Displaying reports 69361-69380 of 77116.Go to page Start 3465 3466 3467 3468 3469 3470 3471 3472 3473 End
Reports until 21:25, Saturday 05 October 2013
H1 ISC
rich.abbott@LIGO.ORG - posted 21:25, Saturday 05 October 2013 (8010)
HAM 1 RFPD Checkout
Sheila, Stefan, Rich

Things went so well yesterday that it was a bit suspicious.

Present status:
1.  Finished a crude checkout of the tip/tilts after installing jumpers inside the coil driver chassis to enable the normal signal path.  The HAM1 tip/tilts are showing signs of damping, so the electronics are fine.  The anti-dewhitening is probably not right, so the servo needs attention.  (The HAM6 tip/tilt coil drivers have not yet had the jumper installed, so they won't work yet).
2.  REFL A and B Wavefront Sensors seem to be fully functional as checked out from the rack.
3.  Both the REFL and POP LSC detectors are in HAM1 and are functioning, but after much troubleshooting we found that there was a voltage missing in the DC wiring serving one of the LSC detectors probably inside the chamber.  This is despite testing each and every wire prior to installation beginning.  After finding that (and being so relieved that the detectors were OK) we realized that it's going to involve getting inside the chamber, which we will do in the morning.

Next Actions:
1.  Fix DC cable serving LSC detectors
2.  Do optical alignment of RFPDs
3.  RF AM measurements
H1 ISC
jeffrey.kissel@LIGO.ORG - posted 02:48, Saturday 05 October 2013 (8009)
Polishing up H1 IMC ODC; Now Ready for Consumption
J. Kissel

Following up on the initial installation of the Online Detector Characterization channel for Input Mode Cleaner control system (see LHO aLOG 7894), I've cleaned things up further by 
- fixing the bit-bug that was inherent to the CTRLON bit (BIT 1), 
- added a few more EPICs records to make
    - calibration of the sum signals and power ratios possible and 
    - the bit generation a little more clear and useful,
- added negative space, notes, and clarifying colors to the slightly-complex bit-logic chain
- spiffing up the screen to Izumi level. 

All bits, even up to the summary bit level, are now regularly green. This channel (H1:IMC-ODC_CHANNEL_OUT_DQ) should be ready for DetCharian DataAnalystic consumption.

I attach new screen shots of the bits (pun intended) I've changed -- just the ODC block in the front-end model, and the screen.

Still to-do, but not imperative for the functionality of the channel:
- Get calibration factors for 
    - All ASC error signals, H1:IMC-DOF[1,2,3,4]_[P/Y]_IN1, in [ct/urad]
    - H1:IMC-PWR_IN, the broad-band PD on PSL periscope in [ct/W]
    - H1:IMC-ODC_MC2_TRANS_SUM, the DC sum signal for MC2 transmitted light QPD in [ct/W]
    - H1:IMC-ODC_IM4_TRANS_SUM, the DC sum signal for MC2 transmitted light QPD in [ct/W]
    - Expected power ratio between PWR_IN and each transmitted sum in [W/W].
  and install them in the available ODC EPICs records.
- Fill out all the EPICs string records explaining each of the bits (though I tried to make the corresponding, EPICs channels {that are redundant with the ODC bitword itself BTW...} have names which are clear-ish).
    
As of this log, new versions of
/opt/rtcds/userapps/release/asc/h1/models/h1ascimc.mdl
/opt/rtcds/userapps/release/ioo/common/medm/IMC_CUST_ODC.adl
/opt/rtcds/userapps/release/asc/h1/burtfiles/h1ascimc_safe.snap
have been committed to the userapps repo.
Images attached to this report
H1 AOS
stefan.ballmer@LIGO.ORG - posted 20:33, Friday 04 October 2013 (8008)
More HAM1 work
(Kiwamu, Sheila, Arnaud, Stefan)

We moved TT2 (RM2) back 1.6 in and M5 back 1 in. This gives us the telescope that Sheila calculated to be optimal for Paul's beam parameters.
We swapped the beam diverter cables for REFL and POP at the CB-2 bracket - this brings it in agreement with document D1300075.
We switched one in-vacuum RF cable (the one plugged in to D6-2D, for WFS A) against a spare. All in-vacuum cables now checked out o.k.
We took some ModeMaster measurements - but before RM1 and RM2 were damped, so the beam was still moving a lot. This should be repeated.
We adjusted the RM1 and RM2 OSEM positions - for details see Arnaud's elog. However the drive is not yet working.
We placed the beam dumps behind RM1 and RM2, as well as the dump for the POP PD.

We left the BS for the REFL LSC diode moved back by 1in to send the beam to the ModeMaster.
H1 SUS
arnaud.pele@LIGO.ORG - posted 20:14, Friday 04 October 2013 - last comment - 14:41, Tuesday 08 October 2013(8007)
OLV RM1 RM2

Open light values have been measured on RM1 and RM2

OPTIC OSEM Open Ligh Value (cts) Gain Offset Serial Number
RM1 M1UL -32768 -0.916 16384 1105240 a
M1LL -32768 -0.916 16384 1105240 b
M1UR -22268 -1.347 11134 1105240 c
M1LR -29171 -1.028 14586 1105240 d
RM2 M1UL -26656 -1.125 13328 1105238 a
M1LL -32768 -0.916 16384 1105238 b
M1UR -32708 -0.917 16354 1105238 c
M1LR -32768 -0.916 16384 1105238 d

damping gains have been set to

-30 in long

-0.02 in Pitch

-0.02 in Yaw

the safe snapshot has been commited to the svn

Comments related to this report
arnaud.pele@LIGO.ORG - 14:41, Tuesday 08 October 2013 (8043)

I used the script "[OSEM2EUL, EUL2OSEM, SENSALIGN, DRIVEALIGN] = make_sushtts_projections" in /HTTS/Common/MatlabTools/ to generate the matrices for RM1 and RM2

They have been automatically filled with fill_matrix_values.m

The values are

OSEM2EUL:

    0.2500    0.2500    0.2500    0.2500
   10.3681  -10.3681   10.3681  -10.3681
  -10.3681  -10.3681   10.3681   10.3681

EUL2OSEM matrix :

    0.2500   10.3681  -10.3681
    0.2500  -10.3681  -10.3681
    0.2500   10.3681   10.3681
    0.2500  -10.3681   10.3681

Safe snapshot has been saved for both RM1 and RM2

H1 ISC
rich.abbott@LIGO.ORG - posted 18:27, Friday 04 October 2013 (8006)
HAM1&6 ISC Electronics Installation Work (V2)
A rare day indeed...

Alexa, Stefan, Sheila, Kiwamu, Rich

HAM1 Status:
1.  All RF connections from air to vacuum have been fixed.  After much head scratching, we found an idiosyncrasy (=design flaw) with the air-side 2-row 5-way coaxial connector.  Each coaxial element in the 5-way connector is supposed to free float somewhat in order to mate properly when inserted into the flange.  Moreover, each coaxial element is spring loaded such that there is a restoring force to maintain proper insertion.  The air side connector has large coaxial cables to minimize the RF loss on the trip back to the racks, and it is here that the trouble begins.  This large coaxial cable - being quite stiff - has enough friction inside the connector body that when you try and plug the 5-way connector into the flange, some of the individual coaxial elements simply compress the spring, and don't insert into the socket.  With the strain relief screws loosened, it is actually possible to push an individual cable and feel it snap into the flange.  Of course, there's a down side to this.  If you pull an individual cable, it is possible to pop it out of its socket causing a loss of connection.  We secured the cable bundles to the conflat protector ring cross bolt such that all the cables are reasonably immobile.  This will likely be quite sufficient.

A small consolation prize is that the in-vacuum version of this connector doesn't seem to be anywhere near as susceptible to this phenomenon.  Still, any plugging and unplugging (which is highly discouraged) should be done by watching with a time domain reflectometer (TDR) to ensure no harm has been done before and after the evolution.

2.  Beam diverters have been tested and are all OK
3.  Tip/tilt electronics chain is showing good signs of life in that the sensors are sensing and the pushers are pushing. 

Next Steps:
1.  Remaining parts for the RFPDs are to be delivered in town tomorrow.  Assembly will be completed and the detectors will be installed in HAM1
2.  Finish checkout of tip/tilt chain
3.  Take transfer functions for all RFPDs in HAM1
4.  Clean up in-vacuum cable installation

H1 AOS
keita.kawabe@LIGO.ORG - posted 17:34, Friday 04 October 2013 (8005)
TMS restraint: done (Cheryl, Pablo, Keita)

We've removed temporarily restraint and put the real one in.  TMSX is floating but cannot crash into ETMX.

We left two big wipes on the ISC table to protect the mirrors, which is probably like 0.2 lbs or something total. If this is a problem for you, please feel free to remove them, but take care not to touch or bump any of the mirrors/lenses/detectors on the table.

There are some minor things that should not affect the task of other people, but these should be fixed later before we pump the volume down:

  1. We need one class A 3/8 nut (either aluminum or Nickel Copper alloy) and two washers for a bolt that is necessary when pulling the TMS back away from ETM. We have the bolt but that is not in place for now due to this.
  2. We need two class A pear shaped link parts. For now we're using class B parts, but they should be replaced with class A parts. We'll ask C/B to get two from Thomas and class A them.
  3. Tuned mass damper pins are still in place.

We brought the transport restraint and some in-vac parts that I thought are ours back to the EX lab. I and Pablo didn't label these, they are just layed out on the work table there. For later labeling purpose for our own sake, these are:

  1. Transport restraint turnbuckles and chains. Chains are inside one of stainless steel tubs.
  2. ISC table covers and support rods. Rods are wrapped separately from covers but are put on the covers.
  3. Class B in-air restraint rod assembly for fake Genie. Do never ever confuse this with the class A restraint rods.
  4. Spare parts for in-vac restraint and one 3/8 bolt that are to be installed in EX are in stailess steel tubs.
  5. Some smaller stainless steel bins containing kapton tubing and screws and 1/4-20 nuts (both Nickel-Copper alloy and alluminum).
H1 CDS
david.barker@LIGO.ORG - posted 16:59, Friday 04 October 2013 (8004)
Beckhoff chassis at EX, serial hookup

Jim and Dave.

We noticed that the TCS rack layout was slightly differerent between EX and EY. The EY layout was more optimal, so we made EX the same as EY. This involved moving the PEM BNC patch below all the timing systems, and moving the End Link chassis down 1U. So from the top of the rack we have: timing fanout, comparator, space, serial concentrator, space, End Link Chassis, space, PEM patch.

Daniel provided the serial cables to hook up the fanout. The large 37pin cable was ran from the End Link to the serial concentrator. A 9pin serial was ran from the RS422 output on the back of the fanout to port 5 (lower left) on the concentrator (Daniel says this is the first RS422 port, lower numbered ports are RS232).

I dont see the timing diagnostics data on my MEDM, perhaps something on ex beckhoff needs to be restarted?

H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:28, Friday 04 October 2013 (8003)
Ops Summary
LVEA Laser Hazard
Alarms: FMCS/RO and CDS

08:00 Dave B. - DTM Broadcaster down and front-end DAQ errors, 
           Jim B reset h1broadcast0 and restarted MX-Streams on affected DAQs. 

Apollo working at End-X removing tooling back to the LVEA
Rich A. Testing cables in the HAM1/HAM/2 area

09:00 Paul F. taking MC measurements
09:55 Cheryl and Pablo in LVEA taking measurements
10:09 Gerardo M.Jr doing assembly work in LVEA mechanical test stand cleanroom
11:16 Justin B. at end-x checking laser barriers 
11:48 Stefan B. working in the HAM1/HAM2 area
16:00 several dust alarms in the DR. Justin B and Jeff B checked dust monitor in diode room.   

LHO General
jeffrey.bartlett@LIGO.ORG - posted 14:36, Friday 04 October 2013 (8001)
Modified TS Blade flattening Procedure

   I assembled the TS cartridges for the 3IFO TMS using a modified procedure from that documented in D060370. I removed the big jacking screw that is used to pull flattening roller across the blade. Instead, I pulled the flattening roller out by hand. 

   This seemed to work better than using the screw jack because: 

      (1). It was much faster. Instead of several minutes to run the screw in and out, pulling by hand took just a couple of seconds to flatten the blade. 
      (2). There is little or no contamination generated by the hand pulling process. When using the screw jack one must continually lubricate the jacking screw with alcohol. As the jacking screw turns, it generates a large amount of aluminum shavings. These shavings mix with the alcohol to make a nasty paste, which drips on the optics table the puller is clamped to and the floor. The Teflon bearing the end of the jacking screw rides on also sheds during the pulling process. Both these contamination sources are eliminated when pulling by hand. 
      (3). The jacking screw is a source of binding. The turning of the jacking screw causes the two guide rods on the sides of the puller to twist. This twisting causes the guide rods to bind, which puts excess stress on the guide rods and the jacking screw. The hand pull greatly reduced this problem, but it did not eliminate it. 

   It did take some strength to pull the blade flat, but it was not excessive. There is a possibility the roller could snap back across the blade, without the screw jack holding it in place. However, there are notches cut into the sides of the puller, which the roller bearings drop into when the puller is fully engaged. The force of the blade pushing upwards holds the roller bearings into the notches very securely. In addition, there are holes on either side of the puller just inside the notches the roller bearings fit in. I put a pin through these two holes to act as a safety stop, should the bearings come out of the notches. 

   This process worked as well for disassembly as it did for assembly. The hardest part of the disassembly process was getting the roller bearings out of the notches.  
H1 AOS
sheila.dwyer@LIGO.ORG - posted 12:40, Friday 04 October 2013 - last comment - 16:58, Monday 07 October 2013(7998)
more beam measurements

Joe, Pablo, Cheryl, Sheila

We measured the beams coming out of the HAM2 viewport, with the nanoscan head 2 feet 6 inches from the viewport.  (in the first version of this alog I wrote the wrong distance)

For the brighter beam we measured beam diameters: 2549 um horizontal, 2632 um vertical.  after rorating the scan head 90 degrees we measured 2650um vertical, 2561 um horizontal.  

For the dim beam we measured 7160um vertical, 5972 um horizontal after rotating  by 90 degrees we got 6077um horizontal 5865um vertical. 

We also measured the beam in HAM1, in the same location as wensday (we move the BS for the RF PD to 16 inches after M2, we put the nanoscan 40 inches after the BS, there we got 4025 um vertical, 4126 horizontal.  After rotating the head 90 degrees we got 4045 um vertical 4020um horizontal.  

Comments related to this report
guido.mueller@LIGO.ORG - 13:43, Friday 04 October 2013 (8000)
Hi Sheila,

Can you be a little more specific which beam you measure where? 
The 4000um diameters sound good but I don't know what you mean with the brighter beam and what with the dimer beam.
sheila.dwyer@LIGO.ORG - 21:48, Saturday 05 October 2013 (8011)

Hi Guido-

I believe the brighter beam is the reflection off of PRM, although I haven't looked at the layout to double check.  As you face the viewport, near the veiwport the dim beam is on the right while the bright beam is on the left.  If you move to about 3 feet away from the viewport they cross, and the dim one is on the left if you are facing the veiwport.  Pablo watched the spots on the wall as I moved the PRM alignment, and the bright one moved.  

sheila.dwyer@LIGO.ORG - 15:14, Sunday 06 October 2013 (8013)

I should have been more clear, the first two measurements are of beam sizes for SM2 trans, coming out of the HAM2 veiwport where IOT2R would normally be. 

paul.fulda@LIGO.ORG - 09:32, Monday 07 October 2013 (8017)

Looking at the table layout for HAM2 (D0901083), I would expect the SM1 forward trans beam (from PMMT2 a.k.a. IM3) to be the dimmer beam, since this beam is split twice before making its way to the viewport. The SM1 return trans beam is not split at all before getting to the viewport. (I think you already came to this conclusion).

From the model, using rather rough estimates for the distances after IM4 transmission (+/- 2 inches), we expect that the SM1 forward trans beam (dimmer beam) where you measured it should have diameters of 6.20mm horizontal and vertical. The SM1 return trans beam (brighter beam) where you measured it should have diameters of 2.68mm horizonal and 2.67mm vertical. Not so far away from what you measured...

I'll try to get more precise numbers for the after-IM4-trans distance from Luke and update accordingly.

paul.fulda@LIGO.ORG - 09:45, Monday 07 October 2013 (8019)

Apologies, everywhere I wrote "SM1" I meant "SM2". Or IM4, they are the same mirror.

sheila.dwyer@LIGO.ORG - 11:34, Monday 07 October 2013 (8020)

SM2TransReturn1.png is a screen shot of the nanoscan program with the bright beam, when apperature 1 veritcal. 

SM2TransForward1.png  the dimmer beam, first with Apperature 1 horizontal then SM2TransForward2.png is with the apperature 1 vertical.  

I haven't figured out how to export data from the software, and I can't uplaod .nsd files to the alog, but if anyone wants the data it is available at http://www.ligo-wa.caltech.edu/~sheila.dwyer/NanoScanData/IO/

You can use the free Nanosan software from Ophir/ Newport to open these files. 

We saw that the Forward beam looks like it could possibly be clipping, Joe tried to move the location of the nanoscan head but the beam profile didn't get any better. 

Images attached to this comment
paul.fulda@LIGO.ORG - 15:27, Monday 07 October 2013 (8028)

Just an update on the expected beam sizes with more accurate distances used in the model (good to 1/4" or so, inlcuding IM4 substrate and viewport substrate effect):

SM2trans forward 2wx=6.349mm, 2wy=6.3455mm

SM2trans return 2wx=2.6813mm, 2wy=2.6697mm

sheila.dwyer@LIGO.ORG - 16:58, Monday 07 October 2013 (8031)
H1 PSL
paul.fulda@LIGO.ORG - posted 12:29, Friday 04 October 2013 (7997)
ALS beam blocked on PSL

To make the process of inserting the pick-off BS for the Faraday isolation ratio measurement easier, we blocked the ALS beam around the same location on the PSL table with a razor dump.

At the time of writing this, that beam is still blocked.

H1 CDS
david.barker@LIGO.ORG - posted 12:28, Friday 04 October 2013 (7996)
restarted web medm snapshots for H1

I restarted the web medm snapshooter for the H1 screens to capture the new state-word overview screen with added Y-end models.

H1 SEI
hugh.radkins@LIGO.ORG - posted 12:19, Friday 04 October 2013 (7995)
WBSC8 ETMX Friday Noon Update
Thomas, Mitchell & Jason got the majority of the fixturing out of the chamber, bagged & wrapped, and out of the VEA.  They then got the retroreflector hanging on the Quad.
We then unlocked the HEPI and leveled & set the elevation of the Optical Table per D0901152.  I set the system ~.5mm low as IAS found the Optic 0.4mm high on the Test Stand.  The level is within +-0.1mm and the elevation is within 0.3mm; good enough since we still likely have much horizontal adjustment to do.
With the retroreflector in place, we then shot an X position.  IAS is still evaluating that result.
LHO General
patrick.thomas@LIGO.ORG - posted 11:25, Friday 04 October 2013 (7993)
Turning off dust monitor 8 appears to kill dust monitor 9
I noticed this morning that dust monitor 9, which had previously been dropping in and out of communication, was no longer coming back. I went out and looked at it, but didn't notice anything obvious. I also managed to smack my head on one of the light pipes between the H1 PSL enclosure and HAM1.

I connected to the IOC screen, pressed Start on the medm for the dust monitor, and got a read timeout reported by the IOC.

I then trended the mode back, which should oscillate from 'holding' to 'running' every minute, to see when communication was lost. Seeing that it stopped yesterday, I compared it to dust monitor 8, which I had turned off and removed yesterday. The two times are in close agreement (see attached plot).
Non-image files attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 10:30, Friday 04 October 2013 (7992)
DAQ restart last night caused some DAQ errors

The DAQ was restarted twice yesterday evening at 20:15 and 20:50 local time. The second restart precipitated two problems:

The front ends affected were: h1susauxex, h1susex, h1pemmx, h1lsc0, h1susauxey, h1seib2, h2seib3, h1susbstst, h1susauxh2, h1sush56, h1sush34, h1sush2b.

All data from these front ends will have been marked as bad (zero'ed) in the frames between 03:51 and 16:11 UTC today, 4th October.

Jim restart h1broadcast0 and restart MX-Streams on the affected front ends to restore the DAQ.

LHO General
patrick.thomas@LIGO.ORG - posted 10:27, Friday 04 October 2013 (7991)
plots of dust counts
Attached are plots of dust counts requested from 4 PM October 2 to 4 PM October 3.
Non-image files attached to this report
LHO General
john.worden@LIGO.ORG - posted 10:00, Friday 04 October 2013 - last comment - 12:06, Friday 04 October 2013(7990)
LVEA Purge Air Compressor Kobelco

The purge air system is up and running again. The Kobelco air compressor had shut down on an over temperature alarm which has been determined to be an open circuit RTD.

As a temporary fix a 1k resistor has been installed in place of the RTD.

 

Temps now after one hour of run time are:

 

1st air discharge - 287F

2nd air suction - 85 F

2nd air discharge - measured at 210F Front panel says 65F(1k resistor)

lube oil - 104F

Comments related to this report
john.worden@LIGO.ORG - 12:06, Friday 04 October 2013 (7994)

Temperatures remain the same at 12:00

H1 ISC
rich.abbott@LIGO.ORG - posted 19:12, Wednesday 02 October 2013 - last comment - 15:49, Friday 04 October 2013(7970)
HAM1&6 ISC Electronics Installation Work
Stefan, Alexa, Rich

HAM1:
1.  All in-air and in-vacuum cabling associated with the ASC detectors,  LSC detectors, and Pico motors have been run.  The in-air cables still require termination in TNC at the rack.
2.  All in-vacuum cabling has been run for the tip-tilts, and the cables have been mated to the tip-tilt stages.
3.  Cables for the beam diverter are attached at the flange, but not run to the diverters yet as one connector set was missing the helicoil inserts.
4.  Operational check was performed on all 4 pico motors, and all axes are correct

HAM6:
1.  All in-vacuum RF detector coaxial cabling is attached at the flange, but not yet run to the racks.

What's Next:
1.  Fix cables requiring helicoils
2.  Hook up and test beam diverters
3.  Mount all in-vacuum detectors and verify proper operation
4.  Clean up in-vacuum cable routing and ensure all is well constrained
5.  Terminate all in-air RF cables at their respective racks
6.  Install tip/tilt coil driver in the ISC R4 rack and test operation in HAM1 through installed air and vacuum cabling

Comments related to this report
alexan.staley@LIGO.ORG - 13:26, Friday 04 October 2013 (7999)

Update on status:

 

 - Helicoils fixed (Rich).

 - Beam diverters hooked up and tested. The beam diverters work, but there is a flip between REFL/POP somewhere in the chain between Beckhoff and the actual BDIVs. The easy option is just to flip the cables attached to the BDIVs; the harder route is to track where the flip happens and fix it (Alexa, Joe, Sheila).

- HAM 1 RF in-air cables have been terminated with TNC. The LSC RF cables have been connected to the proper patch panels; however, ASC RF cable are not. HAM 6 RF in-air cables remain to be terminated (Alexa, Rich).

- In the process of checking RF cable connections; about 1/3 of the cables are not properly connected (Rich, Alexa).

alexan.staley@LIGO.ORG - 15:49, Friday 04 October 2013 (8002)

(Alexa, Rich, Stefan, Kiwamu)

 

We found a swapped wire inside HAM 1; now the beam diverters are properly connected (following the wiring diagrams) and working. 

Displaying reports 69361-69380 of 77116.Go to page Start 3465 3466 3467 3468 3469 3470 3471 3472 3473 End