan.ballmer@LIGO.ORG - 15:02, Thursday 27 August 2015 (20960)
This confusion was due to dark offsets - the for some reasone changed significantly.
H1 ISC
jenne.driggers@LIGO.ORG - posted 21:30, Wednesday 26 August 2015 - last comment - 00:52, Friday 28 August 2015(20939)
Template to decide if OMC DCPD extra whitening is okay

I have created a DTT template that makes it easier to decide when it's okay to turn on more OMC DCPD whitening.

Evan wrote an alog some time ago about the new OMC DCPD whitening on/off guardian states (alog 20578), and Cheryl and Evan made some notes on when it's okay to go to these new states (alog 20787).

As of right now, the guardian will automatically turn on one stage of whitening, but we get better high frequency noise performance if we add a second stage.  However, if some mode (eg. a violin mode) is rung up, then we can't add the second stage of whitening without being in danger of saturating the ADC.  So.  The new DTT template should help decide when it's okay to add the second stage.

The template is /ligo/home/ops/Templates/dtt/DCPD_saturation_check.xml (screenshot below). The template should be run after we have arrived at NOMINAL_LOW_NOISE for the main lock sequence.  If the dashed RMS lines are below the green horizontal line, it's okay to add the second stage of whitening.  

To engage the second stage of DCPD whitening:

Open the full list of guardian states for the OMC_LOCK guardian, and select "ADD_WHITENING". It will take a minute or two, and automatically return to the nominal "READY_FOR_HANDOFF" state.

Images attached to this report
Comments related to this report
rana.adhikari@LIGO.ORG - 16:17, Thursday 27 August 2015 (20965)

could you explain the math & logic a little bit more?

I would have thought that an RMS of 3000 cts is as high as we want to go. Increasing the RMS by a factor of 10 would make it so that its always saturating = not OK. Or isn't this IN1 channel the real ADC input?

evan.hall@LIGO.ORG - 00:52, Friday 28 August 2015 (20975)

Yes, 3000 ct rms = 8500 ct pkpk = too many counts to add a second stage of whitening.

We run with about 10 mA dc on each DCPD, which shows up as 13000 ct or so of dc on the IN1 channels. That means we have something like 19000 ct of headroom before the ADCs saturate on the high side (+32 kct). Assuming the ac fuzz is symmetric about the mean, saturation will certainly occur if the ac is greater than 38000 ct pkpk with two stages of whtening, or 3800 ct pkpk with one stage of whitening.

That's why the criterion I've been using for turning on a second stage of whtening is to look at the IN1 channels and verify that the ac is less than 3000 ct pkpk, or 1000 ct rms when there is only one stage of whitening on. If we find the DCPDs saturating too often with two stages, we should be even more restrictive.

H1 ISC
daniel.sigg@LIGO.ORG - posted 19:02, Wednesday 26 August 2015 - last comment - 03:30, Friday 28 August 2015(20930)
RF AM at 45.5MHz

Evan Stefan Daniel

The second EOM driver was installed in the CER using the 9MHz control and readback channels. The first attached plot shows the DAQ readback signals. Both drivers show the similar noise levels for the in-loop and out-of-loop sensors. They are also coherent with each other as well as ASC-AS_C! The in-loop noise is clearly below which would indicate that the signal is suppressed to the sensor noise. The measured out-of-loop noise level is also a factor of 4 higher than the setup in the shop.

The second plot shows the same traces but this time the ifr is feeding the EOM driver in the CER. As expected its out-of-loop noise level is now consistent with measurements in the shop and no longer coherent with the unit in the PSL.

We were starting to suspect that we are looking at down-converted out-of-band noise...

Non-image files attached to this report
Comments related to this report
evan.hall@LIGO.ORG - 03:24, Thursday 27 August 2015 (20950)

Using a network analyzer, we took the following measurements:

  • rf spectrum of 45.5 MHz from harmonic generator + distribution amplifier in CER,
  • rf spectrum of 45.5 MHz from IFR in CER,
  • rf spectrum of 45.5 MHz from spare harmonic generator in the EE shop,
  • rf spectrum of 9.1 MHz from OCXO + distribution amplifier in CER,
  • audio-band spectrum of out-of-loop RAM readback of EOM driver, using harmonic generator as 45.5 MHz source, and
  • audio-band spectrum of out-of-loop RAM readback of EOM driver, using IFR as 45.5 MHz source.

The first four of these are shown in the attached plot [the OCXO has been multiplied by 5 in frequency for the sake of comparison]. The message is that the 45.5 MHz in the IFO distribution system has huge, broad wings out to 2 MHz away from the carrier. These are not seen on the IFR, the harmonic generator on the bench, or the 9.1 MHz in the distribution system.

Although the EOM driver still works to suppress some of the RFAM below 50 kHz, the broad wings still contribute significantly to the rms; most of it is accumulated above 200 kHz offset from the carrier. This is shown in the second attachment.

Non-image files attached to this comment
evan.hall@LIGO.ORG - 03:30, Friday 28 August 2015 (20977)

I looked again at some rf spectra in the CER.

These peaks appear on every output of the harmonic generator, even when it is not driving any distribution amplifiers (just a network analyzer).

These peaks also appear even when the harmonic generator is driven by +12 dBm of 9.1 MHz from an IFR (not from the OCXO + distribution amplifier).

This suggests we should focus on the harmonic generator or its power supply.

H1 INJ (INJ)
eric.thrane@LIGO.ORG - posted 22:57, Tuesday 25 August 2015 - last comment - 17:17, Thursday 27 August 2015(20893)
CBC Injection Test For Saturation + First Blind Injection Test
Patrick, Sheila, Jenne, Eric

For the first part of the test, we injected our fiducial CBC waveform (same one used in ER7) and tried raising the LIMIT value on the hardware injection block in order to address saturation problems observed in ER7. During ER7, the LIMIT was 200. We raised it to 400. The first injection did not go through:

1124601535 1 1.000000 cbctest_1117582888_		intent bit off, injection canceled

Patrick, Sheila, and Jenne tried to turn on the intent bit, but there was some sort of problem, which will be alog'ged separately. As a temporary work-around, we turned off the tinj intent-bit check and injected again:

1124602724 1 1.000000 cbctest_1117582888_		successful

Patrick determined that the injection produced a maximum |amplitude| of 15 counts coming out of the injection block, which seemed to indicate that the original LIMIT value of 200 was sufficient. However, an alarm went off to indicate that there was saturation at ETMY. Thus, the saturation problem cannot be solved by tinkering with the INJ block in MEDM. Rather, the problem is occurring downstream on the ETM actuators. We request that Jeff K, Adam M, et al. look into options for avoiding saturation at the ETMs.

Next we tried a blind injection using the new blind injection code. The blind injection code does not log injections in EPICS so they are not automatically picked up in the segment database.

1124603111 1 1.000000 cbctest_1117582888_		successful

The blind injection was clearly visible. The ETM saturation warning went off again. The injection was logged correctly in the blind injection blindinj_H1.log:

current time = 1124603049...
Attempting: awgstream H1:CAL-INJ_BLIND_EXC 16384 /ligo/home/eric.thrane/O1/Hardw
areInjection/Details/Inspiral/H1/cbctest_1117582888_H1.out 1 1124603111
Injection successful.

All of these injections were carried out with scale factor = 1; (that's the 1.000000). The injection file, described in a comment below, is a 1.4 on 1.4 BNS, optimal orientation, at D=45 Mpc. It is the same waveform used in previous ER tests.
Comments related to this report
andrew.lundgren@LIGO.ORG - 00:49, Wednesday 26 August 2015 (20894)DetChar, INJ
It looks like the injection actually does hit the 400 count limit (plot 1). It saturates right at the end when the injection chirps up to high frequency. There's some kind of ringing as well (plot 2). From the spectrogram (plot 3) and the zoom (plot 4) this looks like a feature at just above 300 Hz. I thought it might be a notch for the PCal line, but that's 331.9 Hz. So someone will have to check the inverse actuation filter and see what's happening at that frequency.

It's possible to see the overflow from the first injection in the ETMY L3 MASTER channel (plot 5). It happens at -131072 counts, and the injection is trying to push it past -200000. The blind injection caused an overflow as well, but since this channel is only recorded at 2048 Hz, it looks like it falls short of overflow (plot 6). There's a faster readback whose name escapes me at the moment.

Unless the blind injection is made a factor of about 10 smaller, or rolled off at high frequency, it will be trivial to detect it by looking at the drive to the ETM.
Images attached to this comment
eric.thrane@LIGO.ORG - 04:24, Wednesday 26 August 2015 (20901)INJ
FYI, the injected waveform was fiducial waveform from ER7:

https://alog.ligo-la.caltech.edu/aLOG/index.php?callRep=16125

It's a 1.4-1.4 BNS at 45 Mpc, optimal orientation.
duncan.brown@LIGO.ORG - 05:06, Wednesday 26 August 2015 (20904)

There are a couple of things to watch out for when performing CBC hardware injections, based on iLIGO experience:

  • In iLIGO, the actuation function had a notch at the violin-mode frequencies. If you just invert A(f) without smoothing this out, the notch will get inverted and you'll give the the mirrors a hard kick as the inspiral sweeps through the notch frequency. (My guess is that Adam and Jeff have already dealt with this, though.)
  •  If the end of the inspiral signal is not smoothly rolled off and the signal drops from some loudish amplitude to zero then you put a step function in. This caused the iLIGO test mass to swing at its pendulum frequency, putting a huge ringdown in the data (called the "whooper" in iLIGO). In iLIGO, the CBC group generated waveforms in counts, by applying 1/A(f) ourselves using the adiabatic inverse calibration, so we smoothed 1/A(f) ourselves before applying it. In aLIGO, 1/A(f) is: (i) more complicated, and (ii) applied in the front end by IIR filters. It is possible that the sharp turnoff of the CBC injection at the end is causing the filters that apply 1/A(f) to ring and that's what's giving us garbage at the end of the signal.

For the ER7 injection we used an SEOBNRv2 waveform that has a ringdown at the end, hoping that this turn off would not trigger an impulse. However, for BNS masses, the turn off and ringdown is pretty sharp. I've asked Chris check that there are no "whooper" effects with the SEOBNRv2 waveform, but we haven't had chance to do this yet. For a SpinTaylorT4 waveform (the other waveform CBC wants to inject), there will definitely be a step, so this needs to be checked and rolled off carefully.

duncan.brown@LIGO.ORG - 05:08, Wednesday 26 August 2015 (20905)

One other comment on the test: what scaling in awgstream did you use? That waveform looks monstously loud (eyeball SNR > 20). That's much louder than would be useful for a blind injections, but good for helping us find whooper effects.

eric.thrane@LIGO.ORG - 16:44, Wednesday 26 August 2015 (20928)INJ
Duncan, the scale factor is 1.
andrew.lundgren@LIGO.ORG - 14:27, Thursday 27 August 2015 (20959)DetChar, INJ
Just for completeness, because I didn't see it posted, here's an Omega scan of the injections in h(t). The first is the non-blind injection, the second is the blind injection. I think the glitch ten seconds after the blind injection is unrelated. I thought it might be a filter turning off or being reset, but it's not on a GPS second (it's at 1124603210.28). It does cause an overflow of the ETMY ESD DAC.
Images attached to this comment
peter.shawhan@LIGO.ORG - 17:17, Thursday 27 August 2015 (20966)INJ
I verified that the blind injection was correctly recorded in the raw frame file.
Displaying reports 62581-62600 of 82999.Go to page Start 3126 3127 3128 3129 3130 3131 3132 3133 3134 End