Displaying reports 79521-79540 of 85276.Go to page Start 3973 3974 3975 3976 3977 3978 3979 3980 3981 End
Reports until 16:08, Friday 29 March 2013
LHO General
gerardo.moreno@LIGO.ORG - posted 16:08, Friday 29 March 2013 (5932)
Day Shift Summary

- Mark L, and group changed pre-filters for AHU 1 and 2, per WP 3783.
- LVEA transition to laser safe at 9:00 am.
- Corey G. work in the squeezer area, East Bay of LVEA.
- Rick S, Michael R, and others to visit MID-Y, inventory of 3rd IFO PSL items.
- Jim W work at BSC2, top area.
- Betsy W and Filiberto C, work at HAM2, mission aborted.
- Betsy W and Travis S, BS is locked now.
- LVEA transition to laser hazard for IO work.
- IO group work, PSL enclosure --> HAM02.
- LVEA transition to laser safe, 3:32 pm.

 

H1 SUS
arnaud.pele@LIGO.ORG - posted 11:26, Friday 29 March 2013 (5927)
Beamsplitter transfer functions Phase 3a

After two rounds of transfer functions two nights ago and yesterday night (aLog 5907 and 5920) the beamsplitter look(ed) fully supsended (it had to be locked again this morning)

The attached pdfs show

  1. Transfer functions comparing :
    • BSFM model
    • Measurement on March 27th with one of the top EQ stop touching
    • Measurement on March 28th after Travis found the source of rubbing and fixed it
       
  2. Power spectra comparing :
    • LLO measurement on October 2012 Phase 3a
    • LHO measurement on March 27th with one of the top EQ stop touching
    • LHO measurement on March 28th after Travis fixed it
Non-image files attached to this report
H1 ISC
sheila.dwyer@LIGO.ORG - posted 09:57, Friday 29 March 2013 (5926)
beam splitter changed on ALS table, fiber rerouted
Yesterday we continued to struggle to get light from the fiber to the end station. Richard is helping us trace down the problem.  Even with the fiber working well, we only get 10uW onto the ALS table, then there are two 50/50 beam splitters, so there were only about 2.5 uW on the PD, giving us a signal level around -40dBm, which is marginal and might be why I thought the ohase frequency discriminator was not working (it works as expected with larger signal levels).  I changed out the 50/50 beam splitter that sends a pick off to the PDs that monitor the power out of the fiber and the polarization to a 10% beamsplitter.

Chris and Max also rerouted the fiber from the patch panel to the table feedthrough. This fiber was on the floor, and probably stepped on, but it seems to work fine, the probelms we are having are upstream of that.  

Also, I spent some time yesterday afternoon labeling cables inside the ALS table, were there is a suprising number of cables with no labels at all.  Most of these cables are also not included in the cable plan, for the cables that go to feedthroughs I've been naming the cable after the cable on the other side of the feedthrough and adding an A to the end of the name. Otherwise I just make a name up.    
H1 ISC
kiwamu.izumi@LIGO.ORG - posted 05:50, Friday 29 March 2013 - last comment - 09:03, Friday 29 March 2013(5924)
POP alignment at HAM3 done

[Keita, Corey, Kiwamu]

The alignment of the POP paths in HAM3 are done. We removed the green fiber laser.
The next step is a picomotor test at HAM3 with the Beckoff system.


Forward propagating POP
 The POP path behind PR2 for the forward propagating beam (going from PRM to PR2) were successfully adjusted within a precision of ~ 1 mm or less at the QPDs. Comparing the alignment precision with the QPD diameter of 3 mm, we conclude that our alignment is good enough. This time the issue of the transparent BS [1] was mitigated by fully opening the aperture of the irises to make the HR beam as bright as possible. Luckily the HR beam became visible enough to work with. We tweaked the two steering mirrors to get the beam aligned on the QPD sled.   
 Actually we repeated this alignment twice. After the first round it turned out that the first steering mirror (a 3" mirror) which we established its alignment yesterday [2] gave a beam too low for the other POP path (i.e. backward POP path). The first steering mirror is relatively tall by design because it needs to be at the same height as the PRs and therefore the beam reflected by this mirror has to be angled downward such that the beam height gets lowered to the standard height of 4". Yesterday we adjusted the angle such that only the forward beam hits the center of its second mirror but apparently this wasn't a great idea. It resulted in such a low beam in the backward path due to the fact the backward beam propagates a longer distance than that of the forward beam by 6-ish inches. This too-low-beam was found after we removed the green laser setup at HAM2. Therefore we had to setup the green laser again and repeated the same alignment process. We adjusted the first mirror such that the beam is a bit too high for the forward path by 5-ish mm and a bit too low for the backward path by the same amount.


Backward propagating POP
 The backward propagating POP beam behind PR2 was aligned using the green fiber laser and we confirmed that the beam got through to HAM1. The same fiber laser was used to simulate the backward path. The laser was set up at HAM3 and injected at the front of PR2. We let the reflection go through the two irises. The position of the second steering mirror (2" reflector) was intentionally displaced toward east by ~ 7 mm in order to keep a large clearance for the downstream beam which passes by the west side of the mirror. Hence the beam spot on this mirror is also off by the same amount which shouldn't be a problem because the mirror is large enough and also the incident angle is small (about 10 deg ?). Although the green beam diverges a lot when it arrives at HAM2 we aligned the beam such that it passes by any of the towers in HAM2 with the same amount of the clearance. This resulted in a beam off-centered at the viewport in between HAM2 and HAM1 but this is OK. Some alignment of the optics at HAM1 will be performed later.


BS wedge on POP QPD sled
 This is a minor issue and we write this simply as a record here. We found that the BS on the POP QPD sled had its wedge at a wrong side. Ideally we want the fat side to be at the QPD side to let the ghost beam diverge away, but it seems we placed the BS in the opposite way --- skinny side at the QPD side. We checked the engrave mark on the barrel of the BS and found a "W" mark at the far side from the QPD, indicating that the fat side is at the far side and this is wrong. We are not going to fix this as the ghost beam will not hit the QPD anyway since the QPD is close to the BS.

[1] LHO alog 5774 "50-50 IR beam splitter is a good AR for green"
[2] LHO alog 5911 "Alignment of POP QPD path : ongoing"
 

Comments related to this report
keita.kawabe@LIGO.ORG - 09:03, Friday 29 March 2013 (5925)

3" mirror centering:

Ideally the line bisecting the angle of forward and backward going beam is at the center of 3" mirror, which means that the forward going beam is about 9mm to the west from the center and the backward beam 9mm to the east.

We didn't pursue this really strictly. All in all everything is probably 3 or 4mm too much to the west, but I didn't see any problem in that.

POP/ASL septum window between HAM1 and HAM2

The septum window is partly occulted by MC3, MC1 and PMMT2 cages. We aligned things such that the possibility of clipping is minimized. However, see the next point.

Beam position at PR3:

With the current PR2 alignment biases, the forward going green beam didn't hit the center of PR3. It's between 1 and 2 inches too high and to the west. (The beam then bounces off of PR3 and comes back to HAM2 and seems to go toward BS.)

That means that the PR2 angle is a few mrad off both in PIT and YAW as of now (but the beam position on PR2 is very good), and the same error is there for our back-propagating green beam. Once things are nicely aligned, the backward beam will probably be clipped by one of the SUS cages or the edge of the septum window. 

That's not a serious problem, the beam will not be clipped by the steering mirrors in HAM3, and HAM1 will be in air anyway, so we can always steer things back to a good position.

H1 IOO
cheryl.vorvick@LIGO.ORG - posted 02:17, Friday 29 March 2013 - last comment - 16:47, Friday 29 March 2013(5923)
IO work wrapping up:
- Joe, Giacomo, Cheryl

- Filiberto started the process to attach pins/connector to FI HWP pico motor.  Lack of information about the connector convinced us to push this out to at least tomorrow.

- the half wave plate was re-installed in the IMC trans beam path after IM1.  The beam through the FI was misaligned with IM2 to give an unclipped Forward Rejected Beam to minimize, which was minimized to around 40 uW of power.

- IOT2R was moved into place today, on the East side of HAM2, beams were aligned onto the single periscope and onto the table.  The table position needs to be marked before moving the table.

- beams transmitted through IM4 were measured - some measurements will be used to compare expected and actual transmittance of 2" fixed optics.  Actual power readings to be attached.

- AOE1 was aligned downstream of HWP per Rodica's instructions to move it along the beam path by 20mm.  With HA1 at 0, the front of the HWP is at 25mm , and the front plate of AOE1 is at 95mm along the beam path.

- PR2 scrapper baffle was installed.  Joe did the install, and centered the baffle w.r.t  the PR2 optic, since the beam at HAM3 iris was about a beam radius off in yaw, and off in pitch.  Earlier work of adding the HWP back into the beam path is the likely source of the change seen at PR2.  Using IM2, we deturmined that the correction was 100 slider counts or less, i.e. small.

Friday:
Plan is to flash the IMC, though there have been rumors of locking it in air...
Comments related to this report
filiberto.clara@LIGO.ORG - 11:14, Friday 29 March 2013 (5928)
Tried to connect/crimp the pins and connector for the Faraday Isolator. After going inside the chamber, noticed that the other connector that mates with the one I was installing is the same gender. We received a female connector and socket pins, but need male connector and pins. Have contacted Rich Abbot at CIT regarding getting correct parts.

Filiberto Clara
giacomo.ciani@LIGO.ORG - 16:47, Friday 29 March 2013 (5934)

This are the power measurements we took on HAM to estimate the transmissivity of a number of optics. Measurement taken with filter inf ront of the sensr are specified (to account account for possible miscalibrations).

Incident on IM1 (filter on): 189 mW

Transmitted through IM1 (filter on): 6.25 mW

Transmitted through IM1 (filter on): 5.96 mW


NOTE: we did not realize that, because we were using the rerouted REFL beam, the polarization of the incident beam on IM1 was not as expected during operation. So this set of measruement is probably of (very) limited usefulness and will ned to be retaken. This does not apply to the following measurement taken at and after IM4, as only the right polarization remains in the main beam after the FI.

Forward incident on IM4 (filter on): 176 mW

Forward transmitted trough IM4 (filter on): .39 mW

Forward transmitted through IM4: 385 uW

Forward transmitted through ROM LH1: 30.5 uW

Forward reflected of ROM LH1: 361 uW

Forward incident on ROM RH3: 355 uW

Forward reflected of ROM RH4: 325 uW

Forward transmitted through ROM RH4: 25 uW

Forward reflected off IM4 (filter on): 175 mW

Forward transmitted through PRM (filter on): 5.4 mW

Backward transmitted through IM4: 380 uW

Based on the the above measurements, we can estimate the following transmissivities. Values in grey are calculated, not measured.

  Incident    Transmitted Reflected Sum
IM4 Forward 176 .39 0.22% 175 99.43% 175.39 99.65%
ROM LH1 .385 .0305 7.92% 0.361 93.77%  0.3915 101.69%
ROM RH4 .355 .025  7.04% 0.325 91.55% 0.35 98.59%
PRM 175 5.4 3.09% 169.6 96.91% 175 100.00%
IM4 Backwards 169.6 .038 0.22%        
LHO General
patrick.thomas@LIGO.ORG - posted 18:51, Thursday 28 March 2013 (5922)
plots of dust counts
Attached are plots of dust counts > .3 microns and > .5 microns in particles per cubic foot requested from 5 PM March 27 to 5 PM March 28. Also attached are plots of the modes to show when they were running/acquiring data.

Data was taken from h1nds1.
T0=13-03-28-00-00-00; Length=86400 (s)
1440.0 minutes of trend displayed
Non-image files attached to this report
H1 SEI
hugh.radkins@LIGO.ORG - posted 18:07, Thursday 28 March 2013 (5921)
BS WBSC2 IAS Alignment Status: X Y Z complete, moving to Pitch & Yaw
Occupy Mon AM506 (-2133.6x,-182.8y) at HI -82.9 Lz, BackSite LV-22 (-2133.6x,-22692y)
Nominal Turn: HAR 270-01'45" ZA 90-00'02".  Sited Baffle Target at BS at HAR 270-03'10" ZA 89-59'28" for 85" & 34" error.
Over 1931mm these angles give position errors 0.8mm -Y & 0.3mm +Z from nominal
BS position (-202.7x,-183.8y) yields distance from AM506 1930.9mm nominal.  EDM w/ -30mm prism offset shot 1.8617m to retro-reflector.  Retro-reflector measured to be 2.709"=68.8mm from optic face (FC).  1930.9-1.8617-68.8 = 0.4mm -X of nominal.  I am told this is within spec (percomm DCook.)
Of course to get it here we did a number of HEPI moves monitoring the Dial Indicators on the ends of the Support Tubes.  Based on the DIs and 'adding' to the Optical Table leveling results from 25 March, the 'level' of the Optical Table is still +-0.1mm so should be fine.  Would like to confirm with AutoLevel shots directly on the Optical Table, maybe tomorrow.
H1 SUS
arnaud.pele@LIGO.ORG - posted 17:25, Thursday 28 March 2013 - last comment - 11:32, Friday 29 March 2013(5920)
Beamsplitter transfer functions

Starting a round of transfer functions overnight on the beamsplitter.

Comments related to this report
arnaud.pele@LIGO.ORG - 11:32, Friday 29 March 2013 (5931)

see aLog 5927 for summary

LHO VE
kyle.ryan@LIGO.ORG - posted 16:37, Thursday 28 March 2013 (5919)
Site-wide 80K pump (Cryogenic pump, CPx) alarms
The numerous 80K pump alarms today (and tomorrow, this weekend?) are the result of my cracking open the LN2 "bypass" valves on the site dewar plumbing.  The motivation for doing this is to prepare for the upcoming extended power outage.  As such, there are now two flow paths for the LN2 to fill each 80K pump, one is via the nominal CDS PID-controlled valve and a second which "goes around" this valve and which has no external control.  A few days of tweaking should allow us to maintain the pump levels with only a minor contribution from the PID-controlled flow path.  This will guarantee that some LN2 is always flowing through the "transfer" line even when the PID-controlled valve is closed (as will be the case with the loss of instrument air during the outage).  Having a minimum flow will prevent the transfer line from warming up and will greatly facilitate manual adjustments to the pump levels during the outage.  
H1 CDS
david.barker@LIGO.ORG - posted 16:30, Thursday 28 March 2013 (5918)
Beam Splitter Suspension added to IOP software watchdog system

WP 3785. Modified h1iopsusb123 model to add the BS suspension to the software watchdog system. Restarted h1susb123 at 16:06. The h1iopseib2 model was already setup for this and did not need restarting.

So now if either ITMY or BS or both have tripped top OSEM channels, both SEI BSC1 and SEI BSC2 will be tripped if SUS B123 is not bypassed.

I created a new BSC1 and BSC2 WD MEDM screen and made the appropriate links from the top WD screen.

LHO General
michael.rodruck@LIGO.ORG - posted 16:12, Thursday 28 March 2013 (5917)
Ops summary
H1 SUS
arnaud.pele@LIGO.ORG - posted 15:54, Thursday 28 March 2013 (5908)
BSFM/QUAD opticalign sliders

After the recent update of the HLTS and HSTS opticalign sliders (see aLog 5866), I modified a few things for the alignment offsets in BS, ETMY and ITMY.

New sliders range
Optic DOF Range(urad) Ref document
BS Pitch +/-1529

T1100602-v2

Yaw +/-6386
QUAD M0-R0 Pitch +/-440 T110595-v2
Yaw +/-610
New OPTICALIGN gains
Optic DOF Gain (Cts/urad) Ref document
BS Pitch 4.714

aLog 5361

Yaw 4.268
QUAD M0-R0 Pitch 23.219 aLog 4730
Yaw 51.689

Details :

In order to change the sliders range I modified the OPTICALIGN adl files by opening it with medm in edit mode, and changed the limit of the sliders.

SUS_CUST_BSFM_M1_OPTICALIGN.adl located in /opt/rtcds/userapps/release/sus/common/medm/bsfm for BSFM
SUS_CUST_QUAD_${M0/R0}_OPTICALIGN.adl located in /opt/rtcds/userapps/release/sus/common/medm/quad for ETM/ITM

The files have been commited to the svn as well as the new safe.snap files

LHO General
bubba.gateley@LIGO.ORG - posted 15:43, Thursday 28 March 2013 (5916)
Apollo crew
We assisted Pablo with P-Cal fixtures today in the H-2 PSL enclosure and craned the dirty parts over the X arm for Michael Rodruck, and into the LEA on pallets. John and I cut the coupons out of the show and tell beam tube out at the weld shop, I will bend them next week at the Apollo shop. Viewports VPA2F1 &VPA2F4 were installed and torqued on HAM 1. Started installation of viewport G2 on BSC 2, will complete tomorrow. We wraped and transported 4 TMS Optical tables from EY to EX. We reajusted the lower limit on the EX crane so the hook and block do not contact the floor. We relocated IOT2 table from the east bay to the south bay near HAM 2 for Joe Gleason and Cheryl Vorvick and installed the viewport simulator for Cheryl.
H2 General
jodi.fauver@LIGO.ORG - posted 15:09, Thursday 28 March 2013 (5915)
3IFO NSF Storage Review Prep
I sealed up the two new HXTS that were placed in the meat locker yesterday. I also attached signage/drawings/ICS records to the five HXTS in the meat locker. I inventoried and separated MC Baffle parts this morning: small parts were placed in a tote and large parts were wrapped/attached to their shelf with plastic wrap and a few lengths of blue tamper-evident tape. I worked on AC and Elliptical Baffle parts this afternoon: there are two plastic wrapped and taped pallets on the floor level of Shelving Unit B in the West Bay containing these parts. I also applied signage to a HAM Shipping, HAM Storage, and BSC Storage Container for show-and-tell purposes.
H1 PSL
michael.rodruck@LIGO.ORG - posted 14:39, Thursday 28 March 2013 (5914)
PSL plots

For the 35W beam

Images attached to this report
Non-image files attached to this report
H1 SUS
arnaud.pele@LIGO.ORG - posted 17:52, Wednesday 27 March 2013 - last comment - 11:28, Friday 29 March 2013(5907)
Beamsplitter Transfer Functions

Starting a round of matlab transfer functions overnight for the beamsplitter.

Comments related to this report
arnaud.pele@LIGO.ORG - 11:28, Friday 29 March 2013 (5929)

see aLog 5927 for summary

H1 SUS
arnaud.pele@LIGO.ORG - posted 16:04, Monday 25 March 2013 - last comment - 11:31, Friday 29 March 2013(5882)
PRM/PR2/PR3/MC1/MC2/MC3 safe.snap update

Before the power outage of next week, new h1sus${mc1/mc2/mc3/prm/pr2/pr3}safe.snap files have been saved in /opt/rtcds/userapps/release/sus/h1/burtfiles.
It includes alignment offsets with the right values from aLog 5851 for PR3/PR2 and 5825 for MC1/MC2/MC3. It also includes the ODC recent update aLog 5809

The safe state has been defined as the following :

**alignment offsets off
**damping filters on
**master switch off

The snap files have been commited in the svn repository.

 

Comments related to this report
arnaud.pele@LIGO.ORG - 11:31, Friday 29 March 2013 (5930)


		
		
Displaying reports 79521-79540 of 85276.Go to page Start 3973 3974 3975 3976 3977 3978 3979 3980 3981 End