Displaying reports 80081-80100 of 83004.Go to page Start 4001 4002 4003 4004 4005 4006 4007 4008 4009 End
Reports until 11:46, Friday 01 June 2012
H1 FMP
jodi.fauver@LIGO.ORG - posted 11:46, Friday 01 June 2012 (3008)
BSC2-HAM4 ICC
BSC2 flooring was moved into the LVEA. The crew went into HAM4 and removed the dust barriers. BSC2 flooring was installed. (There was a slight delay caused by a missing nut.) The doors will go back on this afternoon.
H2 CDS
david.barker@LIGO.ORG - posted 08:41, Friday 01 June 2012 - last comment - 11:59, Friday 01 June 2012(3006)
h2susb78 (SUS FMY) crashed again
h2susb78 remains unstable. It crashed between 2am and 3am this morning. It was removed from the watchdog system yesterday, and did not trip SEI BSC8 this time. I will power cycle it, and it should not crash SUS ITMY since it is no longer part of the Dolphin fabric.
Comments related to this report
david.barker@LIGO.ORG - 11:59, Friday 01 June 2012 (3009)
CPU was replaced with another H2 frontend with the same card configuration. New machine was restarted at 11:30 today. h2boot was modified to take the new MAC address.
H2 CDS
david.barker@LIGO.ORG - posted 22:12, Thursday 31 May 2012 (3005)
Qlogic switch relocated from H2 EE building to MSR to support H1 DAQ
We relocated one of the two Qlogic fiber channel switches from the H2 EE building (where it was part of a redundant CDS-LDAS network) to its new location in the MSR. It will connect the new H1 DAQ to LDAS, allowing the publishing of H1 frames and distribution of H1 data via the NDS2 server. Dan is setting up the QFS solaris machine for h1fw0 (we currently only have h1fw1 operational). Jim is building up h1fw0 from its cloned state.
H2 CDS
david.barker@LIGO.ORG - posted 22:05, Thursday 31 May 2012 (3004)
H2 FMY disconnected from IOP watchdogs
While h2susb78 remains unstable, FMY has been removed from the IOP watchdog system. This required a code change with the h2iopseib8 model to disconnect the FMY signal from the IOP SEI BSC8 DACKILL part. All the models on h2seib8 were then restarted which included a new ISI model which also had FMY removed from its watchdog.
The frozen h2susb78 was powered down and its Dolphin IPC cable was disconnected before it was powered back. This will ensure that any possible future crashes and subsequent power cycles will not stop the ITMY model.
H2 SEI
jeffrey.garcia@LIGO.ORG - posted 21:43, Thursday 31 May 2012 (3003)
BSC 6 ISI measurements interrupted
There was an operator error this afternoon around 18:44 PST where a script being tested for damping was inadvertently started on the ETMY SUS.  The script was meant to switch off inputs to the damping filters but caused the user model and IOP watchdogs to trip.  The ISI DAC output has been interrupted, but a SUS ETMY measurement is slated to begin tonight.
LHO General
patrick.thomas@LIGO.ORG - posted 19:27, Thursday 31 May 2012 (3002)
plots of dust counts
Attached are plots of dust counts > .5 microns. The dust monitor at location 15 in the LVEA has been turned off.
Non-image files attached to this report
LHO General
jeffrey.garcia@LIGO.ORG - posted 16:46, Thursday 31 May 2012 (3001)
Ops Day Summary
The day's main activities:
End-Y BSC 6 dome cover and door installation.
DAQ reboots by CDS
Simulink model reboots on the BSC 8 chamber models (FMY, ITMY, SEI) by CDS
Removal of FMY from the IOP watchdog monitors
H2 SEI
vincent.lhuillier@LIGO.ORG - posted 16:44, Thursday 31 May 2012 (3000)
Connection between the FMY watchdogs and the ISI temporary bypassed

Due to recurrent crashes of h2susb78, the connection between the FMY watchdogs and the ISI watchdogs is temporary bypassed. This connection will be reestablished as soon as h2susb78 is stable.

H1 SEI
corey.gray@LIGO.ORG - posted 16:19, Thursday 31 May 2012 (2999)
HAM ISI: #5 Can Moved To Staging Receiving, #6 Horiz L4C Testing, #7 Stage-0 Work

(corey, eric, jim, mitch)

#5

Shuffled a few pallets and now this box is in Staging Receiving ready to be moved out.

#6

Received Horiz L4Cs, put them on Optics Table and Hugo will test them. (attached is set-up photo)

#7

Stage-0 is on Assy Stand and helicoiling will be complete this afternoon

Images attached to this report
H2 SUS
jeffrey.garcia@LIGO.ORG - posted 15:55, Thursday 31 May 2012 - last comment - 10:43, Friday 01 June 2012(2992)
ITMY Optical Lever signals added to QUAD model
D. Barker, J. Garcia


The optical lever photodiode signals were added to the H2 SUS ITMY Simulink model ('h2susitmy.mdl') at the "L3" stage.  The signals are routed to the second ADC on 'h2susb478', which is labeled "ADC_1" in the Simulink model.  The "h2susitmy.mdl" file was modified to incorporate the four quadrant signals from the ITMY Optical Lever photodiode into the "QUAD_MASTER.mdl" library part. 

In the 'h2susitmy.mdl' file, the four quadrant signals are on the ADC_1 channels: 
UL = ADC_1_1
UR = ADC_1_3
LL = ADC_1_2
LR = ADC_1_4

NOTE: this configuration will hold true for the One Arm Test and does NOT reflect the latest H2 SUS ITM, BS, FM wiring diagram, D1001725-v10.  

-------

In addition to the above changes to the "custom" top level Simulink model ('h2susitmy'), the "QUAD_MASTER.mdl" generic library part was modified for several bug fixes.  Inside the 'QUAD_MASTER' diagram, the editing was performed mainly at the 'QUAD_MASTER/QUAD/L3/OPLEVWIT/' level.  Initially, SUM, Pitch, and Yaw outputs were test points without filter modules.  However, this prevented the DAQ from accepting these channels and writing them to frames, unbeknowst to CDS.  These library parts were replaced with actual filter modules instead of test points.  This resolved the ability to write these channels to frames.  

The Optical Lever photodiode channels being written to frames are:
H2:SUS-ITMY_L3_OPLEVWIT_P_OUT
H2:SUS-ITMY_L3_OPLEVWIT_Y_OUT
H2:SUS-ITMY_L3_OPLEVWIT_SUM_OUT

The 'h2susitmy' model has now been recompiled and installed on 'h2susb478'.  


Comments related to this report
jeffrey.garcia@LIGO.ORG - 10:43, Friday 01 June 2012 (3007)
In addition to the above changes to the Simulink model, there were two other modifications.  The inter-computer communication library part (PCI) was removed, because the Optical Lever signals are now fed directly to the H2 SUS ITMY machine 'h2susb478'.  Secondly, the input for the Laser Power monitor was grounded.  Currently, the laser power is not directly fed to the ADC on 'h2susb478'.  
H1 FMP
jodi.fauver@LIGO.ORG - posted 15:02, Thursday 31 May 2012 (2998)
BSC1 ICC
The "short" cleanroom was moved from BSC8 to BSC1. Terry S. and crew will do first cleaning tomorrow. 
H1 FMP
jodi.fauver@LIGO.ORG - posted 14:57, Thursday 31 May 2012 (2997)
BSC2-HAM4 ICC
In HAM4, the hand-brushing around the fins and first vacuum were completed this morning. This afternoon, wipe down and second vacuum were completed. Inspection should be completed by the end of the day.

Flooring for BSC2 was brought from the VPW to the LEA. It will be installed after the dust barrier is removed from between BSC2 and HAM4. That activity should take place early tomorrow and then the door can be returned to HAM4.
H2 TCS
cheryl.vorvick@LIGO.ORG - posted 14:56, Thursday 31 May 2012 (2996)
BSC6 H2 ETMY Ring Heater had some issues, which are now resolved:
- Cheryl, Travis


The ring heater in BSC6 was installed on the quad with the correct screws, but with nuts instead of the nut blocks SUS made for the installation.  This caused an issue when trying to close the RH around the ETM because one screw would not loosen, so would not allow one end of the lower segment of the RH to close.

The solution was to modify a wrench, to maneuver between the main and reaction chains, to hold the nut while adjusting the screw and moving the RH into place.

The modified wrench worked well, and allowed us to loosen and tighten the screws as needed to set the alignment of the RH. 

The upper RH segment is aligned to the scribe marks, and the lower RH segment is aligned to the upper segment.  Uncharacteristically, I did not bring a camera, so there are no pictures of the screws and scribe lines on the upper segment.

One of the flathead screws was loose on the upper RH segment.  This is odd, and a little disturbing, because we had this issue before installation on the quad, and chalked it up to an oversight, then made doubly sure all the flat head screws were installed correctly.  That means that either we (me, GregG, ThomasV, back in December 2011) missed one again, OR the screw is somehow backing itself out.

I tightened the flathead screw, and the feel of the screw was comparable to the feel of the screw when I assembled the RH, so all indications are that Macor threads holding the flathead screw are OK.  A picture of the exact screw I worked on, before it was tightened, and before the RH was closed, is attached.

Images attached to this report
H2 CDS
david.barker@LIGO.ORG - posted 12:27, Thursday 31 May 2012 (2993)
Deja Vue all over again, FMY down once more
h2susb78 (SUS FMY) crashed for the third time last night at 20 mins to midnight (so it is unlikely to be human activity). We are working on taking FMY out of the IOP and model DACKILL watchdogs for SEI BSC8 until we can fix this stability problem.
H2 SUS
jeffrey.garcia@LIGO.ORG - posted 10:37, Thursday 31 May 2012 - last comment - 16:14, Friday 01 June 2012(2991)
H2 SUS ITMY, 2012-05-29 Measurements
J. Garcia, S. Steplewski

We made a set of TOP transfer function measurements on ITMY Tuesday.  This was the first time we tested ITMY since this chamber was pumped down.  Measurements were clean and the results match up reasonably well with the (fiber) model - although this is a wire rehang after the fiber break.

The .mat files are located in:
~/SusSVN/trunk/QUAD/H2/ITMY/SAGM0/Data/
~/SusSVN/trunk/QUAD/H2/ITMY/SAGR0/Data/

The .pdf files are located in:

~/SusSVN/trunk/QUAD/H2/ITMY/SAGM0/Results
~/SusSVN/trunk/QUAD/H2/ITMY/SAGR0/Results
Non-image files attached to this report
Comments related to this report
szymon.steplewski@LIGO.ORG - 14:44, Thursday 31 May 2012 (2995)
Attached is another plot that shows the ITMY TOP transfer function taken In-Vacuum compared to that taken In-Air.  Aslo plotted are the wire (for M0) and thincp (for R0) models for reference.
Non-image files attached to this comment
szymon.steplewski@LIGO.ORG - 16:14, Friday 01 June 2012 (3017)
Mark Barton, Szymon Steplewski 

We changed the parameters in the Mathematica model for the QUAD suspension for ITMY to reflect the fact that the glass test mass is suspended from steel wires after the fiber break.  These changes have resulted in noticeably better agreement between the measurements and model for several degrees of freedom.

The TOP Pitch to Pitch mode around 1.4 Hz has shifted to higher frequency (from about 1.31 Hz to 1.44 Hz), while the Pitch mode near 0.56 Hz is practically unchanged, which is where we want it according to the design requirements.  The TOP Longitudinal to Longitudinal plot also shows some nice improvement in the mode around ~1.5 Hz, which matches up a little more with the "wirerehang" model now.

There is now a new wirerehang Mathematica model in the SUS SVN under

~/trunk/Common/MathematicaModels/QuadLite2Lateral/mark.barton/20120601TMproductionTMrehang/

which was built from elements of the fiber model under

~/trunk/Common/MathematicaModels/QuadLite2Lateral/mark.barton/20120601TMproductionTM/

We have added 'wirerehang' to the list of case models for plotting in Matlab, so the different cases are now:

1.  'wire'
2.  'fiber'
3.  'erm'
4.  'thincp'
5.  'wirerehang'
Non-image files attached to this comment
H2 SUS
betsy.weaver@LIGO.ORG - posted 18:47, Wednesday 30 May 2012 - last comment - 22:02, Wednesday 30 May 2012(2989)
BSC6 SUS/TMS/IAS Closeout

(from Betsy on behalf of Keita, Cheryl, Travis, Gerardo, Jason)

This afternoon:

Comments related to this report
gerardo.moreno@LIGO.ORG - 22:02, Wednesday 30 May 2012 (2990)

ETMY Optical Lever Beams Identified.

We found 4 bright beams coming out of the viewport, two pairs belonging to ETMY and the other two from ERM. The two upper spots on the picture are from the ERM, the lower ones from ETMY. This was confirmed by moving the ERM, when doing so the two upper spots moved, while the other two remain still. The beam from the front surface of ETMY is the lowest spot on the photo.

Images attached to this comment
LHO General
patrick.thomas@LIGO.ORG - posted 17:25, Wednesday 30 May 2012 (2988)
plots of dust counts
Attached are plots of dust counts > .5 microns.
Non-image files attached to this report
Displaying reports 80081-80100 of 83004.Go to page Start 4001 4002 4003 4004 4005 4006 4007 4008 4009 End